IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Stone State Park  Date: 11/15/2018  Project No.  
  D1FY19-3 Lodge & Shelter Repairs  County:   WOODBURY  Time: 11:00 a.m.  19-01-97-01

 

 
1
2
3
Estimated Cost: $120,000.00
Contractor: 
L & L Builders Co.W. A. Klinger, L.L.C.
Funding Source: 100% REAP-Parks Maintenance and Operations , 2205 4th St
2015 E. 7th St.

Sioux City IA  51101Sioux City IA  51101  
Plan Sets Requested: 0
Quantities
7122550657712-277-3900
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1DEMOLITION & SALVAGE1L.S.$1,060.00$1,060.00 $0.00$0.00 $0.00 
2LODGE REPAIR1L.S.$41,025.00$41,025.00 $118,057.00$118,057.00 $0.00 
3SHELTER REPAIR1L.S.$56,050.00$56,050.00 $27,753.00$27,753.00 $0.00 
4MOBILIZATION1L.S.$5,200.00$5,200.00 $0.00$0.00 $0.00 
      $103,335.00  $145,810.00  $0.00 
Alternate        
5PORTAL REPAIR1L.S.$12,850.00$12,850.00 $11,865.00$11,865.00 $0.00 
      $116,185.00  $157,675.00  $0.00 
 



 

5/24/2019