IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Black Hawk Lake | Date: 1/23/2020 | Project No. |
| Ice House Point Shoreline Armoring Phase II | County: | SAC | Time: 3:00 p.m. | 20-01-81-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $46,000.00 | Contractor: | Richards Construction Co., Inc. | Reding's Gravel & Excavating Co. Inc. | Iowa Technology Solutions LLC | |||||||||
| Funding Source: 100% Marine Fuel Tax, | 2721 Sierra Ave | 1420 East Richland St | 926 Main St | ||||||||||
| Sac City IA 50583 | Storm Lake IA 50588 | Manson IA 50563 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 7126624421 | 7127324059 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $2,000.00 | $2,000.00 | $2,850.00 | $2,850.00 | $5,000.00 | $5,000.00 | ||||
| 2 | Class "D" Fieldstone Revetment | 575 | Tons | $59.00 | $33,925.00 | $68.55 | $39,416.25 | $75.00 | $43,125.00 | ||||
| 3 | Site Restoration & Hydraulic Seeding | 1 | L.S. | $2,000.00 | $2,000.00 | $3,200.00 | $3,200.00 | $5,000.00 | $5,000.00 | ||||
| $37,925.00 | $45,466.25 | $53,125.00 | |||||||||||