Bids For: | Location: | Clear Lake Wildlife Unit | Date: 2/13/2020 | Project No. |
Langesen Wetland Restoration Rebid | County: | WINNEBAGO | Time: 3:00 p.m. | 19-02-95-03 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $47,000.00 | Contractor: | A1 Excavating and Drainage Inc | David Ryan Construction | Groves Contracting LLC | |||||||||
Funding Source: 100% Other, | 505 410th St | 3566 236th Ave | 1205 Hwy 69 S | ||||||||||
Joice IA 50446 | Decorah IA 52101 | Forest City IA 50436 | |||||||||||
Plan Sets Requested: 0 | Quantities | 6415883576 | 5633801365 | 6415852960 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $0.00 | $0.00 | $4,000.00 | $4,000.00 | $1,628.00 | $1,628.00 | ||||
2 | Earth Filled Embankment | 852 | C.Y. | $10.00 | $8,520.00 | $4.00 | $3,408.00 | $7.00 | $5,964.00 | ||||
3 | Excavation-Stripping, Core Trench, Outlet Chan. | 562 | C.Y. | $10.00 | $5,620.00 | $4.00 | $2,248.00 | $10.95 | $6,153.90 | ||||
4 | Shallow Water Excavation and Spoil | 1 | Acres | $2,000.00 | $2,000.00 | $5,000.00 | $5,000.00 | $6,421.00 | $6,421.00 | ||||
5 | Water Control Structure, Complete | 1 | Each | $5,000.00 | $5,000.00 | $10,000.00 | $10,000.00 | $8,994.00 | $8,994.00 | ||||
6 | Tile Search and Break | 60 | L.F. | $20.00 | $1,200.00 | $10.00 | $600.00 | $10.00 | $600.00 | ||||
7 | 8” Diameter x 5’ CMP Riser, Complete | 1 | Each | $2,500.00 | $2,500.00 | $5,000.00 | $5,000.00 | $894.00 | $894.00 | ||||
8 | 18” Diameter CMP | 33 | L.F. | $40.00 | $1,320.00 | $40.00 | $1,320.00 | $42.00 | $1,386.00 | ||||
9 | 12” Diameter CMP | 10 | L.F. | $20.00 | $200.00 | $35.00 | $350.00 | $30.00 | $300.00 | ||||
10 | 10” Dia. Dual Wall PE Tubing Non-Perf (New) | 1060 | L.F. | $12.00 | $12,720.00 | $8.00 | $8,480.00 | $13.25 | $14,045.00 | ||||
11 | Class “D” Revetment (Outlet Protection) | 2 | Tons | $250.00 | $500.00 | $60.00 | $120.00 | $200.00 | $400.00 | ||||
12 | 36” Dia. CMP (Removal) | 1 | L.S. | $500.00 | $500.00 | $2,000.00 | $2,000.00 | $825.00 | $825.00 | ||||
13 | Erosion Control | 700 | L.F. | $1.50 | $1,050.00 | $3.00 | $2,100.00 | $3.00 | $2,100.00 | ||||
14 | Seeding, Mulching, Fertilizing & Site Restor. | 1 | L.S. | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $3,275.00 | $3,275.00 | ||||
$43,130.00 | $46,626.00 | $52,985.90 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $47,000.00 | Contractor: | Larson Contracting Central LLC | Rognes Bros. Excavating, Inc. | Midwest Liquidation, LLC | |||||||||
Funding Source: 100% Other, | 508 West Main St | 205 N Mill St PO Box 86 | 73137 State Highway 16, Ste 2 | ||||||||||
Lake Mills IA 50450 | Lake Mills IA 50450 | Grand Meadow MN 55936 | |||||||||||
Plan Sets Requested: 0 | Quantities | 6415925800 | 6415928932 | 5077547530 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $2,680.00 | $2,680.00 | $4,000.00 | $4,000.00 | $13,100.00 | $13,100.00 | ||||
2 | Earth Filled Embankment | 852 | C.Y. | $7.17 | $6,108.84 | $5.50 | $4,686.00 | $9.25 | $7,881.00 | ||||
