| Bids For: | Location: | Viking Lake | Date: 4/16/2020 | Project No. |
| building demo @ Aldersgate Rebid | County: | MONTGOMERY | Time: 3:00 p.m. | 19-04-69-05 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $65,000.00 | Contractor: | C&J Conservation LLC | Bridge City Investments dba Environmental Edge LLC | TEK Builder, LLC | |||||||||
| Funding Source: 100% REAP Land Management, | 1676 E Adams St | 2801 Roemer Ave | 105 W Jefferson | ||||||||||
| Creston IA 50801 | Ottumwa IA 52501 | Mount Ayr IA 50854 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 6413445891 | 6412264483 | 6414140008 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Remove Bldg #1, 36'x64' | 1 | L.S. | $4,000.00 | $4,000.00 | $14,899.00 | $14,899.00 | $13,000.00 | $13,000.00 | ||||
| 2 | Remove Bldg #2, 16'8"x16'8"' | 1 | L.S. | $2,500.00 | $2,500.00 | $5,500.00 | $5,500.00 | $3,000.00 | $3,000.00 | ||||
| 3 | Remove Bldg #3, 50'x120' | 1 | L.S. | $12,000.00 | $12,000.00 | $27,000.00 | $27,000.00 | $33,399.00 | $33,399.00 | ||||
| 4 | Grading & Site Restoration | 1 | L.S. | $3,000.00 | $3,000.00 | $2,500.00 | $2,500.00 | $1,500.00 | $1,500.00 | ||||
| $21,500.00 | $49,899.00 | $50,899.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $65,000.00 | Contractor: | Vicker Drilling LLC | JNC Construction LLC | Schaefer Excavating, Inc. | |||||||||
| Funding Source: 100% REAP Land Management, | 2151 S Cherry St Rd | 609 3rd St | 1864 215th St | ||||||||||
| Creston IA 50801 | Clearfield IA 50840 | Mt Ayr IA 50854 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 6412022728 | 6413444119 | 6414642419 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Remove Bldg #1, 36'x64' | 1 | L.S. | $16,390.80 | $16,390.80 | $17,000.00 | $17,000.00 | $20,100.00 | $20,100.00 | ||||
| 2 | Remove Bldg #2, 16'8"x16'8"' | 1 | L.S. | $4,450.50 | $4,450.50 | $3,500.00 | $3,500.00 | $2,720.00 | $2,720.00 | ||||
| 3 | Remove Bldg #3, 50'x120' | 1 | L.S. | $35,600.00 | $35,600.00 | $35,000.00 | $35,000.00 | $34,450.00 | $34,450.00 | ||||
| 4 | Grading & Site Restoration | 1 | L.S. | $5,000.50 | $5,000.50 | $8,500.00 | $8,500.00 | $6,875.00 | $6,875.00 | ||||
| $61,441.80 | $64,000.00 | $64,145.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $65,000.00 | Contractor: | Douglas Bierbaum Electric Corp | Smith Landworx | ||||||||||
| Funding Source: 100% REAP Land Management, | 1507 Chestnut | 401 South St PO Box 486 | |||||||||||
| Atlantic IA 50022 | New Virginia IA 50210 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 7122431946 | 5152404006 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Remove Bldg #1, 36'x64' | 1 | L.S. | $31,459.00 | $31,459.00 | $23,500.00 | $23,500.00 | $0.00 | |||||
| 2 | Remove Bldg #2, 16'8"x16'8"' | 1 | L.S. | $4,249.00 | $4,249.00 | $3,500.00 | $3,500.00 | $0.00 | |||||
| 3 | Remove Bldg #3, 50'x120' | 1 | L.S. | $31,629.00 | $31,629.00 | $51,500.00 | $51,500.00 | $0.00 | |||||
| 4 | Grading & Site Restoration | 1 | L.S. | $9,569.00 | $9,569.00 | $7,150.00 | $7,150.00 | $0.00 | |||||
| $76,906.00 | $85,650.00 | $0.00 | |||||||||||