IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Backbone State Park  Date: 11/17/2022  Project No.  
  Cabin and Museum Road Reconstruction  County:   DELAWARE  Time: 11:00 a.m.  21-03-28-02

 

 
1
2
3
Estimated Cost: $1,500,000.00
Contractor: 
Wicks Construction IncTschiggfrie ExcavatingMidwest Concrete Inc
Funding Source: 96% Park & Institutional Road Fund, 4% Infrastructure, PO Box 428
425 Julien Dubuque Dr
9835 Midwest Lane
Decorah IA  52101Dubuque IA  52003Peosta IA  52068
Plan Sets Requested: 3
Quantities
563-382-2325563-557-7450563-845-0947
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Clearing and Grubbing6.8Acres$7,500.00$51,000.00 $13,000.00$88,400.00 $4,550.00$30,940.00 
2Removal of Existing Pavement and Base7799S.Y.$4.25$33,145.75 $7.30$56,932.70 $3.00$23,397.00 
3Removal of Existing Sidewalk and Base31S.Y.$10.00$310.00 $7.00$217.00 $53.00$1,643.00 
4Removal of Existing Parking Lot and Base148S.Y.$10.00$1,480.00 $7.20$1,065.60 $8.00$1,184.00 
5Removal of Intake1Each$500.00$500.00 $270.00$270.00 $619.00$619.00 
6Removal of Sanitary Sewer Manhole6Each$500.00$3,000.00 $1,100.00$6,600.00 $1,547.00$9,282.00 
7Removal of Existing Reinforced Concrete Pipe < 36"63L.F.$30.00$1,890.00 $7.90$497.70 $20.00$1,260.00 
8Removal of Existing Corrugated Metal Pipe < 36"65L.F.$25.00$1,625.00 $7.90$513.50 $20.00$1,300.00 
9Removal of Headwall1L.S.$1,000.00$1,000.00 $660.00$660.00 $1,238.00$1,238.00 
10Removal of Existing Gate1L.S.$200.00$200.00 $370.00$370.00 $619.00$619.00 
11Manhole, Sanitary Sewer, SW-303, 48"6Each$6,800.00$40,800.00 $7,000.00$42,000.00 $6,527.00$39,162.00 
12Manhole Adjustment, Minor1Each$1,500.00$1,500.00 $1,500.00$1,500.00 $1,774.00$1,774.00 
13Intake, SW-5132Each$7,500.00$15,000.00 $8,000.00$16,000.00 $3,891.00$7,782.00 
14Intake Investigation2Each$750.00$1,500.00 $450.00$900.00 $901.00$1,802.00 
15Tile Investigation50L.F.$25.00$1,250.00 $12.00$600.00 $21.00$1,050.00 
16Intake Grate1Each$2,500.00$2,500.00 $490.00$490.00 $1,655.00$1,655.00 
17Roadway Pavement, 7" PCC10725S.Y.$46.85$502,466.25 $40.20$431,145.00 $47.70$511,582.50 
18Parking Lot Pavement, 7" PCC606S.Y.$57.50$34,845.00 $53.00$32,118.00 $56.00$33,936.00 
19Sidewalk, 6" PCC26S.Y.$50.00$1,300.00 $65.00$1,690.00 $93.00$2,418.00 
20Special Backfill4209Tons$18.00$75,762.00 $21.00$88,389.00 $22.00$92,598.00 
21Granular Shoulder, Type A606Tons$20.00$12,120.00 $24.00$14,544.00 $23.00$13,938.00 
22Reinforced Concrete Pipe, 18"72L.F.$80.00$5,760.00 $83.00$5,976.00 $113.00$8,136.00 
