IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Fairport Fish Hatchery  Date: 4/1/2021  Project No.  
  Holding House Demolition  County:   MUSCATINE  Time: 3:00 p.m.  20-06-70-03

 

 
1
2
3
Estimated Cost: $19,000.00
Contractor: 
SulzCo LLCTriple B ConstructionChris Jones
Funding Source: 100% REAP Land Management, 2410 Imperial Oaks Dr
710 Ayres Progress Dr
263 260th St
Muscatine IA  52761Wilton IA  52778West Branch IA  52358
Plan Sets Requested: 0
Quantities
563272805256373234783196437487
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Cut and Cap Utilities1L.S.$1,200.00$1,200.00 $1,000.00$1,000.00 $2,800.00$2,800.00 
2Demolition and Salvage1L.S.$10,500.00$10,500.00 $30,860.00$30,860.00 $12,900.00$12,900.00 
3Dirt Fill, Compacting and Seeding1L.S.$3,800.00$3,800.00 $4,000.00$4,000.00 $4,800.00$4,800.00 
4Shot-Rock Fill48Tons$31.00$1,488.00 $30.00$1,440.00 $1,200.00$57,600.00 
5Mobilization1L.S.$1,500.00$1,500.00 $2,000.00$2,000.00 $3,000.00$3,000.00 
      $18,488.00  $39,300.00  $81,100.00 
 



 

3/29/2024