IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Lake Macbride | Date: 6/18/2020 | Project No. |
| Boat Slips | County: | JOHNSON | Time: 3:00 p.m. | 19-06-52-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $56,000.00 | Contractor: | Triple B Construction | CAJ Enterprises, Inc. | Boulder Contracting LLC | |||||||||
| Funding Source: 100% Marine Fuel Tax -Minors, | 710 Ayres Progress Dr | 263 260th St | 606 E 1st St | ||||||||||
| Wilton IA 52778 | West Branch IA 52358 | Grundy Center IA 50638 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-732-3478 | 319-643-7487 | 319-242-2182 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $4,000.00 | $4,000.00 | $3,800.00 | $3,800.00 | $8,000.00 | $8,000.00 | ||||
| 2 | Demolition | 1 | L.S. | $10,000.00 | $10,000.00 | $4,000.00 | $4,000.00 | $8,700.00 | $8,700.00 | ||||
| 3 | Sheet Piling | 94 | L.F. | $390.00 | $36,660.00 | $564.00 | $53,016.00 | $485.00 | $45,590.00 | ||||
| 4 | Revetment, Class E | 120 | Tons | $61.50 | $7,380.00 | $48.00 | $5,760.00 | $55.00 | $6,600.00 | ||||
| 5 | Special Backfill | 40 | Tons | $30.00 | $1,200.00 | $48.00 | $1,920.00 | $50.00 | $2,000.00 | ||||
| 6 | PCC Sidewalk, 6" Thick Reinforced | 112 | S.Y. | $57.00 | $6,384.00 | $49.50 | $5,544.00 | $83.00 | $9,296.00 | ||||
| 7 | Handrails | 32 | L.F. | $330.00 | $10,560.00 | $128.13 | $4,100.16 | $183.00 | $5,856.00 | ||||
| 8 | Pea Gravel | 16 | Tons | $68.00 | $1,088.00 | $75.00 | $1,200.00 | $187.00 | $2,992.00 | ||||
| 9 | Handicap Parking | 1 | L.S. | $650.00 | $650.00 | $1,100.00 | $1,100.00 | $750.00 | $750.00 | ||||
| 10 | Site Restoration | 1 | L.S. | $1,500.00 | $1,500.00 | $3,500.00 | $3,500.00 | $3,750.00 | $3,750.00 | ||||
| $79,422.00 | $83,940.16 | $93,534.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $56,000.00 | Contractor: | Miller Trucking & Excavating | Eastern Iowa Excavating & Concrete, LLC | ||||||||||
| Funding Source: 100% Marine Fuel Tax -Minors, | 3303 John Deere Road | 121 Nixon St SE | |||||||||||
| Silvis IL 61282 | Cascade IA 52033 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 309-755-7644 | 563-852-5120 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $5,000.00 | $5,000.00 | $33,500.00 | $33,500.00 | $0.00 | |||||
| 2 | Demolition | 1 | L.S. | $4,500.00 | $4,500.00 | $13,500.00 | $13,500.00 | $0.00 | |||||
| 3 | Sheet Piling | 94 | L.F. | $575.00 | $54,050.00 | $525.00 | $49,350.00 | $0.00 | |||||
| 4 | Revetment, Class E | 120 | Tons | $65.00 | $7,800.00 | $51.25 | $6,150.00 | $0.00 | |||||
| 5 | Special Backfill | 40 | Tons | $30.00 | $1,200.00 | $39.00 | $1,560.00 | $0.00 | |||||
| 6 | PCC Sidewalk, 6" Thick Reinforced | 112 | S.Y. | $90.00 | $10,080.00 | $66.25 | $7,420.00 | $0.00 | |||||
| 7 | Handrails | 32 | L.F. | $250.00 | $8,000.00 | $138.00 | $4,416.00 | $0.00 | |||||
| 8 | Pea Gravel | 16 | Tons | $120.00 | $1,920.00 | $131.00 | $2,096.00 | $0.00 | |||||
| 9 | Handicap Parking | 1 | L.S. | $700.00 | $700.00 | $785.00 | $785.00 | $0.00 | |||||
| 10 | Site Restoration | 1 | L.S. | $3,500.00 | $3,500.00 | $4,500.00 | $4,500.00 | $0.00 | |||||
| $96,750.00 | $123,277.00 | $0.00 | |||||||||||