IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Big Spring Fish Hatchery | Date: 6/27/2019 | Project No. |
Hatchery Road Bank Stabilization | County: | CLAYTON | Time: 3:00 p.m. | 19-03-22-03 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $60,000.00 | Contractor: | Keppler Custom Hire LLC | Ethan Koehn Construction | Donlon Custom Hire LLC | |||||||||
Funding Source: 100% Park & Institutional Road Fund, | 17751 Big Spring Rd | 19397 Fawn Hollow Rd | 18172 145th St | ||||||||||
St Olaf IA 52072 | Farmersburg IA 52047 | Monona IA 52159 | |||||||||||
Plan Sets Requested: 0 | Quantities | 5637837790 | 5638808350 | 5638808378 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $100.00 | $100.00 | $100.00 | $100.00 | $5,000.00 | $5,000.00 | ||||
2 | Tree Removal | 1 | L.S. | $100.00 | $100.00 | $1,000.00 | $1,000.00 | $1,500.00 | $1,500.00 | ||||
3 | Revetment, Rip Rap, Class B | 1035 | Tons | $17.80 | $18,423.00 | $19.00 | $19,665.00 | $18.00 | $18,630.00 | ||||
4 | Excavation & Bank Shaping | 1727 | C.Y. | $1.67 | $2,884.09 | $1.75 | $3,022.25 | $2.00 | $3,454.00 | ||||
5 | Seeding/Straw Mat | 1 | L.S. | $1,000.00 | $1,000.00 | $1,200.00 | $1,200.00 | $1,200.00 | $1,200.00 | ||||
$22,507.09 | $24,987.25 | $29,784.00 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $60,000.00 | Contractor: | Burr Oak Springs | Skyline Construction Inc. | Matt Construction, Inc. | |||||||||
Funding Source: 100% Park & Institutional Road Fund, | 2113 County Rd W14 | 900 Montgomery St | 203 Y Ave | ||||||||||
Ridgeway IA 52165 | Decorah IA 52101 | Sumner IA 50674 | |||||||||||
Plan Sets Requested: 0 | Quantities | 5637372510 | 5633822933 | 5635788418 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $2,000.00 | $2,000.00 | $0.00 | $0.00 | $2,500.00 | $2,500.00 | ||||
2 | Tree Removal | 1 | L.S. | $1,000.00 | $1,000.00 | $3,800.00 | $3,800.00 | $2,050.00 | $2,050.00 | ||||
3 | Revetment, Rip Rap, Class B | 1035 | Tons | $25.00 | $25,875.00 | $28.999 | $30,013.965 | $23.00 | $23,805.00 | ||||
4 | Excavation & Bank Shaping | 1727 | C.Y. | $4.00 | $6,908.00 | $1.699 | $2,934.173 | $10.00 | $17,270.00 | ||||
5 | Seeding/Straw Mat | 1 | L.S. | $1,000.00 | $1,000.00 | $2,500.00 | $2,500.00 | $2,000.00 | $2,000.00 | ||||
$36,783.00 | $39,248.138 | $47,625.00 | |||||||||||
7 | 8 | 9 | |||||||||||
Estimated Cost: $60,000.00 | Contractor: | Connolly Construction Inc. | David Ryan Construction | Dan Oberbreckling Concrete & Excavating | |||||||||
Funding Source: 100% Park & Institutional Road Fund, | 18409 N Cascade Rd | 3566 236th Ave | 2780 Coggon Rd | ||||||||||
Peosta IA 52068 | Decorah IA 52101 | Coggon IA 52218 | |||||||||||
Plan Sets Requested: 0 | Quantities | 5638763225 | 5633809895 | 5639200970 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $6,550.00 | $6,550.00 | $2,000.00 | $2,000.00 | $5,000.00 | $5,000.00 | ||||
2 | Tree Removal | 1 | L.S. | $2,660.00 | $2,660.00 | $4,500.00 | $4,500.00 | $2,200.00 | $2,200.00 | ||||
3 | Revetment, Rip Rap, Class B | 1035 | Tons | $22.70 | $23,494.50 | $40.00 | $41,400.00 | $47.50 | $49,162.50 | ||||
4 | Excavation & Bank Shaping | 1727 | C.Y. | $8.50 | $14,679.50 | $4.50 | $7,771.50 | $7.50 | $12,952.50 | ||||
5 | Seeding/Straw Mat | 1 | L.S. | $3,560.00 | $3,560.00 | $3,150.00 | $3,150.00 | $7,500.00 | $7,500.00 | ||||
$50,944.00 | $58,821.50 | $76,815.00 | |||||||||||