IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Ventura Access  Date: 7/16/2020  Project No.  
  Boat ramp replacement two lanes  County:   CERRO GORDO  Time: 3:00 p.m.  19-03-17-03

 

 
1
2
3
Estimated Cost: $75,000.00
Contractor: 
Larson Contracting Central LLC2 Men And A Hoe LLCDean Snyder Construction
Funding Source: 100% Marine Fuel Tax, 508 West Main St
3268 190th St
913 N 14th St
Lake Mills IA  50450Charles City IA  50616Clear Lake IA  50401
Plan Sets Requested: 0
Quantities
641592580064133080136413557917
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$5,848.00$5,848.00 $5,500.00$5,500.00 $71,725.00$71,725.00 
2Pavement Removal376S.Y.$20.06$7,542.56 $13.00$4,888.00 $25.00$9,400.00 
3Structural Concrete, Class "C", 7" Depth425S.Y.$70.75$30,068.75 $147.00$62,475.00 $108.00$45,900.00 
4Revetment, Class "D" Riprap127Tons$61.56$7,818.12 $31.00$3,937.00 $65.00$8,255.00 
5Revetment, Class "D" Fieldstone27Tons$109.52$2,957.04 $76.00$2,052.00 $150.00$4,050.00 
6Class "A" Crushed Stone, 6" depth132Tons$47.70$6,296.40 $16.50$2,178.00 $40.00$5,280.00 
7Class "A" crushed Stone, Temporary Ramp335Tons$28.52$9,554.20 $16.50$5,527.50 $30.00$10,050.00 
8Recliam Class "A" Crushed Stone178Tons$21.73$3,867.94 $14.00$2,492.00 $30.00$5,340.00 
      $73,953.01  $89,049.50  $160,000.00 
 



 

3/29/2024