IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Pikes Peak | Date: 2/17/2022 | Project No. |
| Campground Upgrade Project | County: | CLAYTON | Time: 11:00 a.m. | 21-03-22-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $2,200,000.00 | Contractor: | Midwest Concrete Inc. | Wicks Construction, Inc. | Eastern Iowa Excavating & Concrete LLC | |||||||||
| Funding Source: 27% Infrastructure, 73% Park & Institutional Road Fund, | 9835 Midwest Lane | PO Box 428 | 121 Nixon St SE | ||||||||||
| Peosta IA 52068 | Decorah IA 52101 | Cascade IA 52033 | |||||||||||
| Plan Sets Requested: 9 | Quantities | 563-845-0947 | 563-382-2325 | 563-852-5120 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Clearing and Grubbing | 1 | L.S. | $15,000.00 | $15,000.00 | $20,000.00 | $20,000.00 | $27,000.00 | $27,000.00 | ||||
| 2 | Tree Clearing/Stump Grinding | 1 | L.S. | $8,000.00 | $8,000.00 | $7,500.00 | $7,500.00 | $31,500.00 | $31,500.00 | ||||
| 3 | Full Depth Saw Cut | 325 | L.F. | $2.89 | $939.25 | $4.00 | $1,300.00 | $4.25 | $1,381.25 | ||||
| 4 | HMA Pavement Removal | 12800 | S.Y. | $2.00 | $25,600.00 | $3.75 | $48,000.00 | $1.80 | $23,040.00 | ||||
| 5 | PCC Removal | 529.4 | S.Y. | $8.00 | $4,235.20 | $11.50 | $6,088.10 | $9.50 | $5,029.30 | ||||
| 6 | Grading | 1 | L.S. | $33,312.50 | $33,312.50 | $42,500.00 | $42,500.00 | $185,000.00 | $185,000.00 | ||||
| 7 | 12-inch Filter Sock | 3160 | L.F. | $2.58 | $8,152.80 | $4.00 | $12,640.00 | $3.50 | $11,060.00 | ||||
| 8 | Sanitary Sewer Connections to Existing Manhole | 2 | Each | $1,846.68 | $3,693.36 | $750.00 | $1,500.00 | $1,000.00 | $2,000.00 | ||||
| 9 | Type SW-301 48" Diameter Sanitary Manhole w/Type 'A' Casting | 1 | Each | $2,883.68 | $2,883.68 | $12,500.00 | $12,500.00 | $3,600.00 | $3,600.00 | ||||
| 10 | 6-inch Sanitary Sewer (PVC SDR 23.5) | 228 | L.F. | $52.82 | $12,042.96 | $67.50 | $15,390.00 | $44.00 | $10,032.00 | ||||
| 11 | 4-inch Sanitary Sewer Service (PVC SDR 23.5) | 242 | L.F. | $65.79 | $15,921.18 | $62.50 | $15,125.00 | $37.00 | $8,954.00 | ||||
| 12 | Disposal Station RV Cleanout Connection | 2 | Each | $2,022.86 | $4,045.72 | $1,500.00 | $3,000.00 | $820.00 | $1,640.00 | ||||
| 13 | RV Sanitary Sewer Cleanout Connection | 6 | Each | $1,482.91 | $8,897.46 | $1,500.00 | $9,000.00 | $840.00 | $5,040.00 | ||||
| 14 | 6"x4" PVC Schedule 40 Service Wye | 6 | Each | $1,260.15 | $7,560.90 | $1,000.00 | $6,000.00 | $88.00 | $528.00 | ||||
| 15 | 2"x2"x2"x2" HDPE Cross | 1 | Each | $732.04 | $732.04 | $150.00 | $150.00 | $92.00 | $92.00 | ||||
| 16 | 1-inch HDPE Pipe | 1128 | L.F. | $31.68 | $35,735.04 | $27.50 | $31,020.00 | $13.00 | $14,664.00 | ||||
| 17 | 2-inch HDPE Pipe | 1195 | L.F. | $33.14 | $39,602.30 | $32.50 | $38,837.50 | $15.00 | $17,925.00 | ||||
