IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Marshall County ATV | Date: 9/17/2026 | Project No. |
| Storage Building | County: | MARSHALL | Time: 11:00 a.m. | 20-05-64-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $400,000.00 | Contractor: | Ciro Diiorio Masonry and Landscaping | GTG Construction LLC | Tri-State Construction Group, Inc. | |||||||||
| Funding Source: 100% ATV Fund, | 907 Sunshine Dr | 2717 Martin Luther King Jr Pkwy | 3151 Brockway Rd., Suite 200 | ||||||||||
| Marshalltown IA 50158 | Des Moines IA 50310 | Waterloo IA 50701 | |||||||||||
| Plan Sets Requested: 2 | Quantities | 641-328-9248 | 515-528-8178 | 319-939-3151 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | MOBILIZATION | 1 | L.S. | $26,873.00 | $26,873.00 | $65,000.00 | $65,000.00 | $105,012.00 | $105,012.00 | ||||
| 2 | SITE GRADING | 1 | L.S. | $27,078.00 | $27,078.00 | $30,000.00 | $30,000.00 | $10,159.00 | $10,159.00 | ||||
| 3 | CONCRETE FOOTINGS | 1 | L.S. | $7,072.00 | $7,072.00 | $2,300.00 | $2,300.00 | $1,155.00 | $1,155.00 | ||||
| 4 | CONCRETE APRON SLAB AND BOLLARDS | 1 | L.S. | $12,941.00 | $12,941.00 | $25,000.00 | $25,000.00 | $23,348.00 | $23,348.00 | ||||
| 5 | INSULATED INTERIOR CONCRETE SLAB | 1 | L.S. | $19,946.00 | $19,946.00 | $30,000.00 | $30,000.00 | $39,111.00 | $39,111.00 | ||||
| 6 | MECHANICAL - VENTS AND LOUVERS | 1 | L.S. | $11,379.00 | $11,379.00 | $10,900.00 | $10,900.00 | $8,250.00 | $8,250.00 | ||||
| 7 | ELECTRICAL - LIGHTING | 1 | L.S. | $16,100.00 | $16,100.00 | $11,000.00 | $11,000.00 | $15,620.00 | $15,620.00 | ||||
| 8 | ELECTRICAL - SERVICE AND MISC. | 1 | L.S. | $9,200.00 | $9,200.00 | $14,250.00 | $14,250.00 | $20,460.00 | $20,460.00 | ||||
| 9 | ELECTRICAL - HEATERS | 1 | L.S. | $8,274.00 | $8,274.00 | $12,850.00 | $12,850.00 | $9,130.00 | $9,130.00 | ||||
| 10 | PLUMBING - STUB-UPS, CURB STOP, DRAIN-DOWN PIT | 1 | L.S. | $2,236.00 | $2,236.00 | $3,900.00 | $3,900.00 | $7,480.00 | $7,480.00 | ||||
| 11 | PRE-ENGINEERED POST FRAME BUILDING - W/ STEEL SIDING AND ROOFING | 1 | L.S. | $68,550.00 | $68,550.00 | $80,000.00 | $80,000.00 | $83,720.00 | $83,720.00 | ||||
| 12 | INTERIOR CORRUGATED METAL WALL AND CEILING LINER PANELS | 1 | L.S. | $22,850.00 | $22,850.00 | $15,000.00 | $15,000.00 | $20,829.00 | $20,829.00 | ||||
| 13 | DOORS, FRAMES, AND TRIM | 1 | L.S. | $11,367.00 | $11,367.00 | $12,250.00 | $12,250.00 | $19,063.00 | $19,063.00 | ||||
| 14 | GUTTERS AND DOWNSPOUTS | 1 | L.S. | $4,100.00 | $4,100.00 | $2,200.00 | $2,200.00 | $1,782.00 | $1,782.00 | ||||
| 15 | CLOSED CELL SPRAY FOAM INSULATION - CEILING AND WALLS | 1 | L.S. | $24,383.00 | $24,383.00 | $24,500.00 | $24,500.00 | $24,281.00 | $24,281.00 | ||||
| $272,349.00 | $339,150.00 | $389,400.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $400,000.00 | Contractor: | N.B. Koch General Contractors | Ball Team, LLC | ||||||||||
| Funding Source: 100% ATV Fund, | 1571 W 7th St PO Box 826 | 10550 New York Ave, Suite 200 | |||||||||||
| Cedar Falls IA 50613 | Urbandale IA 50322 | ||||||||||||
| Plan Sets Requested: 2 | Quantities | 319-269-0889 | 515-440-4544 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | MOBILIZATION | 1 | L.S. | $24,244.00 | $24,244.00 | $194,128.00 | $194,128.00 | $0.00 | |||||
| 2 | SITE GRADING | 1 | L.S. | $20,400.00 | $20,400.00 | $33,914.00 | $33,914.00 | $0.00 | |||||
| 3 | CONCRETE FOOTINGS | 1 | L.S. | $21,225.00 | $21,225.00 | $0.00 | $0.00 | $0.00 | |||||
| 4 | CONCRETE APRON SLAB AND BOLLARDS | 1 | L.S. | $26,070.00 | $26,070.00 | $20,945.00 | $20,945.00 | $0.00 | |||||
| 5 | INSULATED INTERIOR CONCRETE SLAB | 1 | L.S. | $31,780.00 | $31,780.00 | $37,710.00 | $37,710.00 | $0.00 | |||||
| 6 | MECHANICAL - VENTS AND LOUVERS | 1 | L.S. | $15,000.00 | $15,000.00 | $18,600.00 | $18,600.00 | $0.00 | |||||
| 7 | ELECTRICAL - LIGHTING | 1 | L.S. | $14,200.00 | $14,200.00 | $14,200.00 | $14,200.00 | $0.00 | |||||
| 8 | ELECTRICAL - SERVICE AND MISC. | 1 | L.S. | $18,600.00 | $18,600.00 | $18,600.00 | $18,600.00 | $0.00 | |||||
| 9 | ELECTRICAL - HEATERS | 1 | L.S. | $800.00 | $800.00 | $800.00 | $800.00 | $0.00 | |||||
| 10 | PLUMBING - STUB-UPS, CURB STOP, DRAIN-DOWN PIT | 1 | L.S. | $7,200.00 | $7,200.00 | $7,400.00 | $7,400.00 | $0.00 | |||||
| 11 | PRE-ENGINEERED POST FRAME BUILDING - W/ STEEL SIDING AND ROOFING | 1 | L.S. | $145,238.00 | $145,238.00 | $120,263.00 | $120,263.00 | $0.00 | |||||
| 12 | INTERIOR CORRUGATED METAL WALL AND CEILING LINER PANELS | 1 | L.S. | $25,000.00 | $25,000.00 | $64,000.00 | $64,000.00 | $0.00 | |||||
| 13 | DOORS, FRAMES, AND TRIM | 1 | L.S. | $16,728.00 | $16,728.00 | $16,792.00 | $16,792.00 | $0.00 | |||||
| 14 | GUTTERS AND DOWNSPOUTS | 1 | L.S. | $4,700.00 | $4,700.00 | $5,980.00 | $5,980.00 | $0.00 | |||||
| 15 | CLOSED CELL SPRAY FOAM INSULATION - CEILING AND WALLS | 1 | L.S. | $18,815.00 | $18,815.00 | $23,268.00 | $23,268.00 | $0.00 | |||||
| $390,000.00 | $576,600.00 | $0.00 | |||||||||||
9/18/2026