IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Hawkeye Wildlife Management Area | Date: 9/14/2017 | Project No. |
New Boat Ramp (Contract) | County: | JOHNSON | Time: 11:00 a.m. | 16-06-52-05 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $39,000.00 | Contractor: | Triple B Construction | Connolly Construction Inc | ||||||||||
Funding Source: 100% Marine Fuel Tax, | 2272 Spicer Ave | 18409 N Cascade Rd PO Box 68 | |||||||||||
Wilton IA 52778 | Peosta IA 52068 | ||||||||||||
Plan Sets Requested: 0 | Quantities | 563-299-2399 | 563-876-3225 | ||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $7,500.00 | $7,500.00 | $4,200.00 | $4,200.00 | $0.00 | |||||
2 | Clearing and Grubbing | 1 | L.S. | $2,950.00 | $2,950.00 | $2,300.00 | $2,300.00 | $0.00 | |||||
3 | Respread Rip-Rap | 1 | L.S. | $2,500.00 | $2,500.00 | $2,900.00 | $2,900.00 | $0.00 | |||||
4 | Excavation | 1 | L.S. | $5,400.00 | $5,400.00 | $3,500.00 | $3,500.00 | $0.00 | |||||
5 | Granular Subbase, Boat Ramp 6" Depth | 50 | Tons | $50.00 | $2,500.00 | $31.00 | $1,550.00 | $0.00 | |||||
6 | PCC Boat Ramp, 6" Reinforced | 106.6 | S.Y. | $75.00 | $7,995.00 | $290.00 | $30,914.00 | $0.00 | |||||
7 | PCC Grout | 10 | C.Y. | $200.00 | $2,000.00 | $310.00 | $3,100.00 | $0.00 | |||||
8 | Class A Road Stone - Access Road | 80 | Tons | $27.00 | $2,160.00 | $31.00 | $2,480.00 | $0.00 | |||||
$33,005.00 | $50,944.00 | $0.00 | |||||||||||
4/26/2024