IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Pikes Peak State Park  Date: 11/20/2025  Project No.  
  Office Road Pavement Rehabilitation  County:   CLAYTON  Time: 11:00 am  20-03-22-02

 

 
1
2
3
Estimated Cost: $110,000.00
Contractor: 
Kluesner ConstructionEastern Iowa Excavating & Concrete, LLCSkyline Construction, Inc
Funding Source: 75% Park & Institutional Road Fund, 25% Infrastructure, 1007 1st Ave NW
121 Nixon St SE
900 Montgomery St
PO Box 127
Farley IA  52046Cascade IA  52033Decorah IA  52101
Plan Sets Requested: 2
Quantities
563-744-3422563-852-5120563-382-2933
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$1,500.00$1,500.00 $9,000.00$9,000.00 $19,303.39$19,303.39 
2Traffic Control1L.S.$500.00$500.00 $2,850.00$2,850.00 $350.00$350.00 
3Tree Removal, 24"-36" dia. 6Each$1,340.00$8,040.00 $430.00$2,580.00 $1,200.00$7,200.00 
4Culvert, 24" RCP8L.F.$225.00$1,800.00 $305.00$2,440.00 $110.00$880.00 
5Transverse Joint Repairs240L.F.$16.80$4,032.00 $18.75$4,500.00 $18.00$4,320.00 
6HMA Full Depth Patch56S.Y.$116.00$6,496.00 $149.00$8,344.00 $120.00$6,720.00 
7Granular Subbase212Tons$34.20$7,250.40 $22.00$4,664.00 $25.75$5,459.00 
8HMA Widening, 6" Depth692S.Y.$52.50$36,330.00 $59.00$40,828.00 $54.00$37,368.00 
9Class A Road Stone32Tons$34.20$1,094.40 $24.00$768.00 $25.75$824.00 
10Double Chip Seal3824S.Y.$8.94$34,186.56 $7.85$30,018.40 $9.40$35,945.60 
11Signage 1L.S.$695.00$695.00 $335.00$335.00 $350.00$350.00 
12Site Restoration1L.S.$2,692.00$2,692.00 $1,500.00$1,500.00 $1,200.00$1,200.00 
      $104,616.36  $107,827.40  $119,919.99 
 



 

12/5/2025