23Reinforced Concrete Pipe, 24"40L.F.$125.00$5,000.00 $110.00$4,400.00 $142.00$5,680.00 
24Reinforced Concrete Pipe, 30"90L.F.$150.00$13,500.00 $130.00$11,700.00 $156.00$14,040.00 
25Apron, Conc, 18"1Each$1,200.00$1,200.00 $1,500.00$1,500.00 $1,882.00$1,882.00 
26Apron, Conc, 30"1Each$1,500.00$1,500.00 $1,500.00$1,500.00 $2,607.00$2,607.00 
27Footing for Concrete Pipe Apron2Each$1,300.00$2,600.00 $1,400.00$2,800.00 $1,824.00$3,648.00 
28Pipe Apron Guard, 18"1Each$1,000.00$1,000.00 $1,300.00$1,300.00 $1,923.00$1,923.00 
29Pipe Apron Guard, 24"1Each$1,500.00$1,500.00 $1,600.00$1,600.00 $2,258.00$2,258.00 
30Pipe Apron Guard, 30"1Each$2,000.00$2,000.00 $1,900.00$1,900.00 $2,567.00$2,567.00 
31Erosion Control Mat, RECP Type 2.C24S.Y.$29.00$696.00 $17.00$408.00 $23.00$552.00 
32Excavation, Class 10, Roadway and Borrow869C.Y.$10.00$8,690.00 $12.00$10,428.00 $15.00$13,035.00 
33Embankment-In-Place4059C.Y.$12.50$50,737.50 $18.00$73,062.00 $20.00$81,180.00 
34Revetment, Class E25Tons$40.00$1,000.00 $43.00$1,075.00 $63.00$1,575.00 
35Painted Pavement Mark, High-Build Waterborne1L.S.$3,800.00$3,800.00 $4,200.00$4,200.00 $876.00$876.00 
36Precast Concrete Parking Wheel Stops16Each$155.00$2,480.00 $180.00$2,880.00 $160.00$2,560.00 
37Detectable Warning Panel40S.F.$50.00$2,000.00 $44.00$1,760.00 $39.00$1,560.00 
38Seeding, Fertilizing, and Mulching6.8Acres$2,750.00$18,700.00 $2,600.00$17,680.00 $3,090.00$21,012.00 
39Filter Sock, 8"9310L.F.$1.95$18,154.50 $2.80$26,068.00 $3.00$27,930.00 
40Signing10Each$450.00$4,500.00 $280.00$2,800.00 $392.00$3,920.00 
41NPDES General Permit #2 & SWPPP1Each$3,750.00$3,750.00 $2,800.00$2,800.00 $6,180.00$6,180.00 
42Construction Staking1L.S.$23,900.00$23,900.00 $15,200.00$15,200.00 $16,146.00$16,146.00 
43Traffic Control1L.S.$3,400.00$3,400.00 $3,700.00$3,700.00 $1,288.00$1,288.00 
44Mobilization1L.S.$50,000.00$50,000.00 $75,100.00$75,100.00 $95,000.00$95,000.00 
45Bollard4Each$500.00$2,000.00 $710.00$2,840.00 $830.00$3,320.00 
      $1,011,062.00  $1,057,579.50  $1,098,054.50 
 
4
5
6
Estimated Cost: $1,500,000.00
Contractor: 
Rays Excavating LLCEastern Iowa Excavating & Concrete LLCBoomerang Corp of Iowa
Funding Source: 96% Park & Institutional Road Fund, 4% Infrastructure, 404 E Union St
121 Nixon St SE
13225 Circle Drive Suite A
PO Box 227
Edgewood IA  52042Cascade IA  52033Anamosa IA  52205
Plan Sets Requested: 3
Quantities
563-928-7290563-852-5120319-462-4435
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Clearing and Grubbing6.8Acres$9,500.00$64,600.00 $7,950.00$54,060.00 $10,000.00$68,000.00 
