IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Viking Lake State Park | Date: 7/18/2019 | Project No. |
| Sediment Ponds | County: | MONTGOMERY | Time: 11:00 a.m. | 18-04-69-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $140,000.00 | Contractor: | JNC Construction, LLC | |||||||||||
| Funding Source: 100% Lake Restoration, | 609 3rd St | ||||||||||||
| Clearfield IA 50840 | |||||||||||||
| Plan Sets Requested: 3 | Quantities | 6413444119 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Clearing | 13.5 | Acres | $1,200.00 | $16,200.00 | $0.00 | $0.00 | ||||||
| 2 | Fill in place | 30888 | C.Y. | $2.00 | $61,776.00 | $0.00 | $0.00 | ||||||
| 3 | Core trench | 5326 | C.Y. | $2.50 | $13,315.00 | $0.00 | $0.00 | ||||||
| 4 | 6" Pipe | 1278 | L.F. | $14.00 | $17,892.00 | $0.00 | $0.00 | ||||||
| 5 | Trash rack | 11 | Each | $100.00 | $1,100.00 | $0.00 | $0.00 | ||||||
| 6 | 4x4 Antiseep | 34 | Each | $200.00 | $6,800.00 | $0.00 | $0.00 | ||||||
| 7 | Seeding | 8 | Acres | $1,500.00 | $12,000.00 | $0.00 | $0.00 | ||||||
| 8 | Control structure | 1 | Each | $2,000.00 | $2,000.00 | $0.00 | $0.00 | ||||||
| 9 | 6" Gate valve | 1 | Each | $850.00 | $850.00 | $0.00 | $0.00 | ||||||
| 10 | Animal Guard | 1 | Each | $50.00 | $50.00 | $0.00 | $0.00 | ||||||
| 11 | Mobilization | 1 | L.S. | $5,000.00 | $5,000.00 | $0.00 | $0.00 | ||||||
| 12 | 8" Filter sock | 2025 | L.F. | $2.00 | $4,050.00 | $0.00 | $0.00 | ||||||
| 13 | Construction Staking | 1 | L.S. | $14,700.00 | $14,700.00 | $0.00 | $0.00 | ||||||
| $155,733.00 | $0.00 | $0.00 | |||||||||||
4/7/2026