Bids For: | Location: | Rogers WPA & Center Lake WMA | Date: 2/25/2021 | Project No. |
Water Control Structure Replacements | County: | DICKINSON | Time: 3:00 p.m. | 20-01-30-19 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $56,000.00 | Contractor: | McCarty Custom Inc | Valley Contracting Inc | Diamond Concrete and Construction, Inc | |||||||||
Funding Source: 50% Federal-FEMA 1, 50% Federal-Other, | 1760 440th St | 1850 Hwy 4 | 2360 15th St | ||||||||||
Linn Grove IA 51033 | Estherville IA 51334 | Spirit Lake IA 51360 | |||||||||||
Plan Sets Requested: 0 | Quantities | 7122602773 | 7123624969 | 7123369062 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Rogers - Mobilization | 1 | L.S. | $3,000.00 | $3,000.00 | $1,600.00 | $1,600.00 | $500.00 | $500.00 | ||||
2 | Rogers - Structure Removal | 1 | L.S. | $2,500.00 | $2,500.00 | $2,600.00 | $2,600.00 | $1,500.00 | $1,500.00 | ||||
3 | Rogers - Water Control Structure (Complete) | 1 | L.S. | $7,500.00 | $7,500.00 | $11,600.00 | $11,600.00 | $11,750.00 | $11,750.00 | ||||
4 | Rogers - 24" CMP w/ Bands | 20 | L.F. | $48.00 | $960.00 | $110.00 | $2,200.00 | $150.00 | $3,000.00 | ||||
5 | Rogers - 4'x4' Antiseep Collar | 1 | Each | $100.00 | $100.00 | $777.00 | $777.00 | $775.00 | $775.00 | ||||
6 | Rogers - Stop Logs | 7 | Each | $50.00 | $350.00 | $35.00 | $245.00 | $35.00 | $245.00 | ||||
7 | Rogers - 1" Minus Granular Bedding | 4 | Tons | $80.00 | $320.00 | $56.00 | $224.00 | $60.00 | $240.00 | ||||
8 | Center Lake - Mobilization | 1 | L.S. | $3,500.00 | $3,500.00 | $2,600.00 | $2,600.00 | $800.00 | $800.00 | ||||
9 | Center Lake - Structure Removal | 1 | L.S. | $2,500.00 | $2,500.00 | $2,600.00 | $2,600.00 | $2,000.00 | $2,000.00 | ||||
10 | Center Lake - Water Control Structure (Complete) | 1 | L.S. | $11,100.00 | $11,100.00 | $14,770.00 | $14,770.00 | $17,500.00 | $17,500.00 | ||||
11 | Center Lake - 57"x38" Arch CMP w/ Bands | 44 | L.F. | $150.00 | $6,600.00 | $200.00 | $8,800.00 | $254.00 | $11,176.00 | ||||
12 | Center Lake - Imported Fill | 10 | C.Y. | $75.00 | $750.00 | $20.00 | $200.00 | $21.50 | $215.00 | ||||
13 | Center Lake - 7'x5' Antiseep Collar | 2 | Each | $1,200.00 | $2,400.00 | $1,770.00 | $3,540.00 | $1,650.00 | $3,300.00 | ||||
14 | Center Lake - Class "D" Rip Rap | 10 | Tons | $65.00 | $650.00 | $40.00 | $400.00 | $75.00 | $750.00 | ||||
15 | Center Lake - Stop Logs | 15 | Each | $50.00 | $750.00 | $35.00 | $525.00 | $35.00 | $525.00 | ||||
16 | Center Lake - 1" Minus Granular Bedding | 10 | Tons | $60.00 | $600.00 | $50.00 | $500.00 | $80.00 | $800.00 | ||||
17 | Center lake - Seeding | 1 | L.S. | $2,500.00 | $2,500.00 | $1,200.00 | $1,200.00 | $1,500.00 | $1,500.00 | ||||
18 | Center Lake - Type 1 Rolled Erosion Control Matting (RECP) | 250 | S.Y. | $2.00 | $500.00 | $5.00 | $1,250.00 | $5.00 | $1,250.00 | ||||
$46,580.00 | $55,631.00 | $57,826.00 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $56,000.00 | Contractor: | BLAC Construction LLC | |||||||||||
Funding Source: 50% Federal-FEMA 1, 50% Federal-Other, | 1281 Miller Rd | ||||||||||||
Sherburn MN 56171 | |||||||||||||
Plan Sets Requested: 0 | Quantities | 5072360128 | |||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Rogers - Mobilization | 1 | L.S. | $350.00 | $350.00 | $0.00 | $0.00 | ||||||
2 | Rogers - Structure Removal | 1 | L.S. | $2,470.00 | $2,470.00 | $0.00 | $0.00 | ||||||
3 | Rogers - Water Control Structure (Complete) | 1 | L.S. | $13,296.00 | $13,296.00 | $0.00 | $0.00 | ||||||
4 | Rogers - 24" CMP w/ Bands | 20 | L.F. | $107.75 | $2,155.00 | $0.00 | $0.00 | ||||||
5 | Rogers - 4'x4' Antiseep Collar | 1 | Each | $615.00 | $615.00 | $0.00 | $0.00 | ||||||
6 | Rogers - Stop Logs | 7 | Each | $50.71 | $354.97 | $0.00 | $0.00 | ||||||
7 | Rogers - 1" Minus Granular Bedding | 4 | Tons | $44.00 | $176.00 | $0.00 | $0.00 | ||||||
8 | Center Lake - Mobilization | 1 | L.S. | $350.00 | $350.00 | $0.00 | $0.00 | ||||||
9 | Center Lake - Structure Removal | 1 | L.S. | $1,490.00 | $1,490.00 | $0.00 | $0.00 | ||||||
10 | Center Lake - Water Control Structure (Complete) | 1 | L.S. | $17,996.60 | $17,996.60 | $0.00 | $0.00 | ||||||
11 | Center Lake - 57"x38" Arch CMP w/ Bands | 44 | L.F. | $386.09 | $16,987.96 | $0.00 | $0.00 | ||||||
12 | Center Lake - Imported Fill | 10 | C.Y. | $24.70 | $247.00 | $0.00 | $0.00 | ||||||
13 | Center Lake - 7'x5' Antiseep Collar | 2 | Each | $1,490.00 | $2,980.00 | $0.00 | $0.00 | ||||||
14 | Center Lake - Class "D" Rip Rap | 10 | Tons | $96.00 | $960.00 | $0.00 | $0.00 | ||||||
15 | Center Lake - Stop Logs | 15 | Each | $50.71 | $760.65 | $0.00 | $0.00 | ||||||
16 | Center Lake - 1" Minus Granular Bedding | 10 | Tons | $44.00 | $440.00 | $0.00 | $0.00 | ||||||
17 | Center lake - Seeding | 1 | L.S. | $215.00 | $215.00 | $0.00 | $0.00 | ||||||
18 | Center Lake - Type 1 Rolled Erosion Control Matting (RECP) | 250 | S.Y. | $0.56 | $140.00 | $0.00 | $0.00 | ||||||
$61,984.18 | $0.00 | $0.00 | |||||||||||