IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Deer Creek Wildlife Management Area (WMA) | Date: 2/20/2020 | Project No. |
Building Site Demolition | County: | PLYMOUTH | Time: 3:00 p.m. | 19-01-75-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $40,000.00 | Contractor: | Schoon Construction and Excavation, LLC | Bohle Construction LLC | LA Carlson Contracting, Inc. | |||||||||
Funding Source: 100% REAP Land Management, | 5047 Hwy 3 | 320 E 1st St | 20984 C-43 | ||||||||||
Cherokee IA 51012 | Kingsley IA 51028 | Merrill IA 51038 | |||||||||||
Plan Sets Requested: 0 | Quantities | 7122256224 | 7123782364 | 7129470002 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $2,700.00 | $2,700.00 | $2,700.00 | $2,700.00 | $2,500.00 | $2,500.00 | ||||
2 | Asbestos Removal & Disposal (per report) | 1 | L.S. | $10,500.00 | $10,500.00 | $9,245.00 | $9,245.00 | $9,500.00 | $9,500.00 | ||||
3 | Structures/Foundations Demolition & Disposal | 1 | L.S. | $11,500.00 | $11,500.00 | $21,900.00 | $21,900.00 | $27,350.00 | $27,350.00 | ||||
4 | Miscellaneous Debris Removal | 1 | L.S. | $6,500.00 | $6,500.00 | $2,500.00 | $2,500.00 | $8,000.00 | $8,000.00 | ||||
5 | Well and Cistern Plugging | 1 | L.S. | $800.00 | $800.00 | $2,000.00 | $2,000.00 | $1,500.00 | $1,500.00 | ||||
$32,000.00 | $38,345.00 | $48,850.00 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $40,000.00 | Contractor: | BD Construction Services LLC | Jeppesen Gravel | Midwest Mechanical Industrial Services | |||||||||
Funding Source: 100% REAP Land Management, | 2410 W 11th St PO Box 1375 | 5857 100th St | 2602 Niagra Trl | ||||||||||
Spencer IA 51301 | Sibley IA 51249 | Logan IA 51546 | |||||||||||
Plan Sets Requested: 0 | Quantities | 7123631499 | 7124610630 | 7126442711 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $3,000.00 | $3,000.00 | $9,500.00 | $9,500.00 | $5,000.00 | $5,000.00 | ||||
2 | Asbestos Removal & Disposal (per report) | 1 | L.S. | $9,500.00 | $9,500.00 | $9,000.00 | $9,000.00 | $23,650.00 | $23,650.00 | ||||
3 | Structures/Foundations Demolition & Disposal | 1 | L.S. | $30,000.00 | $30,000.00 | $26,000.00 | $26,000.00 | $22,600.00 | $22,600.00 | ||||
4 | Miscellaneous Debris Removal | 1 | L.S. | $8,500.00 | $8,500.00 | $7,000.00 | $7,000.00 | $3,500.00 | $3,500.00 | ||||
5 | Well and Cistern Plugging | 1 | L.S. | $2,000.00 | $2,000.00 | $3,000.00 | $3,000.00 | $2,000.00 | $2,000.00 | ||||
$53,000.00 | $54,500.00 | $56,750.00 | |||||||||||
7 | 8 | 9 | |||||||||||
Estimated Cost: $40,000.00 | Contractor: | Blumer Excavating Co LLC | Bridge City Investments dba Environmental Edge LLC | C & D Services | |||||||||
Funding Source: 100% REAP Land Management, | 3530 Noble Ave | 2801 Roemer Ave | 33609 260th St | ||||||||||
Osage IA 50461 | Ottumwa IA 52501 | LeMars IA 51031 | |||||||||||
Plan Sets Requested: 0 | Quantities | 6418327407 | 6412264483 | 7125391639 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $1,500.00 | $1,500.00 | $6,675.00 | $6,675.00 | $1,750.00 | $1,750.00 | ||||
2 | Asbestos Removal & Disposal (per report) | 1 | L.S. | $8,850.00 | $8,850.00 | $11,195.00 | $11,195.00 | $21,004.17 | $21,004.17 | ||||
3 | Structures/Foundations Demolition & Disposal | 1 | L.S. | $46,700.00 | $46,700.00 | $47,000.00 | $47,000.00 | $21,500.00 | $21,500.00 | ||||
4 | Miscellaneous Debris Removal | 1 | L.S. | $3,000.00 | $3,000.00 | $1,400.00 | $1,400.00 | $23,845.83 | $23,845.83 | ||||
5 | Well and Cistern Plugging | 1 | L.S. | $2,500.00 | $2,500.00 | $800.00 | $800.00 | $600.00 | $600.00 | ||||
$62,550.00 | $67,070.00 | $68,700.00 | |||||||||||
4/30/2024