IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Lake Manawa State Park | Date: 6/18/2020 | Project No. |
Campground Construction | County: | POTTAWATTAMIE | Time: 11:00 a.m. | 20-04-78-02 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $3,733,000.00 | Contractor: | Carley Construction LLC | Meco-Henne Contracting Inc | Bluffs Paving & Utility Company, Inc. | |||||||||
Funding Source: 18% Infrastructure, 34% Park & Institutional Road Fund, 48% Federal-Land and Water Conservation Fund, | 421 E Broadway, Ste A | 4140 S 87th St | 20474 Monument Rd | ||||||||||
Council Bluffs IA 51503 | Omaha NE 68127 | Crescent IA 51526 | |||||||||||
Plan Sets Requested: 7 | Quantities | 712-256-5818 | 402-339-8127 | 712-328-0068 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Clearing and Grubbing | 1 | L.S. | $27,950.00 | $27,950.00 | $36,660.00 | $36,660.00 | $42,633.07 | $42,633.07 | ||||
2 | Removal of Exisitng Pavement and Base | 7230 | STA.-CY | $6.30 | $45,549.00 | $7.80 | $56,394.00 | $9.09 | $65,720.70 | ||||
3 | Demolition | 1 | L.S. | $20,650.00 | $20,650.00 | $45,515.00 | $45,515.00 | $23,900.35 | $23,900.35 | ||||
4 | Sanitary Sewer, 4" (PVC SDR 35) | 3083 | L.F. | $26.00 | $80,158.00 | $26.00 | $80,158.00 | $67.75 | $208,873.25 | ||||
5 | Sanitary Sewer, 8" (PVC SDR 35) | 1888 | L.F. | $106.65 | $201,355.20 | $29.00 | $54,752.00 | $75.50 | $142,544.00 | ||||
6 | RV Sewer Connection | 41 | Each | $1,177.50 | $48,277.50 | $1,691.00 | $69,331.00 | $782.70 | $32,090.70 | ||||
7 | Sanitary Manhole, SW-301 | 11 | Each | $3,560.00 | $39,160.00 | $4,347.00 | $47,817.00 | $4,805.96 | $52,865.56 | ||||
8 | Sanitary Manhole, SW-303 | 1 | Each | $4,050.00 | $4,050.00 | $5,290.00 | $5,290.00 | $4,994.39 | $4,994.39 | ||||
9 | Water Service Line, 1" HDPE | 18223 | L.F. | $12.50 | $227,787.50 | $14.00 | $255,122.00 | $5.32 | $96,946.36 | ||||
10 | Water Service Line, 2" HDPE | 90 | L.F. | $14.50 | $1,305.00 | $17.00 | $1,530.00 | $24.92 | $2,242.80 | ||||
11 | Water Main, 2" HDPE | 540 | L.F. | $13.60 | $7,344.00 | $22.00 | $11,880.00 | $49.02 | $26,470.80 | ||||
12 | Water Main, 3" HDPE | 1350 | L.F. | $16.00 | $21,600.00 | $22.00 | $29,700.00 | $33.69 | $45,481.50 | ||||
13 | Hydrant | 43 | Each | $1,100.00 | $47,300.00 | $1,375.00 | $59,125.00 | $1,083.94 | $46,609.42 | ||||
14 | Painted Pavement Mark, High-Build Waterborne | 1 | L.S. | $15,225.00 | $15,225.00 | $2,300.00 | $2,300.00 | $18,732.72 | $18,732.72 | ||||
15 | Painted Symbol+Legend, High-Build Waterborne | 10 | Each | $265.00 | $2,650.00 | $173.00 | $1,730.00 | $322.98 | $3,229.80 | ||||
16 | Drain Down Pit | 3 | Each | $5,315.00 | $15,945.00 | $5,923.00 | $17,769.00 | $7,460.89 | $22,382.67 | ||||
17 | Electrical | 1 | L.S. | $325,110.00 | $325,110.00 | $382,120.00 | $382,120.00 | $406,454.59 | $406,454.59 | ||||
