IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Ingham Wetland Complex | Date: 5/12/2022 | Project No. |
| Shoreline Armoring | County: | EMMET | Time: 11:00 a.m. | 19-01-32-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $270,000.00 | Contractor: | B & B Farm Drainage Inc | BD Construction Services LLC | ||||||||||
| Funding Source: 100% Park & Institutional Road Fund, | 217 Davy Ave | 2410 West 11th St 1134 | |||||||||||
| Wallingford IA 51365 | Spencer IA 51301 | ||||||||||||
| Plan Sets Requested: 7 | Quantities | 7122603918 | 7122622959 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 2101 - CLEARING | 1 | L.S. | $45,000.00 | $45,000.00 | $50,000.00 | $50,000.00 | $0.00 | |||||
| 2 | 2507 - FIELDSTONE, CLASS "E" REVETMENT | 3630 | Tons | $79.00 | $286,770.00 | $109.00 | $395,670.00 | $0.00 | |||||
| 3 | 2528 - TRAFFIC CONTROL | 1 | L.S. | $500.00 | $500.00 | $3,000.00 | $3,000.00 | $0.00 | |||||
| 4 | 2533 - MOBILIZATION | 1 | L.S. | $500.00 | $500.00 | $27,000.00 | $27,000.00 | $0.00 | |||||
| $332,770.00 | $475,670.00 | $0.00 | |||||||||||