IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Brushy Creek Recreation Area  Date: 5/7/2020  Project No.  
  Fish Barrier  County:   WEBSTER  Time: 3:00 p.m.  20-02-94-03

 

 
1
2
3
Estimated Cost: $50,000.00
Contractor: 
Doyle ConstructionCentral Iowa Dirt and Demo LLCRichards Construction Co., Inc.
Funding Source: 100% REAP OS Acquisition & Development, 516 N 6th St
3075 Hancock Ave
2721 Sierra Ave
Fort Dodge IA  50501Woolstock IA  50599Sac City IA  50583
Plan Sets Requested: 0
Quantities
515570771831929074797126624421
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$2,000.00$2,000.00 $4,000.00$4,000.00 $5,000.00$5,000.00 
2Grading1L.S.$7,150.00$7,150.00 $11,264.00$11,264.00 $5,500.00$5,500.00 
3Concrete62C.Y.$335.00$20,770.00 $315.00$19,530.00 $400.00$24,800.00 
4Fish Barrier197L.F.$61.00$12,017.00 $48.00$9,456.00 $58.00$11,426.00 
      $41,937.00  $44,250.00  $46,726.00 
 
 
4
5
6
Estimated Cost: $50,000.00
Contractor: 
Woodruff Construction, LLCIowa Technology Solutions LLC Boulder Contracting, LLC
Funding Source: 100% REAP OS Acquisition & Development, 1890 Kountry Lane
926 Main St
606 E 1st St
Fort Dodge IA  50501Manson IA  50563Grundy Center IA  50638
Plan Sets Requested: 0
Quantities
515576111871246920403192422182
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$5,000.00$5,000.00 $5,150.00$5,150.00 $6,200.00$6,200.00 
2Grading1L.S.$11,000.00$11,000.00 $10,300.00$10,300.00 $4,825.00$4,825.00 
3Concrete62C.Y.$339.00$21,018.00 $309.00$19,158.00 $642.00$39,804.00 
4Fish Barrier197L.F.$51.00$10,047.00 $66.95$13,189.15 $45.00$8,865.00 
      $47,065.00  $47,797.15  $59,694.00 
 



 