2Removal of Existing Pavement and Base7799S.Y.$8.50$66,291.50 $12.85$100,217.15 $5.00$38,995.00 
3Removal of Existing Sidewalk and Base31S.Y.$10.00$310.00 $26.00$806.00 $15.00$465.00 
4Removal of Existing Parking Lot and Base148S.Y.$10.00$1,480.00 $16.00$2,368.00 $9.00$1,332.00 
5Removal of Intake1Each$1,500.00$1,500.00 $855.00$855.00 $1,000.00$1,000.00 
6Removal of Sanitary Sewer Manhole6Each$1,500.00$9,000.00 $735.00$4,410.00 $1,000.00$6,000.00 
7Removal of Existing Reinforced Concrete Pipe < 36"63L.F.$20.00$1,260.00 $15.25$960.75 $20.00$1,260.00 
8Removal of Existing Corrugated Metal Pipe < 36"65L.F.$20.00$1,300.00 $18.00$1,170.00 $10.00$650.00 
9Removal of Headwall1L.S.$1,500.00$1,500.00 $750.00$750.00 $1,000.00$1,000.00 
10Removal of Existing Gate1L.S.$1,500.00$1,500.00 $315.00$315.00 $1,000.00$1,000.00 
11Manhole, Sanitary Sewer, SW-303, 48"6Each$800.00$4,800.00 $5,900.00$35,400.00 $8,000.00$48,000.00 
12Manhole Adjustment, Minor1Each$1,500.00$1,500.00 $1,385.00$1,385.00 $1,500.00$1,500.00 
13Intake, SW-5132Each$8,500.00$17,000.00 $3,650.00$7,300.00 $7,000.00$14,000.00 
14Intake Investigation2Each$1,500.00$3,000.00 $975.00$1,950.00 $1,000.00$2,000.00 
15Tile Investigation50L.F.$25.00$1,250.00 $47.25$2,362.50 $30.00$1,500.00 
16Intake Grate1Each$2,500.00$2,500.00 $540.00$540.00 $1,500.00$1,500.00 
17Roadway Pavement, 7" PCC10725S.Y.$48.50$520,162.50 $43.15$462,783.75 $51.00$546,975.00 
18Parking Lot Pavement, 7" PCC606S.Y.$62.00$37,572.00 $52.00$31,512.00 $67.00$40,602.00 
19Sidewalk, 6" PCC26S.Y.$225.00$5,850.00 $72.75$1,891.50 $77.00$2,002.00 
20Special Backfill4209Tons$22.00$92,598.00 $21.25$89,441.25 $20.00$84,180.00 
21Granular Shoulder, Type A606Tons$22.00$13,332.00 $26.25$15,907.50 $25.00$15,150.00 
22Reinforced Concrete Pipe, 18"72L.F.$71.80$5,169.60 $84.25$6,066.00 $95.00$6,840.00 
23Reinforced Concrete Pipe, 24"40L.F.$92.20$3,688.00 $102.25$4,090.00 $125.00$5,000.00 
24Reinforced Concrete Pipe, 30"90L.F.$152.80$13,752.00 $134.85$12,136.50 $140.00$12,600.00 
25Apron, Conc, 18"1Each$1,300.00$1,300.00 $1,500.00$1,500.00 $2,500.00$2,500.00 
26Apron, Conc, 30"1Each$2,500.00$2,500.00 $2,185.00$2,185.00 $3,000.00$3,000.00 
27Footing for Concrete Pipe Apron2Each$1,350.00$2,700.00 $750.00$1,500.00 $400.00$800.00 
28Pipe Apron Guard, 18"1Each$1,300.00$1,300.00 $1,575.00$1,575.00 $750.00$750.00 
29Pipe Apron Guard, 24"1Each$1,850.00$1,850.00 $1,950.00$1,950.00 $950.00$950.00 
30Pipe Apron Guard, 30"1Each$2,500.00$2,500.00 $2,315.00$2,315.00 $1,050.00$1,050.00 
31Erosion Control Mat, RECP Type 2.C24S.Y.$24.00$576.00 $46.75$1,122.00 $54.00$1,296.00 