| 18 | 2-Inch Valve | 3 | Each | $1,667.19 | $5,001.57 | $1,250.00 | $3,750.00 | $895.00 | $2,685.00 | ||||
| 19 | Woodford Model S-3 Sanitary Yard Hydrant w/Drain Down Pit (or Approved Equal) | 16 | Each | $2,742.09 | $43,873.44 | $2,000.00 | $32,000.00 | $2,605.00 | $41,680.00 | ||||
| 20 | Woodford Model S-3 Sanitary Yard Hydrant w/o Drain Down Pit (or Approved Equal) | 2 | Each | $2,610.70 | $5,221.40 | $2,000.00 | $4,000.00 | $1,921.00 | $3,842.00 | ||||
| 21 | Woodford Model S-4H ADA Sanitary Yard Hydrant w/Drain Down Pit (or Approved Equal) | 2 | Each | $2,748.60 | $5,497.20 | $2,000.00 | $4,000.00 | $2,420.00 | $4,840.00 | ||||
| 22 | Woodford Model S-4H ADA Sanitary Yard Hydrant w/o Drain Down Pit (or Approved Equal) | 2 | Each | $2,610.70 | $5,221.40 | $2,000.00 | $4,000.00 | $1,921.00 | $3,842.00 | ||||
| 23 | 1"x1"x1" HDPE Tee | 2 | Each | $565.57 | $1,131.14 | $100.00 | $200.00 | $14.50 | $29.00 | ||||
| 24 | 2"x2"x1" HDPE Tee | 14 | Each | $571.25 | $7,997.50 | $120.00 | $1,680.00 | $43.00 | $602.00 | ||||
| 25 | 2"x2"x2" HDPE Tee | 3 | Each | $570.37 | $1,711.11 | $150.00 | $450.00 | $30.00 | $90.00 | ||||
| 26 | 2"x1" HDPE Reducer | 5 | Each | $568.04 | $2,840.20 | $150.00 | $750.00 | $13.00 | $65.00 | ||||
| 27 | WellXTrol Model WX-452C Pressure Tanks (or Approved Equal) | 2 | Each | $8,240.00 | $16,480.00 | $19,500.00 | $39,000.00 | $8,555.00 | $17,110.00 | ||||
| 28 | Pressure Tank Installation and Removal of 2 Old Tanks | 1 | L.S. | $17,270.62 | $17,270.62 | $1,500.00 | $1,500.00 | $1,200.00 | $1,200.00 | ||||
| 29 | Water Connection | 2 | Each | $1,758.47 | $3,516.94 | $1,000.00 | $2,000.00 | $1,800.00 | $3,600.00 | ||||
| 30 | Disinfection | 1 | L.S. | $1,250.00 | $1,250.00 | $1,000.00 | $1,000.00 | $1,800.00 | $1,800.00 | ||||
| 31 | Type SW-512 Circular Area Intake W/Type 3A Casting | 8 | Each | $2,179.61 | $17,436.88 | $3,000.00 | $24,000.00 | $1,669.00 | $13,352.00 | ||||
| 32 | Type SW-513 open Sided Area Intake W/Type G Casting | 4 | Each | $1,483.18 | $5,932.72 | $3,750.00 | $15,000.00 | $2,807.00 | $11,228.00 | ||||
| 33 | 12-inch RCP Class III | 505.7 | L.F. | $56.60 | $28,622.62 | $72.00 | $36,410.40 | $50.00 | $25,285.00 | ||||
| 34 | 15-inch RCP Class III | 415.4 | L.F. | $60.53 | $25,144.162 | $75.00 | $31,155.00 | $55.00 | $22,847.00 | ||||
| 35 | 12-inch RCP Class III FES | 1 | Each | $2,213.00 | $2,213.00 | $1,475.00 | $1,475.00 | $815.00 | $815.00 | ||||
| 36 | 15-inch RCP Class III FES | 1 | Each | $2,296.17 | $2,296.17 | $1,575.00 | $1,575.00 | $900.00 | $900.00 | ||||
| 37 | Class 'D' Riprap | 100 | Tons | $36.08 | $3,608.00 | $27.50 | $2,750.00 | $24.00 | $2,400.00 | ||||
| 38 | Primary Electric Service To Distribution Panels | 1 | L.S. | $33,856.10 | $33,856.10 | $32,870.00 | $32,870.00 | $510.00 | $510.00 | ||||
| 39 | Single Campsite Outlet Post-30 Amp | 1 | Each | $391.28 | $391.28 | $379.88 | $379.88 | $510.00 | $510.00 | ||||
