IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Grant Park | Date: 1/24/2019 | Project No. |
| Enhancement Project Rebid | County: | SAC | Time: 11:00 a.m. | 18-01-81-08 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $157,431.00 | Contractor: | Richards Construction Co., Inc. | Hendrickson Transportation, LLC | LA Carlson Contracting, Inc. | |||||||||
| Funding Source: 100% Marine Fuel Tax, | 2721 Sierra Ave | 2762 310th St | 20984 C-43 | ||||||||||
| Sac City IA 50583 | Hamburg IA 51640 | Merrill IA 51038-8674 | |||||||||||
| Plan Sets Requested: 2 | Quantities | 17126624421 | 7123821505 | 7129470002 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 3’x3’x3’ WEIR STONE, 2.5 MINIMUM SPECIFIC GRAVITY | 170 | Each | $400.00 | $68,000.00 | $400.00 | $68,000.00 | $440.00 | $74,800.00 | ||||
| 2 | CLASS ‘B’ RIPRAP | 700 | Tons | $48.00 | $33,600.00 | $55.00 | $38,500.00 | $57.00 | $39,900.00 | ||||
| 3 | 6-INCH REINFORCED PCC PAVEMENT | 33.4 | S.Y. | $112.00 | $3,740.80 | $200.00 | $6,680.00 | $120.00 | $4,008.00 | ||||
| 4 | REINFORCED PCC BOAT RAMP PUSH-IN SLAB | 40 | S.Y. | $112.00 | $4,480.00 | $220.00 | $8,800.00 | $120.00 | $4,800.00 | ||||
| 5 | CLASS ‘A’ CRUSHED STONE | 50 | Tons | $40.00 | $2,000.00 | $38.00 | $1,900.00 | $50.00 | $2,500.00 | ||||
| 6 | CLASS ‘D’ RIPRAP | 100 | Tons | $50.00 | $5,000.00 | $55.00 | $5,500.00 | $57.00 | $5,700.00 | ||||
| 7 | MACADAM STONE | 11.7 | Tons | $60.00 | $702.00 | $42.00 | $491.40 | $52.00 | $608.40 | ||||
| 8 | SURFACE RESTORATION | 1 | L.S. | $3,000.00 | $3,000.00 | $5,000.00 | $5,000.00 | $4,000.00 | $4,000.00 | ||||
| 9 | NPDES GENERAL PERMIT #2 & SWPPP | 1 | L.S. | $2,000.00 | $2,000.00 | $6,000.00 | $6,000.00 | $4,500.00 | $4,500.00 | ||||
| 10 | MOBILIZATION | 1 | L.S. | $9,000.00 | $9,000.00 | $15,000.00 | $15,000.00 | $17,500.00 | $17,500.00 | ||||
| $131,522.80 | $155,871.40 | $158,316.40 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $157,431.00 | Contractor: | Lodge Construction Inc. | |||||||||||
| Funding Source: 100% Marine Fuel Tax, | PO Box 459 | ||||||||||||
| Clarksville IA 50619 | |||||||||||||
| Plan Sets Requested: 2 | Quantities | 3192905767 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 3’x3’x3’ WEIR STONE, 2.5 MINIMUM SPECIFIC GRAVITY | 170 | Each | $475.00 | $80,750.00 | $0.00 | $0.00 | ||||||
| 2 | CLASS ‘B’ RIPRAP | 700 | Tons | $59.00 | $41,300.00 | $0.00 | $0.00 | ||||||
| 3 | 6-INCH REINFORCED PCC PAVEMENT | 33.4 | S.Y. | $105.00 | $3,507.00 | $0.00 | $0.00 | ||||||
| 4 | REINFORCED PCC BOAT RAMP PUSH-IN SLAB | 40 | S.Y. | $210.00 | $8,400.00 | $0.00 | $0.00 | ||||||
| 5 | CLASS ‘A’ CRUSHED STONE | 50 | Tons | $50.00 | $2,500.00 | $0.00 | $0.00 | ||||||
| 6 | CLASS ‘D’ RIPRAP | 100 | Tons | $59.00 | $5,900.00 | $0.00 | $0.00 | ||||||
| 7 | MACADAM STONE | 11.7 | Tons | $78.00 | $912.60 | $0.00 | $0.00 | ||||||
| 8 | SURFACE RESTORATION | 1 | L.S. | $10,000.00 | $10,000.00 | $0.00 | $0.00 | ||||||
| 9 | NPDES GENERAL PERMIT #2 & SWPPP | 1 | L.S. | $20,000.00 | $20,000.00 | $0.00 | $0.00 | ||||||
| 10 | MOBILIZATION | 1 | L.S. | $12,000.00 | $12,000.00 | $0.00 | $0.00 | ||||||
| $185,269.60 | $0.00 | $0.00 | |||||||||||
12/22/2025