IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Banner Lakes At Summerset State Park  Date: 4/30/2020  Project No.  
  Flood Damage Repairs  County:   WARREN  Time: 3:00 p.m.  20-05-91-03

 

 
1
2
3
Estimated Cost: $9,400.00
Contractor: 
Sterk Excavating IncHaworth Land ConstructionKupka Excavating & Trucking
Funding Source: 100% Executive Council, 117 180th Ave
12981 Quaker St
2998 W Ave
Otley IA  50214Indianola IA  50125Elberon IA  52225
Plan Sets Requested: 0
Quantities
641416011051524947476414854231
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
13" Minus Stone18Tons$34.00$612.00 $25.00$450.00 $27.00$486.00 
2Macadam Stone54Tons$31.50$1,701.00 $28.00$1,512.00 $33.00$1,782.00 
3Class "E" Riprap36Tons$50.00$1,800.00 $45.00$1,620.00 $47.00$1,692.00 
4Ditch Cleanout1L.S.$1,500.00$1,500.00 $3,668.00$3,668.00 $1,300.00$1,300.00 
5Fill hole in front of 2 piers with 3" minus6Tons$84.00$504.00 $25.00$150.00 $27.00$162.00 
6Mobilization1L.S.$600.00$600.00 $1,000.00$1,000.00 $3,625.00$3,625.00 
7Replace Deck Boards4Each$125.00$500.00 $25.00$100.00 $30.00$120.00 
      $7,217.00  $8,500.00  $9,167.00 
 
 
4
5
6
Estimated Cost: $9,400.00
Contractor: 
Vanderpool Construction, Inc.Berkey Homebuilders dba Concrete ProfessionalsIron Hill Construction LLC
Funding Source: 100% Executive Council, 1100 N 14th St

PO Box 7
2800 University Ave, Ste 128
Indianola IA  50125Altoona IA  50009West Des Moines IA  50266
Plan Sets Requested: 0
Quantities
515961468251596731365157207163
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
13" Minus Stone18Tons$35.00$630.00 $34.50$621.00 $25.00$450.00 
2Macadam Stone54Tons$38.00$2,052.00 $43.50$2,349.00 $30.00$1,620.00 
3Class "E" Riprap36Tons$53.00$1,908.00 $69.88$2,515.68 $52.00$1,872.00 
4Ditch Cleanout1L.S.$2,800.00$2,800.00 $2,970.00$2,970.00 $2,470.00$2,470.00 
5Fill hole in front of 2 piers with 3" minus6Tons$55.00$330.00 $100.00$600.00 $61.00$366.00 
6Mobilization1L.S.$1,015.00$1,015.00 $1,100.00$1,100.00 $9,857.00$9,857.00 
7Replace Deck Boards4Each$125.00$500.00 $187.50$750.00 $72.00$288.00 
      $9,235.00  $10,905.68  $16,923.00 
 



 

3/28/2024