IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Lake Geode  Date: 10/18/2018  Project No.  
  Valve Replacement Plan  County:   HENRY  Time: 11:00 a.m.  18-06-44-02

 

 
1
2
3
Estimated Cost: $250,000.00
Contractor: 
Engineering & Construction Innovations, Inc.Miller Trucking & ExcavatingMeyers Driveway
Funding Source: 100% Lake Restoration, 7012 6th Street North
3303 John Deere Rd
1000 Cedar Street
PO Box 488
Oakdale MN  55128Silvis IL  61282Keokuk IA  52132
Plan Sets Requested: 3
Quantities
651-298-9111(309) 755-7644319-524-7329
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Efflorescence Removal64S.F.$35.00$2,240.00 $350.00$22,400.00 $300.00$19,200.00 
2Concrete Repair400S.F.$47.00$18,800.00 $80.00$32,000.00 $35.00$14,000.00 
3Remaining Work1L.S.$136,860.00$136,860.00 $171,500.00$171,500.00 $230,000.00$230,000.00 
      $157,900.00  $225,900.00  $263,200.00 
 
 
4
5
6
Estimated Cost: $250,000.00
Contractor: 
Carl A Nelson & CoMinturn Inc
Funding Source: 100% Lake Restoration, 1815 Des Moines Ave
144 W. Front Street

Burlington IA  52601Brooklyn IA  52211  
Plan Sets Requested: 3
Quantities
(319) 754-8415641-455-0331
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Efflorescence Removal64S.F.$13.50$864.00 $50.00$3,200.00 $0.00 
2Concrete Repair400S.F.$45.75$18,300.00 $150.00$60,000.00 $0.00 
3Remaining Work1L.S.$286,075.00$286,075.00 $266,000.00$266,000.00 $0.00 
      $305,239.00  $329,200.00  $0.00 
 



 