IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Dolliver Memorial  Date: 7/11/2019  Project No.  
  2018 Flood Repair  County:   WEBSTER  Time: 3:00 p.m.  20-02-94-02

 

 
1
2
3
Estimated Cost: $86,000.00
Contractor: 
Dingman Const
Funding Source: 100% Executive Council, 1265 240th St


Creston IA  50801    
Plan Sets Requested: 0
Quantities
6412471431
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$3,000.00$3,000.00 $0.00 $0.00 
2Class “D” Revetment1183Tons$51.00$60,333.00 $0.00 $0.00 
3Class “D” Revetment - Canyon129Tons$51.00$6,579.00 $0.00 $0.00 
448” Diameter CMP Culvert, Complete48L.F.$100.42$4,820.16 $0.00 $0.00 
5Barricades and Cleanup1L.S.$1,500.00$1,500.00 $0.00 $0.00 
      $76,232.16  $0.00  $0.00 
 



 

12/19/2025