IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Rathbun WMA  Date: 1/16/2020  Project No.  
  North Colyn - Bridge Deck (rebid)  County:   LUCAS  Time: 3:00 p.m.  20-05-59-07

 

 
1
2
3
Estimated Cost: $12,000.00
Contractor: 
Haworth Land ConstructionDingman Const.Boulder Contracting LLC
Funding Source: 100% REAP OS Acquisition & Development, 12981 Quaker St
1265 240th St
25789 N Ave
Indianola IA  50125Creston IA  50801Grundy Center IA  50638
Plan Sets Requested: 0
Quantities
515249474764124714313192422182
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Bridge Deck, Complete1L.S.$10,059.00$10,059.00 $13,485.73$13,485.73 $20,000.00$20,000.00 
      $10,059.00  $13,485.73  $20,000.00 
 



 

4/8/2026