3 | Excavation-Stripping, Core Trench, Outlet Chan. | 562 | C.Y. | $11.96 | $6,721.52 | $5.00 | $2,810.00 | $10.30 | $5,788.60 | ||||
4 | Shallow Water Excavation and Spoil | 1 | Acres | $6,937.00 | $6,937.00 | $7,000.00 | $7,000.00 | $13,380.00 | $13,380.00 | ||||
5 | Water Control Structure, Complete | 1 | Each | $10,442.00 | $10,442.00 | $12,500.00 | $12,500.00 | $3,250.00 | $3,250.00 | ||||
6 | Tile Search and Break | 60 | L.F. | $10.00 | $600.00 | $6.00 | $360.00 | $7.50 | $450.00 | ||||
7 | 8” Diameter x 5’ CMP Riser, Complete | 1 | Each | $908.00 | $908.00 | $2,000.00 | $2,000.00 | $350.00 | $350.00 | ||||
8 | 18” Diameter CMP | 33 | L.F. | $52.24 | $1,723.92 | $32.00 | $1,056.00 | $20.25 | $668.25 | ||||
9 | 12” Diameter CMP | 10 | L.F. | $34.30 | $343.00 | $27.00 | $270.00 | $13.25 | $132.50 | ||||
10 | 10” Dia. Dual Wall PE Tubing Non-Perf (New) | 1060 | L.F. | $14.00 | $14,840.00 | $14.00 | $14,840.00 | $9.15 | $9,699.00 | ||||
11 | Class “D” Revetment (Outlet Protection) | 2 | Tons | $212.00 | $424.00 | $75.00 | $150.00 | $60.25 | $120.50 | ||||
12 | 36” Dia. CMP (Removal) | 1 | L.S. | $860.00 | $860.00 | $750.00 | $750.00 | $2,400.00 | $2,400.00 | ||||
13 | Erosion Control | 700 | L.F. | $3.00 | $2,100.00 | $2.25 | $1,575.00 | $3.25 | $2,275.00 | ||||
14 | Seeding, Mulching, Fertilizing & Site Restor. | 1 | L.S. | $3,300.00 | $3,300.00 | $7,000.00 | $7,000.00 | $11,203.00 | $11,203.00 | ||||
$57,988.28 | $58,997.00 | $70,697.85 | |||||||||||
7 | 8 | 9 | |||||||||||
Estimated Cost: $47,000.00 | Contractor: | Reding's Gravel & Excavating Co. | |||||||||||
Funding Source: 100% Other, | 2001 E Oak St | ||||||||||||
Algona IA 50511 | |||||||||||||
Plan Sets Requested: 0 | Quantities | 5152953661 | |||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $5,600.00 | $5,600.00 | $0.00 | $0.00 | ||||||
2 | Earth Filled Embankment | 852 | C.Y. | $14.50 | $12,354.00 | $0.00 | $0.00 | ||||||
3 | Excavation-Stripping, Core Trench, Outlet Chan. | 562 | C.Y. | $28.00 | $15,736.00 | $0.00 | $0.00 | ||||||
4 | Shallow Water Excavation and Spoil | 1 | Acres | $6,760.00 | $6,760.00 | $0.00 | $0.00 | ||||||
5 | Water Control Structure, Complete | 1 | Each | $11,760.10 | $11,760.10 | $0.00 | $0.00 | ||||||
6 | Tile Search and Break | 60 | L.F. | $6.50 | $390.00 | $0.00 | $0.00 | ||||||
7 | 8” Diameter x 5’ CMP Riser, Complete | 1 | Each | $804.00 | $804.00 | $0.00 | $0.00 | ||||||
8 | 18” Diameter CMP | 33 | L.F. | $65.00 | $2,145.00 | $0.00 | $0.00 | ||||||
9 | 12” Diameter CMP | 10 | L.F. | $24.00 | $240.00 | $0.00 | $0.00 | ||||||
10 | 10” Dia. Dual Wall PE Tubing Non-Perf (New) | 1060 | L.F. | $18.00 | $19,080.00 | $0.00 | $0.00 | ||||||
11 | Class “D” Revetment (Outlet Protection) | 2 | Tons | $240.00 | $480.00 | $0.00 | $0.00 | ||||||
12 | 36” Dia. CMP (Removal) | 1 | L.S. | $1,500.00 | $1,500.00 | $0.00 | $0.00 | ||||||
13 | Erosion Control | 700 | L.F. | $3.50 | $2,450.00 | $0.00 | $0.00 | ||||||
14 | Seeding, Mulching, Fertilizing & Site Restor. | 1 | L.S. | $5,500.00 | $5,500.00 | $0.00 | $0.00 | ||||||
$84,799.10 | $0.00 | $0.00 | |||||||||||