IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Hickory Grove Lake | Date: 12/21/2017 | Project No. |
| Phase 1 Shoreline Armoring Rebid | County: | STORY | Time: 11.00A.M | 16-02-85-04 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $130,000.00 | Contractor: | Gehrke Inc. | Customized Environmental Solutions dba Telum | Con-Struct, Inc. | |||||||||
| Funding Source: 75% Lake Restoration, 25% Other, | 1405 21st Ave PO Box 228 | 2045 Grand Ave, Ste A | 305 Dayton Ave | ||||||||||
| Eldora IA 50627 | West Des Moines IA 50265 | Ames IA 50010 | |||||||||||
| Plan Sets Requested: 6 | Quantities | 641-858-3821 | 515-230-1214 | 515-232-4663 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $12,000.00 | $12,000.00 | $10,000.00 | $10,000.00 | $6,500.00 | $6,500.00 | ||||
| 2 | Class E Revetment | 1348 | Tons | $52.00 | $70,096.00 | $55.40 | $74,679.20 | $55.00 | $74,140.00 | ||||
| 3 | Macadam Stone | 160 | Tons | $40.00 | $6,400.00 | $42.35 | $6,776.00 | $39.50 | $6,320.00 | ||||
| 4 | Engineering Fabric | 2311 | S.Y. | $3.00 | $6,933.00 | $2.45 | $5,661.95 | $2.00 | $4,622.00 | ||||
| 5 | Class A Crushed Stone | 336 | Tons | $29.50 | $9,912.00 | $38.65 | $12,986.40 | $31.00 | $10,416.00 | ||||
| 6 | 3/8" Minus Granular Surfacing | 127 | Tons | $25.00 | $3,175.00 | $30.90 | $3,924.30 | $26.00 | $3,302.00 | ||||
| 7 | Intake Structure Complete (East Game Area) | 1 | L.S. | $2,250.00 | $2,250.00 | $1,550.00 | $1,550.00 | $7,775.00 | $7,775.00 | ||||
| 8 | Intake Structure Complete (South Game Area) | 1 | L.S. | $3,225.00 | $3,225.00 | $1,550.00 | $1,550.00 | $7,075.00 | $7,075.00 | ||||
| 9 | 6" Corr. Non Perf Tubing | 140 | L.F. | $15.00 | $2,100.00 | $19.00 | $2,660.00 | $20.00 | $2,800.00 | ||||
| 10 | 24" Dia CMP Ga | 16 | L.F. | $68.75 | $1,100.00 | $200.00 | $3,200.00 | $171.00 | $2,736.00 | ||||
| 11 | Seeding, Fertilizing & Mulch | 1 | L.S. | $12,000.00 | $12,000.00 | $6,500.00 | $6,500.00 | $9,500.00 | $9,500.00 | ||||
| $129,191.00 | $129,487.85 | $135,186.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $130,000.00 | Contractor: | Cole Excavating | Jasper Construction Services, Inc. | Synergy Contracting, LLC | |||||||||
| Funding Source: 75% Lake Restoration, 25% Other, | 10471 Packard Ave | 928 N 19th Ave E | 1120 2nd St NE | ||||||||||
| Greene IA 50636 | Newton IA 50208 | Bondurant IA 50035 | |||||||||||
| Plan Sets Requested: 6 | Quantities | 641-823-4700 | 641-792-8650 | 515-957-4907 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $14,500.00 | $14,500.00 | $17,500.00 | $17,500.00 | $24,000.00 | $24,000.00 | ||||
| 2 | Class E Revetment | 1348 | Tons | $56.50 | $76,162.00 | $65.00 | $87,620.00 | $85.00 | $114,580.00 | ||||
| 3 | Macadam Stone | 160 | Tons | $31.50 | $5,040.00 | $45.00 | $7,200.00 | $55.00 | $8,800.00 | ||||
| 4 | Engineering Fabric | 2311 | S.Y. | $4.00 | $9,244.00 | $2.10 | $4,853.10 | $2.00 | $4,622.00 | ||||
| 5 | Class A Crushed Stone | 336 | Tons | $27.50 | $9,240.00 | $32.00 | $10,752.00 | $40.00 | $13,440.00 | ||||
| 6 | 3/8" Minus Granular Surfacing | 127 | Tons | $20.00 | $2,540.00 | $20.00 | $2,540.00 | $32.00 | $4,064.00 | ||||
| 7 | Intake Structure Complete (East Game Area) | 1 | L.S. | $4,900.00 | $4,900.00 | $4,000.00 | $4,000.00 | $3,500.00 | $3,500.00 | ||||
| 8 | Intake Structure Complete (South Game Area) | 1 | L.S. | $5,750.00 | $5,750.00 | $3,000.00 | $3,000.00 | $3,500.00 | $3,500.00 | ||||
| 9 | 6" Corr. Non Perf Tubing | 140 | L.F. | $12.00 | $1,680.00 | $30.00 | $4,200.00 | $60.00 | $8,400.00 | ||||
| 10 | 24" Dia CMP Ga | 16 | L.F. | $48.00 | $768.00 | $12.00 | $192.00 | $100.00 | $1,600.00 | ||||
| 11 | Seeding, Fertilizing & Mulch | 1 | L.S. | $12,000.00 | $12,000.00 | $100.00 | $100.00 | $10,000.00 | $10,000.00 | ||||
| $141,824.00 | $141,957.10 | $196,506.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $130,000.00 | Contractor: | J & K Contracting LLC | |||||||||||
| Funding Source: 75% Lake Restoration, 25% Other, | 1307 E Lincoln Way | ||||||||||||
| Ames IA 50010 | |||||||||||||
| Plan Sets Requested: 6 | Quantities | 515-233-5500 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $17,395.00 | $17,395.00 | $0.00 | $0.00 | ||||||
| 2 | Class E Revetment | 1348 | Tons | $82.00 | $110,536.00 | $0.00 | $0.00 | ||||||
| 3 | Macadam Stone | 160 | Tons | $66.00 | $10,560.00 | $0.00 | $0.00 | ||||||
| 4 | Engineering Fabric | 2311 | S.Y. | $1.00 | $2,311.00 | $0.00 | $0.00 | ||||||
| 5 | Class A Crushed Stone | 336 | Tons | $40.00 | $13,440.00 | $0.00 | $0.00 | ||||||
| 6 | 3/8" Minus Granular Surfacing | 127 | Tons | $32.00 | $4,064.00 | $0.00 | $0.00 | ||||||
| 7 | Intake Structure Complete (East Game Area) | 1 | L.S. | $14,235.00 | $14,235.00 | $0.00 | $0.00 | ||||||
| 8 | Intake Structure Complete (South Game Area) | 1 | L.S. | $12,000.00 | $12,000.00 | $0.00 | $0.00 | ||||||
| 9 | 6" Corr. Non Perf Tubing | 140 | L.F. | $59.00 | $8,260.00 | $0.00 | $0.00 | ||||||
| 10 | 24" Dia CMP Ga | 16 | L.F. | $445.00 | $7,120.00 | $0.00 | $0.00 | ||||||
| 11 | Seeding, Fertilizing & Mulch | 1 | L.S. | $12,800.00 | $12,800.00 | $0.00 | $0.00 | ||||||
| $212,721.00 | $0.00 | $0.00 | |||||||||||
Jasper Construction Services, Inc., Newton, IA
Customized Environmental Solutions dba Telum, West Des Moines, IA
Gehrke Inc., Eldora, IA