32Excavation, Class 10, Roadway and Borrow869C.Y.$12.50$10,862.50 $30.50$26,504.50 $7.00$6,083.00 
33Embankment-In-Place4059C.Y.$13.00$52,767.00 $23.35$94,777.65 $30.00$121,770.00 
34Revetment, Class E25Tons$50.00$1,250.00 $43.85$1,096.25 $90.00$2,250.00 
35Painted Pavement Mark, High-Build Waterborne1L.S.$1,000.00$1,000.00 $4,100.00$4,100.00 $900.00$900.00 
36Precast Concrete Parking Wheel Stops16Each$200.00$3,200.00 $165.00$2,640.00 $160.00$2,560.00 
37Detectable Warning Panel40S.F.$60.00$2,400.00 $31.25$1,250.00 $40.00$1,600.00 
38Seeding, Fertilizing, and Mulching6.8Acres$3,000.00$20,400.00 $4,500.00$30,600.00 $2,500.00$17,000.00 
39Filter Sock, 8"9310L.F.$4.00$37,240.00 $3.25$30,257.50 $2.50$23,275.00 
40Signing10Each$450.00$4,500.00 $265.00$2,650.00 $400.00$4,000.00 
41NPDES General Permit #2 & SWPPP1Each$4,000.00$4,000.00 $2,500.00$2,500.00 $3,000.00$3,000.00 
42Construction Staking1L.S.$17,500.00$17,500.00 $14,750.00$14,750.00 $15,000.00$15,000.00 
43Traffic Control1L.S.$1,500.00$1,500.00 $3,850.00$3,850.00 $3,200.00$3,200.00 
44Mobilization1L.S.$70,000.00$70,000.00 $62,000.00$62,000.00 $21,000.00$21,000.00 
45Bollard4Each$1,200.00$4,800.00 $325.00$1,300.00 $1,100.00$4,400.00 
      $1,115,061.10  $1,129,100.80  $1,137,935.00 
 
7
8
9
Estimated Cost: $1,500,000.00
Contractor: 
E & F Paving LLCC J Moyna & Sons LLC
Funding Source: 96% Park & Institutional Road Fund, 4% Infrastructure, 714 31st Ave SW
24412 Hwy 13

Cedar Rapids IA  52404Elkader IA  52043  
Plan Sets Requested: 3
Quantities
319-338-3498563-245-1442
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Clearing and Grubbing6.8Acres$9,500.00$64,600.00 $10,000.00$68,000.00 $0.00 
2Removal of Existing Pavement and Base7799S.Y.$8.50$66,291.50 $21.60$168,458.40 $0.00 
3Removal of Existing Sidewalk and Base31S.Y.$10.00$310.00 $60.00$1,860.00 $0.00 
4Removal of Existing Parking Lot and Base148S.Y.$10.00$1,480.00 $30.00$4,440.00 $0.00 
5Removal of Intake1Each$1,500.00$1,500.00 $720.00$720.00 $0.00 
6Removal of Sanitary Sewer Manhole6Each$1,500.00$9,000.00 $720.00$4,320.00 $0.00 
7Removal of Existing Reinforced Concrete Pipe < 36"63L.F.$20.00$1,260.00 $23.00$1,449.00 $0.00 
8Removal of Existing Corrugated Metal Pipe < 36"65L.F.$20.00$1,300.00 $10.00$650.00 $0.00 
9Removal of Headwall1L.S.$1,500.00$1,500.00 $8,500.00$8,500.00 $0.00 
10Removal of Existing Gate1L.S.$1,500.00$1,500.00 $1,500.00$1,500.00 $0.00 
11Manhole, Sanitary Sewer, SW-303, 48"6Each$800.00$4,800.00 $7,000.00$42,000.00 $0.00 
