IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Saylorville Wildlife Unit | Date: 9/17/2020 | Project No. |
| Lakin Slough Culvert Flow Line Adjustment | County: | GUTHRIE | Time: 3:00 p.m. | 20-04-39-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $56,000.00 | Contractor: | Richards Construction Co., Inc. | Progressive Structures LLC | Gus Construction Co., Inc. | |||||||||
| Funding Source: 100% REAP Land Management, | 2721 Sierra Ave | 24412 Hwy 13 | 606 McPherson St | ||||||||||
| Sac City IA 50583 | Elkader IA 52043 | Casey IA 50048 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 7126624421 | 5638809138 | 6417462229 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | MOBILIZATION | 1 | L.S. | $2,000.00 | $2,000.00 | $5,000.00 | $5,000.00 | $12,321.00 | $12,321.00 | ||||
| 2 | PAVEMENT REMOVAL, EXCAVATION & RE-POSITIONING THE CULVERT (COMPLETE WITH BACKFILL) | 1 | L.S. | $16,000.00 | $16,000.00 | $21,000.00 | $21,000.00 | $34,000.00 | $34,000.00 | ||||
| 3 | SPECIAL BACKFILL | 56 | Tons | $50.00 | $2,800.00 | $26.00 | $1,456.00 | $83.00 | $4,648.00 | ||||
| 4 | 6” PCC | 123 | S.Y. | $85.00 | $10,455.00 | $125.00 | $15,375.00 | $125.00 | $15,375.00 | ||||
| 5 | ROAD SIGNAGE | 1 | L.S. | $1,500.00 | $1,500.00 | $2,500.00 | $2,500.00 | $4,500.00 | $4,500.00 | ||||
| 6 | DUST CONTROL | 1 | L.S. | $1,000.00 | $1,000.00 | $1,800.00 | $1,800.00 | $6,000.00 | $6,000.00 | ||||
| 7 | DITCH CLEANING SOUTH SIDE OF CULVERT | 1 | L.S. | $1,500.00 | $1,500.00 | $7,000.00 | $7,000.00 | $4,000.00 | $4,000.00 | ||||
| 8 | DREDGE SLOUGH AREA | 445 | C.Y. | $4.00 | $1,780.00 | $25.00 | $11,125.00 | $32.00 | $14,240.00 | ||||
| 9 | SILT FENCE | 500 | L.F. | $3.00 | $1,500.00 | $7.50 | $3,750.00 | $8.00 | $4,000.00 | ||||
| 10 | SITE RESTORATION | 1 | L.S. | $3,000.00 | $3,000.00 | $4,500.00 | $4,500.00 | $5,221.00 | $5,221.00 | ||||
| $41,535.00 | $73,506.00 | $104,305.00 | |||||||||||
4/9/2026