| 40 | Single Campsite Outlet Post-50 Amp | 60 | Each | $391.28 | $23,476.80 | $379.88 | $22,792.80 | $612.00 | $36,720.00 | ||||
| 41 | No. 2 AWG Grounding Conductor Cable, Type THW or USE | 4359 | L.F. | $3.15 | $13,730.85 | $3.05 | $13,294.95 | $4.11 | $17,915.49 | ||||
| 42 | No. 4 AWG Grounding Conductor Cable, Type THW or USE | 822 | L.F. | $2.02 | $1,660.44 | $1.96 | $1,611.12 | $2.65 | $2,178.30 | ||||
| 43 | No. 350 MCM Single Conductor Cable, Type USE | 837 | L.F. | $12.34 | $10,328.58 | $11.98 | $10,027.26 | $16.15 | $13,517.55 | ||||
| 44 | No. 300 MCM Single Conductor Cable, Type USE | 1386 | L.F. | $10.39 | $14,400.54 | $10.00 | $13,860.00 | $13.38 | $18,544.68 | ||||
| 45 | No. 250 MCM Single Conductor Cable, Type USE | 2640 | L.F. | $9.10 | $24,024.00 | $8.83 | $23,311.20 | $11.80 | $31,152.00 | ||||
| 46 | No. 4/0 AWG Single Conductor Cable, Type USE | 8214 | L.F. | $8.47 | $69,572.58 | $8.22 | $67,519.08 | $10.76 | $88,382.64 | ||||
| 47 | No. 3/0 AWG Single Conductor Cable, Type USE | 1656 | L.F. | $6.78 | $11,227.68 | $6.58 | $10,896.48 | $8.75 | $14,490.00 | ||||
| 48 | No. 2/0 AWG Single Conductor Cable, Type USE | 810 | L.F. | $5.42 | $4,390.20 | $5.26 | $4,260.60 | $7.00 | $5,670.00 | ||||
| 49 | Roadway Crossing 3-Inch Conduit-Schedule 80 PVC | 90 | L.F. | $12.22 | $1,099.80 | $11.86 | $1,067.40 | $24.00 | $2,160.00 | ||||
| 50 | Roadway Crossing 2.5-inch Conduit-Schedule 80 PVC | 290 | L.F. | $10.37 | $3,007.30 | $10.06 | $2,917.40 | $22.00 | $6,380.00 | ||||
| 51 | Roadway Crossing 2-inch Conduit-Schedule 80 PVC | 25 | L.F. | $8.20 | $205.00 | $7.96 | $199.00 | $20.00 | $500.00 | ||||
| 52 | Detectable Warning Tape, 3" Electric | 4116 | L.F. | $0.15 | $617.40 | $0.14 | $576.24 | $0.15 | $617.40 | ||||
| 53 | Trench, Single Circuit Secondary | 4521 | L.F. | $11.40 | $51,539.40 | $11.06 | $50,002.26 | $9.50 | $42,949.50 | ||||
| 54 | 200 Amp Circuit Breaker | 9 | Each | $400.79 | $3,607.11 | $389.11 | $3,501.99 | $420.00 | $3,780.00 | ||||
| 55 | 175 Amp Circuit Breaker | 1 | Each | $1,174.20 | $1,174.20 | $1,140.00 | $1,140.00 | $420.00 | $420.00 | ||||
| 56 | 150 Amp Circuit Breaker | 1 | Each | $309.00 | $309.00 | $300.00 | $300.00 | $420.00 | $420.00 | ||||
| 57 | 600 Amp Distribution Panel | 1 | Each | $6,798.00 | $6,798.00 | $6,600.00 | $6,600.00 | $21,033.00 | $21,033.00 | ||||
| 58 | 400 Amp Distribution Panel | 1 | Each | $5,562.00 | $5,562.00 | $5,400.00 | $5,400.00 | $14,983.00 | $14,983.00 | ||||
| 59 | Electrical Connection To Check-in Kiosk and LED Light | 1 | L.S. | $1,891.20 | $1,891.20 | $1,836.11 | $1,836.11 | $2,139.00 | $2,139.00 | ||||
| 60 | Special Backfill/Granular Base | 4658.3 | Tons | $14.44 | $67,265.852 | $15.15 | $70,573.245 | $16.50 | $76,861.95 | ||||
