IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | State Forest Nursery | Date: 6/21/2018 | Project No. |
| Restroom Renovation | County: | STORY | Time: 11:00 a.m. | 19-02-85-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $124,000.00 | Contractor: | Iron Hill Construction, LLC | Story Construction Co. | R H Grabau Construction Inc | |||||||||
| Funding Source: 100% REAP OS Acquisition & Development, | 2800 University Ave, Ste 128 | 2810 Wakefield Circle | 871 "P" Ave PO Box | ||||||||||
| West Des Moines, IA 50266 | Ames IA 50010 | Boone IA 50036 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 515-720-7263 | 515-432-4358 | (515) 432-6935 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | DEMOLITION | 1 | L.S. | $7,420.00 | $7,420.00 | $1,700.00 | $1,700.00 | $1,800.00 | $1,800.00 | ||||
| 2 | STOOP FOOTING | 1 | L.S. | $3,195.00 | $3,195.00 | $1,100.00 | $1,100.00 | $1,000.00 | $1,000.00 | ||||
| 3 | RESTROOM REMODEL | 1 | L.S. | $38,230.00 | $38,230.00 | $29,000.00 | $29,000.00 | $40,000.00 | $40,000.00 | ||||
| 4 | KITCHENETTE REMODEL | 1 | L.S. | $6,105.00 | $6,105.00 | $29,255.00 | $29,255.00 | $4,000.00 | $4,000.00 | ||||
| 5 | RESTORATION | 1 | L.S. | $630.00 | $630.00 | $1,000.00 | $1,000.00 | $14,800.00 | $14,800.00 | ||||
| 6 | MOBILIZATION | 1 | L.S. | $6,500.00 | $6,500.00 | $1,000.00 | $1,000.00 | $10,000.00 | $10,000.00 | ||||
| $62,080.00 | $63,055.00 | $71,600.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $124,000.00 | Contractor: | Vieco Dev. & Construction Co. Inc. | Edge Commercial | The Wilson Group, Inc. | |||||||||
| Funding Source: 100% REAP OS Acquisition & Development, | 5180 SE 70th Rd | 3155 SE Miehe Drive #2 | 1606 W Main Street | ||||||||||
| Saint Joseph MO 64507 | Grimes IA 50111 | Greenwood MO 64034 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 816-232-9044 | 515-986-2229 | 816-537-0212 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | DEMOLITION | 1 | L.S. | $8,500.00 | $8,500.00 | $6,000.00 | $6,000.00 | $4,224.00 | $4,224.00 | ||||
| 2 | STOOP FOOTING | 1 | L.S. | $2,800.00 | $2,800.00 | $5,000.00 | $5,000.00 | $13,166.00 | $13,166.00 | ||||
| 3 | RESTROOM REMODEL | 1 | L.S. | $54,002.00 | $54,002.00 | $30,000.00 | $30,000.00 | $60,847.00 | $60,847.00 | ||||
| 4 | KITCHENETTE REMODEL | 1 | L.S. | $8,200.00 | $8,200.00 | $30,000.00 | $30,000.00 | $25,952.00 | $25,952.00 | ||||
| 5 | RESTORATION | 1 | L.S. | $8,700.00 | $8,700.00 | $15,000.00 | $15,000.00 | $4,252.00 | $4,252.00 | ||||
| 6 | MOBILIZATION | 1 | L.S. | $4,200.00 | $4,200.00 | $15,970.00 | $15,970.00 | $4,245.00 | $4,245.00 | ||||
| $86,402.00 | $101,970.00 | $112,686.00 | |||||||||||
12/21/2025