Bids For: | Location: | Pammel State Park | Date: 6/18/2020 | Project No. |
Whitetopping | County: | MADISON | Time: 11:00 a.m. | 20-05-61-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $1,100,000.00 | Contractor: | Wicks Construction Inc | Concrete Technologies Inc. | Iowa Civil Contracting, Inc. | |||||||||
Funding Source: 100% Park & Institutional Road Fund, | 2201 Hwy 9 | 1001 SE 37th St | 1106 3rd St | ||||||||||
Decorah IA 52101 | Grimes IA 50111 | Victor IA 52347 | |||||||||||
Plan Sets Requested: 2 | Quantities | 563-382-2325 | 515-252-1650 | 319-647-3561 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | 2102 - SPECIAL BACKFILL (SUBBASE) | 720 | Tons | $26.00 | $18,720.00 | $26.25 | $18,900.00 | $30.00 | $21,600.00 | ||||
2 | 2102 - EMBANKMENT-IN-PLACE, CONTRACTOR FURNISHED | 843 | C.Y. | $28.00 | $23,604.00 | $14.75 | $12,434.25 | $50.00 | $42,150.00 | ||||
3 | 2102 - EXCAVATION, CLASS 10, ROADWAY AND BORROW | 218 | C.Y. | $15.00 | $3,270.00 | $14.75 | $3,215.50 | $32.00 | $6,976.00 | ||||
4 | 2301 - STD/S-F PCC PAV'T, CL C CL 3, 6" | 809 | S.Y. | $60.45 | $48,904.05 | $58.75 | $47,528.75 | $53.00 | $42,877.00 | ||||
5 | 2310 PORTLAND CEMENT CONCRETE OVERLAY, FURNISH ONLY | 2084 | C.Y. | $130.00 | $270,920.00 | $132.00 | $275,088.00 | $150.00 | $312,600.00 | ||||
6 | 2310 PORTLAND CEMENT CONCRETE OVERLAY, PLACEMENT ONLY (WHITE TOPPING) | 13638 | S.Y. | $7.83 | $106,785.54 | $16.85 | $229,800.30 | $27.00 | $368,226.00 | ||||
7 | 2310 - PAVEMENT INTERLAYER GEOTEXTILE | 13638 | S.Y. | $2.50 | $34,095.00 | $2.15 | $29,321.70 | $3.00 | $40,914.00 | ||||
8 | 2312 - GRANULAR SURF ON RD, CL A CR STONE | 90 | Tons | $28.00 | $2,520.00 | $26.25 | $2,362.50 | $50.00 | $4,500.00 | ||||
9 | 2401 - RMVL OF EXIST STRUCT | 1 | L.S. | $4,000.00 | $4,000.00 | $2,100.00 | $2,100.00 | $4,000.00 | $4,000.00 | ||||
10 | 2416 - APRON, CONC, 18" | 1 | Each | $1,000.00 | $1,000.00 | $1,890.00 | $1,890.00 | $4,000.00 | $4,000.00 | ||||
11 | 2416 - CULV, CONC RDWY PIPE, 18" | 494 | L.F. | $55.00 | $27,170.00 | $54.50 | $26,923.00 | $440.00 | $217,360.00 | ||||
12 | 2435 - INTAKE, SW-507 | 13 | Each | $3,600.00 | $46,800.00 | $4,200.00 | $54,600.00 | $22,700.00 | $295,100.00 | ||||
13 | 2435 - INTAKE, SW-511 | 3 | Each | $3,600.00 | $10,800.00 | $3,675.00 | $11,025.00 | $15,000.00 | $45,000.00 | ||||
14 | 2507 - ENGINEER FABRIC | 529 | S.Y. | $3.00 | $1,587.00 | $4.25 | $2,248.25 | $6.30 | $3,332.70 | ||||
15 | 2507 - REVETMENT, CLASS E | 200 | Tons | $100.00 | $20,000.00 | $68.25 | $13,650.00 | $154.00 | $30,800.00 | ||||
16 | 2507 - EROSION STONE | 45 | Tons | $36.00 | $1,620.00 | $42.00 | $1,890.00 | $96.00 | $4,320.00 | ||||
17 | 2510 - REMOVAL OF PAVEMENT | 1630 | S.Y. | $6.00 | $9,780.00 | $68.25 | $111,247.50 | $12.30 | $20,049.00 | ||||
18 | 2511 - REMOVE/REPLACE SIDEWALK, PCC, 5" | 134 | S.Y. | $80.00 | $10,720.00 | $127.00 | $17,018.00 | $80.00 | $10,720.00 | ||||
19 | 2526 - CONSTRUCTION SURVEY | 1 | L.S. | $28,000.00 | $28,000.00 | $15,750.00 | $15,750.00 | $11,800.00 | $11,800.00 | ||||
20 | 2528 - TRAFFIC CONTROL | 1 | L.S. | $5,000.00 | $5,000.00 | $4,725.00 | $4,725.00 | $4,000.00 | $4,000.00 | ||||
21 | 2533 - MOBILIZATION | 1 | L.S. | $35,000.00 | $35,000.00 | $59,000.00 | $59,000.00 | $146,000.00 | $146,000.00 | ||||
22 | 2601 - SEED+FERTILIZE (RURAL) | 1.5 | Acres | $1,750.00 | $2,625.00 | $1,840.00 | $2,760.00 | $1,750.00 | $2,625.00 | ||||
23 | 2601 - SLOPE PROTECTION, WOOD EXCELSIOR | 525 | SQ. | $13.80 | $7,245.00 | $14.50 | $7,612.50 | $13.80 | $7,245.00 | ||||
24 | 2602 - GRATE INTAKE SEDIMENT FILTER BAG | 16 | Each | $130.00 | $2,080.00 | $136.50 | $2,184.00 | $130.00 | $2,080.00 | ||||
$722,245.59 | $953,274.25 | $1,648,274.70 | |||||||||||