| 61 | 6-inch Non-Reinforced PCC | 3625.3 | S.Y. | $37.00 | $134,136.10 | $40.95 | $148,456.035 | $35.25 | $127,791.825 | ||||
| 62 | 7-inch Nylon Reinforced PCC | 10747.3 | S.Y. | $40.00 | $429,892.00 | $51.60 | $554,560.68 | $47.95 | $515,333.035 | ||||
| 63 | Disposal Station Island Pavement | 2 | Each | $5,589.00 | $11,178.00 | $3,500.00 | $7,000.00 | $3,575.00 | $7,150.00 | ||||
| 64 | Granular Base-Sidewalks | 32.1 | Tons | $25.31 | $812.451 | $27.50 | $882.75 | $25.25 | $810.525 | ||||
| 65 | 5-inch Non-Reinforced PCC Sidewalks | 160.4 | S.Y. | $51.00 | $8,180.40 | $62.00 | $9,944.80 | $41.65 | $6,680.66 | ||||
| 66 | Engineering Fabric | 7770 | S.Y. | $1.15 | $8,935.50 | $3.00 | $23,310.00 | $2.25 | $17,482.50 | ||||
| 67 | Macadam Stone | 1515 | Tons | $17.39 | $26,345.85 | $18.50 | $28,027.50 | $29.00 | $43,935.00 | ||||
| 68 | Class 'A' Crushed Stone | 1129 | Tons | $16.71 | $18,865.59 | $19.50 | $22,015.50 | $29.00 | $32,741.00 | ||||
| 69 | 4'x4'x5.5" Reinforced PCC Fire Ring | 60 | Each | $500.00 | $30,000.00 | $600.00 | $36,000.00 | $275.00 | $16,500.00 | ||||
| 70 | Traffic Control | 1 | L.S. | $2,575.00 | $2,575.00 | $1,000.00 | $1,000.00 | $2,850.00 | $2,850.00 | ||||
| 71 | Seeding, Fertilizing and Mulching | 5 | Acres | $4,120.00 | $20,600.00 | $3,400.00 | $17,000.00 | $4,100.00 | $20,500.00 | ||||
| 72 | Street Signage | 1 | L.S. | $3,502.00 | $3,502.00 | $2,805.00 | $2,805.00 | $2,265.00 | $2,265.00 | ||||
| 73 | Handicap Parking Signage | 1 | L.S. | $1,442.00 | $1,442.00 | $2,040.00 | $2,040.00 | $1,028.00 | $1,028.00 | ||||
| 74 | Street Pavement Markings | 1 | L.S. | $3,862.50 | $3,862.50 | $1,835.00 | $1,835.00 | $1,950.00 | $1,950.00 | ||||
| 75 | Parking Space Pavement Striping, Handicap Parking Cross Hatch Markings | 1 | L.S. | $3,862.50 | $3,862.50 | $3,295.00 | $3,295.00 | $3,500.00 | $3,500.00 | ||||
| 76 | 6' Concrete Parking Wheel Stops | 27 | Each | $188.64 | $5,093.28 | $135.00 | $3,645.00 | $86.00 | $2,322.00 | ||||
| 77 | 8' Concrete Parking Wheel Stops | 13 | Each | $214.66 | $2,790.58 | $135.00 | $1,755.00 | $126.00 | $1,638.00 | ||||
| 78 | Snow Fence Barrier W/Archeological Area | 440 | L.F. | $5.20 | $2,288.00 | $5.00 | $2,200.00 | $5.40 | $2,376.00 | ||||
| 79 | Construction Survey Staking and As-Built Survey | 1 | Each | $35,354.75 | $35,354.75 | $57,500.00 | $57,500.00 | $82,500.00 | $82,500.00 | ||||
| 80 | NPDES General Permit #2 & SWPPP | 1 | L.S. | $8,240.00 | $8,240.00 | $7,000.00 | $7,000.00 | $2,200.00 | $2,200.00 | ||||
| 81 | Mobilization | 1 | L.S. | $155,000.00 | $155,000.00 | $50,000.00 | $50,000.00 | $99,500.00 | $99,500.00 | ||||
| $1,691,712.275 | $1,802,455.28 | $1,899,585.605 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $2,200,000.00 | Contractor: | CJ Moyna and Sons, LLC | |||||||||||