18 | Campsites Pavement, 6" PCC | 6170 | S.Y. | $48.50 | $299,245.00 | $44.00 | $271,480.00 | $50.91 | $314,114.70 | ||||
19 | Modified Subbase | 6200 | C.Y. | $58.75 | $364,250.00 | $65.00 | $403,000.00 | $71.93 | $445,966.00 | ||||
20 | Subdrain, Longitudinal, (Shoulder), 4" | 8343 | L.F. | $4.00 | $33,372.00 | $18.00 | $150,174.00 | $11.27 | $94,025.61 | ||||
21 | Subdrain Outlet, DR-306 | 46 | Each | $150.00 | $6,900.00 | $414.00 | $19,044.00 | $473.05 | $21,760.30 | ||||
22 | Roadway Pavement, 7" PCC | 10120 | S.Y. | $43.75 | $442,750.00 | $47.00 | $475,640.00 | $47.18 | $477,461.60 | ||||
23 | Parking Lot Pavement, 7" PCC | 5670 | S.Y. | $45.25 | $256,567.50 | $47.00 | $266,490.00 | $43.55 | $246,928.50 | ||||
24 | Curb and Gutter, PCC, 2.5' | 95 | L.F. | $26.20 | $2,489.00 | $23.00 | $2,185.00 | $42.54 | $4,041.30 | ||||
25 | Reinforced Concrete Pipe, 24" | 94 | L.F. | $84.00 | $7,896.00 | $108.00 | $10,152.00 | $94.25 | $8,859.50 | ||||
26 | Reinforced Concrete Pipe Apron, 24" | 4 | Each | $2,870.00 | $11,480.00 | $2,122.00 | $8,488.00 | $2,178.51 | $8,714.04 | ||||
27 | Precast Concrete Parking Wheel Stops | 2 | Each | $420.00 | $840.00 | $863.00 | $1,726.00 | $802.18 | $1,604.36 | ||||
28 | Sidewalk, 6" PCC | 120 | S.Y. | $48.00 | $5,760.00 | $46.00 | $5,520.00 | $58.35 | $7,002.00 | ||||
29 | Trail, 6" PCC | 1160 | S.Y. | $44.25 | $51,330.00 | $46.00 | $53,360.00 | $50.55 | $58,638.00 | ||||
30 | ADA Campfire Ring with Pad | 41 | Each | $880.00 | $36,080.00 | $542.00 | $22,222.00 | $889.93 | $36,487.13 | ||||
31 | Picnic Table, 6' Handicap Accessible | 41 | Each | $1,750.00 | $71,750.00 | $952.00 | $39,032.00 | $1,567.95 | $64,285.95 | ||||
32 | Wood Fence, 8' | 573 | L.F. | $22.40 | $12,835.20 | $24.00 | $13,752.00 | $77.51 | $44,413.23 | ||||
33 | Excavation, Class 10, Roadway and Borrow | 10000 | C.Y. | $12.00 | $120,000.00 | $5.00 | $50,000.00 | $20.48 | $204,800.00 | ||||
34 | Seeding, Fertilizing, and Mulching | 16.68 | Acres | $1,715.00 | $28,606.20 | $2,760.00 | $46,036.80 | $2,131.65 | $35,555.922 | ||||
35 | Filter Sock, 8" | 14280 | L.F. | $2.65 | $37,842.00 | $3.00 | $42,840.00 | $3.55 | $50,694.00 | ||||
36 | 2 Stall Modern Bathroom/Shower (Wolverine) | 1 | Each | $105,000.00 | $105,000.00 | $102,944.00 | $102,944.00 | $65,216.89 | $65,216.89 | ||||
37 | Check-In Station | 1 | L.S. | $66,000.00 | $66,000.00 | $80,981.00 | $80,981.00 | $158,191.10 | $158,191.10 | ||||
38 | Vegetative Barrier | 1259 | L.F. | $41.15 | $51,807.85 | $115.00 | $144,785.00 | $50.71 | $63,843.89 | ||||
39 | Security Gate | 1 | L.S. | $17,850.00 | $17,850.00 | $5,750.00 | $5,750.00 | $27,000.95 | $27,000.95 | ||||
40 | Signing | 58 | Each | $172.00 | $9,976.00 | $230.00 | $13,340.00 | $516.76 | $29,972.08 | ||||
41 | Revetment, Class E | 852 | Tons | $52.15 | $44,431.80 | $63.00 | $53,676.00 | $63.37 | $53,991.24 | ||||
