IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | State Forest Nursery | Date: 7/18/2019 | Project No. |
| Irrigation System Phase 2 | County: | STORY | Time: 11:00 a.m. | 18-02-85-04 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $200,000.00 | Contractor: | Vicker Drilling, LLC | Mort's Water Company | ||||||||||
| Funding Source: 100% REAP OS Acquisition & Development, | 2151 S Cherry St Rd | 1410 Gull Ave | |||||||||||
| Creston IA 50801 | Latimer IA 50452 | ||||||||||||
| Plan Sets Requested: 1 | Quantities | 6412022728 | 6415796500 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $6,200.00 | $6,200.00 | $11,000.00 | $11,000.00 | $0.00 | |||||
| 2 | Connect New 6" PVC with Existing Valves | 1 | L.S. | $1,500.00 | $1,500.00 | $2,000.00 | $2,000.00 | $0.00 | |||||
| 3 | 6" CI Gate Valves with Valve Box & Stem Extension | 2 | Each | $1,895.00 | $3,790.00 | $2,056.00 | $4,112.00 | $0.00 | |||||
| 4 | 4" CI Gate Valves with Valve Box & Stem Extension | 4 | Each | $1,500.00 | $6,000.00 | $1,680.00 | $6,720.00 | $0.00 | |||||
| 5 | 2" Plug Valves with Valve Box & Stem Extension | 2 | Each | $1,235.00 | $2,470.00 | $1,016.00 | $2,032.00 | $0.00 | |||||
| 6 | 6" PVC DR 25 C900 PVC Pipe | 2483 | L.F. | $14.00 | $34,762.00 | $24.04 | $59,691.32 | $0.00 | |||||
| 7 | 4" PVC DR 25 C900 PVC Pipe | 1697 | L.F. | $12.00 | $20,364.00 | $17.07 | $28,967.79 | $0.00 | |||||
| 8 | 2" PVC DR 25 C900 PVC Pipe | 2900 | L.F. | $8.50 | $24,650.00 | $12.29 | $35,641.00 | $0.00 | |||||
| 9 | 6"x6"x2" Ts Installed | 5 | Each | $1,565.00 | $7,825.00 | $486.00 | $2,430.00 | $0.00 | |||||
| 10 | 6"x6"x2"x2" Cross | 12 | Each | $1,565.00 | $18,780.00 | $1,212.00 | $14,544.00 | $0.00 | |||||
| 11 | 4"x4"x2"x2" Cross | 17 | Each | $1,375.00 | $23,375.00 | $1,144.00 | $19,448.00 | $0.00 | |||||
| 12 | 4"x4"x2" Ts Installed | 16 | Each | $1,155.00 | $18,480.00 | $868.00 | $13,888.00 | $0.00 | |||||
| 13 | Connect 2" Drain Line to Manhole | 2 | Each | $1,050.00 | $2,100.00 | $1,144.00 | $2,288.00 | $0.00 | |||||
| 14 | Site Restoration | 1 | L.S. | $1,000.00 | $1,000.00 | $2,500.00 | $2,500.00 | $0.00 | |||||
| $171,296.00 | $205,262.11 | $0.00 | |||||||||||
4/7/2026