IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Pine Lake State Park  Date: 12/16/2021  Project No.  
  Beach Tunnel Repair  County:   HARDIN  Time: 3:00 p.m.  19-02-42-02

 

 
1
2
3
Estimated Cost: $54,000.00
Contractor: 
Boulder Contracting LLCPillar Inc.Peterson Contractors, Inc.
Funding Source: 100% Park & Institutional Road Fund, 606 E 1st St
PO Box 310
906 W 18th St, Bldg A
104 Black Hawk St
Grundy Center IA  50638Nevada IA  50201Reinbeck IA  50669
Plan Sets Requested: 0
Quantities
319243328551532179383195750796
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Demolition1L.S.$7,000.00$7,000.00 $15,000.00$15,000.00 $7,000.00$7,000.00 
2Mobilization1L.S.$7,500.00$7,500.00 $15,000.00$15,000.00 $17,500.00$17,500.00 
3Concrete Retaining Walls and Footings1L.S.$34,000.00$34,000.00 $30,000.00$30,000.00 $46,000.00$46,000.00 
4Stone Veneer and Caps1L.S.$25,500.00$25,500.00 $60,000.00$60,000.00 $55,000.00$55,000.00 
5Concrete Sidewalks, Stairs, and Subbase1L.S.$15,000.00$15,000.00 $15,000.00$15,000.00 $12,500.00$12,500.00 
      $89,000.00  $135,000.00  $138,000.00 
 



 