IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Wildcat Den  Date: 7/17/2019  Project No.  
  Culvert Replacement  County:   MUSCATINE  Time: 11:00 a.m.  20-06-70-02

 

 
1
2
3
Estimated Cost: $9,500.00
Contractor: 
DeLong Construction, Inc.
Funding Source: 100% Park & Institutional Road Fund, PO Box 488


Washington IA  52353    
Plan Sets Requested: 0
Quantities
3196533334
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$2,000.00$2,000.00 $0.00 $0.00 
2Pavement Removal (Including Sawcutting)1L.S.$1,500.00$1,500.00 $0.00 $0.00 
3Culvert Pipe, 36" Dia. CMP50L.F.$75.00$3,750.00 $0.00 $0.00 
4Road Stone23Tons$30.00$690.00 $0.00 $0.00 
      $7,940.00  $0.00  $0.00 
 



 