42 | Detectable Warning Panel | 246 | S.F. | $43.00 | $10,578.00 | $41.00 | $10,086.00 | $31.07 | $7,643.22 | ||||
43 | Furnish and Place 3' Boulders (Minimum 2.5 Ton Each) | 22 | Each | $540.00 | $11,880.00 | $621.00 | $13,662.00 | $805.02 | $17,710.44 | ||||
44 | NPDES General Permit #2 & SWPPP | 1 | L.S. | $5,000.00 | $5,000.00 | $27,530.00 | $27,530.00 | $23,686.90 | $23,686.90 | ||||
45 | Bollards | 7 | Each | $1,020.00 | $7,140.00 | $801.00 | $5,607.00 | $1,033.53 | $7,234.71 | ||||
46 | Construction Staking | 1 | L.S. | $45,500.00 | $45,500.00 | $37,915.00 | $37,915.00 | $66,662.61 | $66,662.61 | ||||
47 | Traffic Control | 1 | L.S. | $5,000.00 | $5,000.00 | $9,309.00 | $9,309.00 | $4,586.29 | $4,586.29 | ||||
48 | Mobilization | 1 | L.S. | $55,000.00 | $55,000.00 | $104,941.00 | $104,941.00 | $285,231.95 | $285,231.95 | ||||
$3,356,572.75 | $3,648,860.80 | $4,178,497.092 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $3,733,000.00 | Contractor: | Vieco Development & Construction Co. Inc. | |||||||||||
Funding Source: 18% Infrastructure, 34% Park & Institutional Road Fund, 48% Federal-Land and Water Conservation Fund, | 5180 SE 70th Rd | ||||||||||||
St Joseph MO 64507 | |||||||||||||
Plan Sets Requested: 7 | Quantities | 816-387-1884 | |||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Clearing and Grubbing | 1 | L.S. | $6,000.00 | $6,000.00 | $0.00 | $0.00 | ||||||
2 | Removal of Exisitng Pavement and Base | 7230 | STA.-CY | $6.00 | $43,380.00 | $0.00 | $0.00 | ||||||
3 | Demolition | 1 | L.S. | $12,000.00 | $12,000.00 | $0.00 | $0.00 | ||||||
4 | Sanitary Sewer, 4" (PVC SDR 35) | 3083 | L.F. | $25.00 | $77,075.00 | $0.00 | $0.00 | ||||||
5 | Sanitary Sewer, 8" (PVC SDR 35) | 1888 | L.F. | $28.00 | $52,864.00 | $0.00 | $0.00 | ||||||
6 | RV Sewer Connection | 41 | Each | $250.00 | $10,250.00 | $0.00 | $0.00 | ||||||
7 | Sanitary Manhole, SW-301 | 11 | Each | $4,000.00 | $44,000.00 | $0.00 | $0.00 | ||||||
8 | Sanitary Manhole, SW-303 | 1 | Each | $4,000.00 | $4,000.00 | $0.00 | $0.00 | ||||||
9 | Water Service Line, 1" HDPE | 18223 | L.F. | $12.00 | $218,676.00 | $0.00 | $0.00 | ||||||
10 | Water Service Line, 2" HDPE | 90 | L.F. | $20.00 | $1,800.00 | $0.00 | $0.00 | ||||||
11 | Water Main, 2" HDPE | 540 | L.F. | $24.00 | $12,960.00 | $0.00 | $0.00 | ||||||
12 | Water Main, 3" HDPE | 1350 | L.F. | $26.00 | $35,100.00 | $0.00 | $0.00 | ||||||
13 | Hydrant | 43 | Each | $1,800.00 | $77,400.00 | $0.00 | $0.00 | ||||||
14 | Painted Pavement Mark, High-Build Waterborne | 1 | L.S. | $2,500.00 | $2,500.00 | $0.00 | $0.00 | ||||||
15 | Painted Symbol+Legend, High-Build Waterborne | 10 | Each | $200.00 | $2,000.00 | $0.00 | $0.00 | ||||||
16 | Drain Down Pit | 3 | Each | $1,800.00 | $5,400.00 | $0.00 | $0.00 | ||||||
17 | Electrical | 1 | L.S. | $276,000.00 | $276,000.00 | $0.00 | $0.00 | ||||||
18 | Campsites Pavement, 6" PCC | 6170 | S.Y. | $63.00 | $388,710.00 | $0.00 | $0.00 | ||||||