| Funding Source: 27% Infrastructure, 73% Park & Institutional Road Fund, | 24412 Hwy 13 | ||||||||||||
| Elkader IA 52043 | |||||||||||||
| Plan Sets Requested: 9 | Quantities | 563-245-1442 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Clearing and Grubbing | 1 | L.S. | $45,000.00 | $45,000.00 | $0.00 | $0.00 | ||||||
| 2 | Tree Clearing/Stump Grinding | 1 | L.S. | $45,000.00 | $45,000.00 | $0.00 | $0.00 | ||||||
| 3 | Full Depth Saw Cut | 325 | L.F. | $10.00 | $3,250.00 | $0.00 | $0.00 | ||||||
| 4 | HMA Pavement Removal | 12800 | S.Y. | $15.00 | $192,000.00 | $0.00 | $0.00 | ||||||
| 5 | PCC Removal | 529.4 | S.Y. | $25.00 | $13,235.00 | $0.00 | $0.00 | ||||||
| 6 | Grading | 1 | L.S. | $260,000.00 | $260,000.00 | $0.00 | $0.00 | ||||||
| 7 | 12-inch Filter Sock | 3160 | L.F. | $2.50 | $7,900.00 | $0.00 | $0.00 | ||||||
| 8 | Sanitary Sewer Connections to Existing Manhole | 2 | Each | $1,450.00 | $2,900.00 | $0.00 | $0.00 | ||||||
| 9 | Type SW-301 48" Diameter Sanitary Manhole w/Type 'A' Casting | 1 | Each | $7,050.00 | $7,050.00 | $0.00 | $0.00 | ||||||
| 10 | 6-inch Sanitary Sewer (PVC SDR 23.5) | 228 | L.F. | $66.00 | $15,048.00 | $0.00 | $0.00 | ||||||
| 11 | 4-inch Sanitary Sewer Service (PVC SDR 23.5) | 242 | L.F. | $52.00 | $12,584.00 | $0.00 | $0.00 | ||||||
| 12 | Disposal Station RV Cleanout Connection | 2 | Each | $2,050.00 | $4,100.00 | $0.00 | $0.00 | ||||||
| 13 | RV Sanitary Sewer Cleanout Connection | 6 | Each | $1,875.00 | $11,250.00 | $0.00 | $0.00 | ||||||
| 14 | 6"x4" PVC Schedule 40 Service Wye | 6 | Each | $315.00 | $1,890.00 | $0.00 | $0.00 | ||||||
| 15 | 2"x2"x2"x2" HDPE Cross | 1 | Each | $300.00 | $300.00 | $0.00 | $0.00 | ||||||
| 16 | 1-inch HDPE Pipe | 1128 | L.F. | $24.00 | $27,072.00 | $0.00 | $0.00 | ||||||
| 17 | 2-inch HDPE Pipe | 1195 | L.F. | $25.00 | $29,875.00 | $0.00 | $0.00 | ||||||
| 18 | 2-Inch Valve | 3 | Each | $900.00 | $2,700.00 | $0.00 | $0.00 | ||||||
| 19 | Woodford Model S-3 Sanitary Yard Hydrant w/Drain Down Pit (or Approved Equal) | 16 | Each | $4,200.00 | $67,200.00 | $0.00 | $0.00 | ||||||
| 20 | Woodford Model S-3 Sanitary Yard Hydrant w/o Drain Down Pit (or Approved Equal) | 2 | Each | $3,500.00 | $7,000.00 | $0.00 | $0.00 | ||||||
| 21 | Woodford Model S-4H ADA Sanitary Yard Hydrant w/Drain Down Pit (or Approved Equal) | 2 | Each | $3,600.00 | $7,200.00 | $0.00 | $0.00 | ||||||
| 22 | Woodford Model S-4H ADA Sanitary Yard Hydrant w/o Drain Down Pit (or Approved Equal) | 2 | Each | $5,800.00 | $11,600.00 | $0.00 | $0.00 | ||||||
| 23 | 1"x1"x1" HDPE Tee | 2 | Each | $262.00 | $524.00 | $0.00 | $0.00 | ||||||
| 24 | 2"x2"x1" HDPE Tee | 14 | Each | $275.00 | $3,850.00 | $0.00 | $0.00 | ||||||
| 25 | 2"x2"x2" HDPE Tee | 3 | Each | $275.00 | $825.00 | $0.00 | $0.00 | ||||||
| 26 | 2"x1" HDPE Reducer | 5 | Each | $260.00 | $1,300.00 | $0.00 | $0.00 | ||||||
