IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Viking Lake | Date: 9/12/2019 | Project No. |
| Fish Habitat Spawning Bed Repair | County: | MONTGOMERY | Time: 3:00 p.m. | 20-04-69-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $10,000.00 | Contractor: | JNC Construction, LLC | |||||||||||
| Funding Source: 100% REAP Land Management, | 609 3rd St | ||||||||||||
| Clearfield IA 50840 | |||||||||||||
| Plan Sets Requested: 0 | Quantities | 6413444119 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 3/8" Pea Gravel | 168 | Tons | $50.00 | $8,400.00 | $0.00 | $0.00 | ||||||
| 2 | Engineering Fabric | 668 | S.Y. | $3.00 | $2,004.00 | $0.00 | $0.00 | ||||||
| 3 | Site Restoration | 1 | L.S. | $200.00 | $200.00 | $0.00 | $0.00 | ||||||
| $10,604.00 | $0.00 | $0.00 | |||||||||||