19 | Modified Subbase | 6200 | C.Y. | $83.00 | $514,600.00 | $0.00 | $0.00 | ||||||
20 | Subdrain, Longitudinal, (Shoulder), 4" | 8343 | L.F. | $5.00 | $41,715.00 | $0.00 | $0.00 | ||||||
21 | Subdrain Outlet, DR-306 | 46 | Each | $135.00 | $6,210.00 | $0.00 | $0.00 | ||||||
22 | Roadway Pavement, 7" PCC | 10120 | S.Y. | $72.00 | $728,640.00 | $0.00 | $0.00 | ||||||
23 | Parking Lot Pavement, 7" PCC | 5670 | S.Y. | $72.00 | $408,240.00 | $0.00 | $0.00 | ||||||
24 | Curb and Gutter, PCC, 2.5' | 95 | L.F. | $41.00 | $3,895.00 | $0.00 | $0.00 | ||||||
25 | Reinforced Concrete Pipe, 24" | 94 | L.F. | $200.00 | $18,800.00 | $0.00 | $0.00 | ||||||
26 | Reinforced Concrete Pipe Apron, 24" | 4 | Each | $2,000.00 | $8,000.00 | $0.00 | $0.00 | ||||||
27 | Precast Concrete Parking Wheel Stops | 2 | Each | $300.00 | $600.00 | $0.00 | $0.00 | ||||||
28 | Sidewalk, 6" PCC | 120 | S.Y. | $100.00 | $12,000.00 | $0.00 | $0.00 | ||||||
29 | Trail, 6" PCC | 1160 | S.Y. | $76.00 | $88,160.00 | $0.00 | $0.00 | ||||||
30 | ADA Campfire Ring with Pad | 41 | Each | $350.00 | $14,350.00 | $0.00 | $0.00 | ||||||
31 | Picnic Table, 6' Handicap Accessible | 41 | Each | $900.00 | $36,900.00 | $0.00 | $0.00 | ||||||
32 | Wood Fence, 8' | 573 | L.F. | $30.00 | $17,190.00 | $0.00 | $0.00 | ||||||
33 | Excavation, Class 10, Roadway and Borrow | 10000 | C.Y. | $11.00 | $110,000.00 | $0.00 | $0.00 | ||||||
34 | Seeding, Fertilizing, and Mulching | 16.68 | Acres | $3,000.00 | $50,040.00 | $0.00 | $0.00 | ||||||
35 | Filter Sock, 8" | 14280 | L.F. | $2.20 | $31,416.00 | $0.00 | $0.00 | ||||||
36 | 2 Stall Modern Bathroom/Shower (Wolverine) | 1 | Each | $136,000.00 | $136,000.00 | $0.00 | $0.00 | ||||||
37 | Check-In Station | 1 | L.S. | $55,000.00 | $55,000.00 | $0.00 | $0.00 | ||||||
38 | Vegetative Barrier | 1259 | L.F. | $110.00 | $138,490.00 | $0.00 | $0.00 | ||||||
39 | Security Gate | 1 | L.S. | $35,000.00 | $35,000.00 | $0.00 | $0.00 | ||||||
40 | Signing | 58 | Each | $500.00 | $29,000.00 | $0.00 | $0.00 | ||||||
41 | Revetment, Class E | 852 | Tons | $62.00 | $52,824.00 | $0.00 | $0.00 | ||||||
42 | Detectable Warning Panel | 246 | S.F. | $55.00 | $13,530.00 | $0.00 | $0.00 | ||||||
43 | Furnish and Place 3' Boulders (Minimum 2.5 Ton Each) | 22 | Each | $450.00 | $9,900.00 | $0.00 | $0.00 | ||||||
44 | NPDES General Permit #2 & SWPPP | 1 | L.S. | $8,000.00 | $8,000.00 | $0.00 | $0.00 | ||||||
45 | Bollards | 7 | Each | $1,000.00 | $7,000.00 | $0.00 | $0.00 | ||||||
46 | Construction Staking | 1 | L.S. | $57,600.00 | $57,600.00 | $0.00 | $0.00 | ||||||
47 | Traffic Control | 1 | L.S. | $4,000.00 | $4,000.00 | $0.00 | $0.00 | ||||||
48 | Mobilization | 1 | L.S. | $334,000.00 | $334,000.00 | $0.00 | $0.00 | ||||||
$4,241,215.00 | $0.00 | $0.00 | |||||||||||
Meco-Henne Contracting Inc, Omaha, NE
4/25/2024