 Bids For:  Location:   Spirit Lake Fish Hatchery  Date: 9/20/2018  Project No.  
  Discharge Line Replacement  County:   DICKINSON  Time: 3:00 p.m.  19-01-30-02

 

 
1
2
3
Estimated Cost: $84,000.00
Contractor: 
Cory Juergens Construction LLCValley Contracting, Inc.
Funding Source: 75% Cash Donation, 25% REAP Land Management, 219 W 2 St S
1850 Hwy 4

Estherville IA  51334Estherville IA  51334  
Plan Sets Requested: 0
Quantities
712380018417123624969
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$5,000.00$5,000.00 $1,900.00$1,900.00 $0.00 
2Clear & Grub Trees & Vegetation1L.S.$2,000.00$2,000.00 $3,050.00$3,050.00 $0.00 
3Saw Cut Pavement120L.F.$4.00$480.00 $7.00$840.00 $0.00 
4Pavement Removal172S.Y.$8.00$1,376.00 $10.00$1,720.00 $0.00 
56" PCC Paving130S.Y.$47.00$6,110.00 $52.00$6,760.00 $0.00 
6Granular Sub Base for PCC50Tons$14.00$700.00 $20.00$1,000.00 $0.00 
7Replace Pipe with 8" SDR 35 C900 PVC Pipe1L.S.$2,800.00$2,800.00 $3,000.00$3,000.00 $0.00 
8Connect 8" PVC Pipe to Hatchery Building & Existing Pipe4Each$500.00$2,000.00 $750.00$3,000.00 $0.00 
9Connect 12 PVC Pipe to Existing Manhole1Each$1,500.00$1,500.00 $1,100.00$1,100.00 $0.00 
104000 PSI 6" PCC with #4 Bar 18" c-c42S.Y.$75.00$3,150.00 $60.00$2,520.00 $0.00 
11Replace 12" VCP Pipe with DR 25 C900 PVC Discharge Pipe471L.F.$26.00$12,246.00 $52.00$24,492.00 $0.00 
12Granular Pipe Bedding52Tons$22.00$1,144.00 $32.00$1,664.00 $0.00 
1312" Direct Bury Gate Valve2Each$3,000.00$6,000.00 $2,350.00$4,700.00 $0.00 
14Remove Existing Piping & PCC Structures1L.S.$2,500.00$2,500.00 $3,000.00$3,000.00 $0.00 
15Bar Guard for End of Pipe1Each$750.00$750.00 $250.00$250.00 $0.00 
16Reshape/Repair Dike (Imported Fill)100C.Y.$40.00$4,000.00 $30.00$3,000.00 $0.00 
17DOT Class D Revetment Stone270Tons$65.00$17,550.00 $47.00$12,690.00 $0.00 
189" to 18" Fieldstone for Pipe Outlet & Shoreline15Tons$50.00$750.00 $40.00$600.00 $0.00 
19Replace Existing Pipe with 18" CMP Pipe (between ponds)25L.F.$26.00$650.00 $44.00$1,100.00 $0.00 
20Erosion Control1L.S.$2,000.00$2,000.00 $600.00$600.00 $0.00 
21Dewatering (for trench)1L.S.$1,000.00$1,000.00 $1,600.00$1,600.00 $0.00 
22Site Restoration/Seeding1L.S.$4,000.00$4,000.00 $2,100.00$2,100.00 $0.00 
      $77,706.00  $80,686.00  $0.00 
 



 