IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Gull Point State Park  Date: 5/17/2018  Project No.  
  Gull Point Residence Window & Door Replacement  County:   DICKINSON  Time: 3:00 p.m.  17-01-30-02

 

 
1
2
3
Estimated Cost: $26,500.00
Contractor: 
Wilcon Construction, IncMidstates Builder, Inc.
Funding Source: 100% Infrastructure, 1512 7th Ave S
520 S Grand Ave

St James MN  56081Spencer IA  51301  
Plan Sets Requested: 0
Quantities
507-375-5464712-262-2227
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$250.00$250.00 $6,115.00$6,115.00 $0.00 
2Remove & Replace Windows1L.S.$34,130.00$34,130.00 $29,946.00$29,946.00 $0.00 
3Remove & Replace Storm Doors1L.S.$4,800.00$4,800.00 $6,481.00$6,481.00 $0.00 
4Interior Trim Work & Staining1L.S.$1,103.00$1,103.00 $5,500.00$5,500.00 $0.00 
5Exterior Trim Work & Painting1L.S.$2,315.00$2,315.00 $10,870.00$10,870.00 $0.00 
      $42,598.00  $58,912.00  $0.00 
 



 

3/28/2024