| 27 | WellXTrol Model WX-452C Pressure Tanks (or Approved Equal) | 2 | Each | $4,500.00 | $9,000.00 | $0.00 | $0.00 | ||||||
| 28 | Pressure Tank Installation and Removal of 2 Old Tanks | 1 | L.S. | $1,800.00 | $1,800.00 | $0.00 | $0.00 | ||||||
| 29 | Water Connection | 2 | Each | $2,400.00 | $4,800.00 | $0.00 | $0.00 | ||||||
| 30 | Disinfection | 1 | L.S. | $1,800.00 | $1,800.00 | $0.00 | $0.00 | ||||||
| 31 | Type SW-512 Circular Area Intake W/Type 3A Casting | 8 | Each | $2,650.00 | $21,200.00 | $0.00 | $0.00 | ||||||
| 32 | Type SW-513 open Sided Area Intake W/Type G Casting | 4 | Each | $5,050.00 | $20,200.00 | $0.00 | $0.00 | ||||||
| 33 | 12-inch RCP Class III | 505.7 | L.F. | $68.00 | $34,387.60 | $0.00 | $0.00 | ||||||
| 34 | 15-inch RCP Class III | 415.4 | L.F. | $72.00 | $29,908.80 | $0.00 | $0.00 | ||||||
| 35 | 12-inch RCP Class III FES | 1 | Each | $2,300.00 | $2,300.00 | $0.00 | $0.00 | ||||||
| 36 | 15-inch RCP Class III FES | 1 | Each | $2,500.00 | $2,500.00 | $0.00 | $0.00 | ||||||
| 37 | Class 'D' Riprap | 100 | Tons | $90.00 | $9,000.00 | $0.00 | $0.00 | ||||||
| 38 | Primary Electric Service To Distribution Panels | 1 | L.S. | $36,000.00 | $36,000.00 | $0.00 | $0.00 | ||||||
| 39 | Single Campsite Outlet Post-30 Amp | 1 | Each | $400.00 | $400.00 | $0.00 | $0.00 | ||||||
| 40 | Single Campsite Outlet Post-50 Amp | 60 | Each | $400.00 | $24,000.00 | $0.00 | $0.00 | ||||||
| 41 | No. 2 AWG Grounding Conductor Cable, Type THW or USE | 4359 | L.F. | $3.10 | $13,512.90 | $0.00 | $0.00 | ||||||
| 42 | No. 4 AWG Grounding Conductor Cable, Type THW or USE | 822 | L.F. | $2.00 | $1,644.00 | $0.00 | $0.00 | ||||||
| 43 | No. 350 MCM Single Conductor Cable, Type USE | 837 | L.F. | $12.00 | $10,044.00 | $0.00 | $0.00 | ||||||
| 44 | No. 300 MCM Single Conductor Cable, Type USE | 1386 | L.F. | $10.00 | $13,860.00 | $0.00 | $0.00 | ||||||
| 45 | No. 250 MCM Single Conductor Cable, Type USE | 2640 | L.F. | $9.00 | $23,760.00 | $0.00 | $0.00 | ||||||
| 46 | No. 4/0 AWG Single Conductor Cable, Type USE | 8214 | L.F. | $8.30 | $68,176.20 | $0.00 | $0.00 | ||||||
| 47 | No. 3/0 AWG Single Conductor Cable, Type USE | 1656 | L.F. | $6.80 | $11,260.80 | $0.00 | $0.00 | ||||||
| 48 | No. 2/0 AWG Single Conductor Cable, Type USE | 810 | L.F. | $5.40 | $4,374.00 | $0.00 | $0.00 | ||||||
| 49 | Roadway Crossing 3-Inch Conduit-Schedule 80 PVC | 90 | L.F. | $12.00 | $1,080.00 | $0.00 | $0.00 | ||||||
| 50 | Roadway Crossing 2.5-inch Conduit-Schedule 80 PVC | 290 | L.F. | $10.20 | $2,958.00 | $0.00 | $0.00 | ||||||
| 51 | Roadway Crossing 2-inch Conduit-Schedule 80 PVC | 25 | L.F. | $8.00 | $200.00 | $0.00 | $0.00 | ||||||
| 52 | Detectable Warning Tape, 3" Electric | 4116 | L.F. | $0.20 | $823.20 | $0.00 | $0.00 | ||||||
| 53 | Trench, Single Circuit Secondary | 4521 | L.F. | $11.50 | $51,991.50 | $0.00 | $0.00 | ||||||
