| Bids For: | Location: | State Forrest Nursery | Date: 11/15/2018 | Project No. |
| Irrigation System | County: | STORY | Time: 11:00 a.m. | 18-02-85-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $126,000.00 | Contractor: | Vicker Drilling, LLC | On Track Construction, LLC | ||||||||||
| Funding Source: 100% REAP OS Acquisition & Development, | 2151 S. Cherry St. Rd, | 1316 6th St. Suite 109 | |||||||||||
| Creston IA 50801 | Nevada IA 52632 | ||||||||||||
| Plan Sets Requested: 3 | Quantities | 641-202-2728 | 888-850-0208 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | MOBILIZATION | 1 | L.S. | $2,000.00 | $2,000.00 | $20,000.00 | $20,000.00 | $0.00 | |||||
| 2 | 6" CI GATE VALVES | 3 | Each | $1,450.00 | $4,350.00 | $1,350.00 | $4,050.00 | $0.00 | |||||
| 3 | CONNECT 6" PVC WITH 8" CI PIPE AT PUMP HOUSE | 1 | L.S. | $850.00 | $850.00 | $828.00 | $828.00 | $0.00 | |||||
| 4 | 6" CI GATE VALVES WITH VALVE BOX & STEM EXTENSION | 2 | Each | $1,850.00 | $3,700.00 | $1,500.00 | $3,000.00 | $0.00 | |||||
| 5 | 4" CI GATE VALVES WITH VALVE BOX & STEM EXTENSION | 1 | Each | $1,125.00 | $1,125.00 | $1,400.00 | $1,400.00 | $0.00 | |||||
| 6 | 2" PLUG VALVES WITH VALVE BOX & STEM EXTENSION | 1 | Each | $1,125.00 | $1,125.00 | $1,300.00 | $1,300.00 | $0.00 | |||||
| 7 | 6" PVC DR 25 C900 PVC PIPE | 2077 | L.F. | $12.50 | $25,962.50 | $29.00 | $60,233.00 | $0.00 | |||||
| 8 | 4" PVC DR 25 C900 PVC PIPE | 569 | L.F. | $10.25 | $5,832.25 | $26.00 | $14,794.00 | $0.00 | |||||
| 9 | 2" PVC DR 25 C900 PVC PIPE | 765 | L.F. | $7.25 | $5,546.25 | $24.00 | $18,360.00 | $0.00 | |||||
| 10 | 6"x 6"x 2" Ts INSTALLED | 17 | Each | $1,425.00 | $24,225.00 | $885.00 | $15,045.00 | $0.00 | |||||
| 11 | 6" X 6" X 2" X 2" CROSS | 12 | Each | $1,425.00 | $17,100.00 | $1,120.00 | $13,440.00 | $0.00 | |||||
| 12 | 4" X 4" X 2" X 2" CROSS | 5 | Each | $1,250.00 | $6,250.00 | $1,100.00 | $5,500.00 | $0.00 | |||||
| 13 | 4" X 4" X 2" Ts INSTALLED | 5 | Each | $1,050.00 | $5,250.00 | $945.00 | $4,725.00 | $0.00 | |||||
| 14 | CONNECT 2" DRAIN LINE TO MANHOLE | 1 | Each | $950.00 | $950.00 | $775.00 | $775.00 | $0.00 | |||||
| 15 | SITE RESTORATION | 1 | L.S. | $1,000.00 | $1,000.00 | $17,500.00 | $17,500.00 | $0.00 | |||||
| $105,266.00 | $180,950.00 | $0.00 | |||||||||||