12Manhole Adjustment, Minor1Each$1,500.00$1,500.00 $2,200.00$2,200.00 $0.00 
13Intake, SW-5132Each$8,500.00$17,000.00 $6,400.00$12,800.00 $0.00 
14Intake Investigation2Each$1,500.00$3,000.00 $1,800.00$3,600.00 $0.00 
15Tile Investigation50L.F.$25.00$1,250.00 $68.00$3,400.00 $0.00 
16Intake Grate1Each$2,500.00$2,500.00 $2,000.00$2,000.00 $0.00 
17Roadway Pavement, 7" PCC10725S.Y.$47.75$512,118.75 $47.75$512,118.75 $0.00 
18Parking Lot Pavement, 7" PCC606S.Y.$72.50$43,935.00 $72.50$43,935.00 $0.00 
19Sidewalk, 6" PCC26S.Y.$81.00$2,106.00 $81.00$2,106.00 $0.00 
20Special Backfill4209Tons$22.00$92,598.00 $30.50$128,374.50 $0.00 
21Granular Shoulder, Type A606Tons$22.00$13,332.00 $36.00$21,816.00 $0.00 
22Reinforced Concrete Pipe, 18"72L.F.$71.80$5,169.60 $160.00$11,520.00 $0.00 
23Reinforced Concrete Pipe, 24"40L.F.$92.20$3,688.00 $195.00$7,800.00 $0.00 
24Reinforced Concrete Pipe, 30"90L.F.$152.80$13,752.00 $240.00$21,600.00 $0.00 
25Apron, Conc, 18"1Each$1,300.00$1,300.00 $2,100.00$2,100.00 $0.00 
26Apron, Conc, 30"1Each$2,500.00$2,500.00 $4,700.00$4,700.00 $0.00 
27Footing for Concrete Pipe Apron2Each$1,350.00$2,700.00 $1,375.00$2,750.00 $0.00 
28Pipe Apron Guard, 18"1Each$1,300.00$1,300.00 $1,550.00$1,550.00 $0.00 
29Pipe Apron Guard, 24"1Each$1,850.00$1,850.00 $1,950.00$1,950.00 $0.00 
30Pipe Apron Guard, 30"1Each$2,500.00$2,500.00 $2,285.00$2,285.00 $0.00 
31Erosion Control Mat, RECP Type 2.C24S.Y.$24.00$576.00 $45.00$1,080.00 $0.00 
32Excavation, Class 10, Roadway and Borrow869C.Y.$12.50$10,862.50 $28.60$24,853.40 $0.00 
33Embankment-In-Place4059C.Y.$13.00$52,767.00 $36.10$146,529.90 $0.00 
34Revetment, Class E25Tons$50.00$1,250.00 $80.00$2,000.00 $0.00 
35Painted Pavement Mark, High-Build Waterborne1L.S.$1,000.00$1,000.00 $850.00$850.00 $0.00 
36Precast Concrete Parking Wheel Stops16Each$200.00$3,200.00 $155.00$2,480.00 $0.00 
37Detectable Warning Panel40S.F.$85.00$3,400.00 $85.00$3,400.00 $0.00 
38Seeding, Fertilizing, and Mulching6.8Acres$3,000.00$20,400.00 $3,250.00$22,100.00 $0.00 
39Filter Sock, 8"9310L.F.$4.00$37,240.00 $2.00$18,620.00 $0.00 
40Signing10Each$450.00$4,500.00 $380.00$3,800.00 $0.00 
41NPDES General Permit #2 & SWPPP1Each$4,000.00$4,000.00 $6,500.00$6,500.00 $0.00 
42Construction Staking1L.S.$17,500.00$17,500.00 $35,000.00$35,000.00 $0.00 
43Traffic Control1L.S.$1,500.00$1,500.00 $8,500.00$8,500.00 $0.00 
44Mobilization1L.S.$211,963.65$211,963.65 $170,000.00$170,000.00 $0.00 
45Bollard4Each$550.00$2,200.00 $550.00$2,200.00 $0.00 
      $1,250,000.00  $1,538,415.95  $0.00 
 



 

12/22/2024