| 54 | 200 Amp Circuit Breaker | 9 | Each | $400.00 | $3,600.00 | $0.00 | $0.00 | ||||||
| 55 | 175 Amp Circuit Breaker | 1 | Each | $1,200.00 | $1,200.00 | $0.00 | $0.00 | ||||||
| 56 | 150 Amp Circuit Breaker | 1 | Each | $300.00 | $300.00 | $0.00 | $0.00 | ||||||
| 57 | 600 Amp Distribution Panel | 1 | Each | $6,600.00 | $6,600.00 | $0.00 | $0.00 | ||||||
| 58 | 400 Amp Distribution Panel | 1 | Each | $5,400.00 | $5,400.00 | $0.00 | $0.00 | ||||||
| 59 | Electrical Connection To Check-in Kiosk and LED Light | 1 | L.S. | $1,900.00 | $1,900.00 | $0.00 | $0.00 | ||||||
| 60 | Special Backfill/Granular Base | 4658.3 | Tons | $27.00 | $125,774.10 | $0.00 | $0.00 | ||||||
| 61 | 6-inch Non-Reinforced PCC | 3625.3 | S.Y. | $47.00 | $170,389.10 | $0.00 | $0.00 | ||||||
| 62 | 7-inch Nylon Reinforced PCC | 10747.3 | S.Y. | $45.00 | $483,628.50 | $0.00 | $0.00 | ||||||
| 63 | Disposal Station Island Pavement | 2 | Each | $3,500.00 | $7,000.00 | $0.00 | $0.00 | ||||||
| 64 | Granular Base-Sidewalks | 32.1 | Tons | $90.00 | $2,889.00 | $0.00 | $0.00 | ||||||
| 65 | 5-inch Non-Reinforced PCC Sidewalks | 160.4 | S.Y. | $55.00 | $8,822.00 | $0.00 | $0.00 | ||||||
| 66 | Engineering Fabric | 7770 | S.Y. | $6.00 | $46,620.00 | $0.00 | $0.00 | ||||||
| 67 | Macadam Stone | 1515 | Tons | $26.00 | $39,390.00 | $0.00 | $0.00 | ||||||
| 68 | Class 'A' Crushed Stone | 1129 | Tons | $23.00 | $25,967.00 | $0.00 | $0.00 | ||||||
| 69 | 4'x4'x5.5" Reinforced PCC Fire Ring | 60 | Each | $375.00 | $22,500.00 | $0.00 | $0.00 | ||||||
| 70 | Traffic Control | 1 | L.S. | $12,000.00 | $12,000.00 | $0.00 | $0.00 | ||||||
| 71 | Seeding, Fertilizing and Mulching | 5 | Acres | $4,000.00 | $20,000.00 | $0.00 | $0.00 | ||||||
| 72 | Street Signage | 1 | L.S. | $3,400.00 | $3,400.00 | $0.00 | $0.00 | ||||||
| 73 | Handicap Parking Signage | 1 | L.S. | $1,400.00 | $1,400.00 | $0.00 | $0.00 | ||||||
| 74 | Street Pavement Markings | 1 | L.S. | $3,750.00 | $3,750.00 | $0.00 | $0.00 | ||||||
| 75 | Parking Space Pavement Striping, Handicap Parking Cross Hatch Markings | 1 | L.S. | $3,750.00 | $3,750.00 | $0.00 | $0.00 | ||||||
| 76 | 6' Concrete Parking Wheel Stops | 27 | Each | $180.00 | $4,860.00 | $0.00 | $0.00 | ||||||
| 77 | 8' Concrete Parking Wheel Stops | 13 | Each | $260.00 | $3,380.00 | $0.00 | $0.00 | ||||||
| 78 | Snow Fence Barrier W/Archeological Area | 440 | L.F. | $8.00 | $3,520.00 | $0.00 | $0.00 | ||||||
| 79 | Construction Survey Staking and As-Built Survey | 1 | Each | $100,000.00 | $100,000.00 | $0.00 | $0.00 | ||||||
| 80 | NPDES General Permit #2 & SWPPP | 1 | L.S. | $12,000.00 | $12,000.00 | $0.00 | $0.00 | ||||||
| 81 | Mobilization | 1 | L.S. | $250,000.00 | $250,000.00 | $0.00 | $0.00 | ||||||
| $2,551,673.70 | $0.00 | $0.00 | |||||||||||
12/11/2025