IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Artesian Lake WMA | Date: 11/7/2019 | Project No. |
Water Control Structure Replacement | County: | CARROLL | Time: 3:00 pm | 18-02-14-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $30,000.00 | Contractor: | M & S Dirt Work | Richards Construction Co., Inc. | ||||||||||
Funding Source: 100% REAP OS Acquisition & Development, | 10742 Ivy Ave | 2721 Sierra Ave | |||||||||||
Breda IA 51436 | Sac City IA 50583 | ||||||||||||
Plan Sets Requested: 0 | Quantities | 7127902324 | 7126624421 | ||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $1,000.00 | $1,000.00 | $5,000.00 | $5,000.00 | $0.00 | |||||
2 | 18" Dual Wall Polypropylene Pipe | 50 | L.F. | $30.00 | $1,500.00 | $50.00 | $2,500.00 | $0.00 | |||||
3 | 18" Dual Wall Polypropylene Perforated Inlet Pipe | 17 | L.F. | $17.65 | $300.05 | $150.00 | $2,550.00 | $0.00 | |||||
4 | 6' Inline Water Control Structure | 1 | Each | $2,500.00 | $2,500.00 | $4,200.00 | $4,200.00 | $0.00 | |||||
5 | 6' X 6' Anti Seep Collars | 3 | Each | $300.00 | $900.00 | $500.00 | $1,500.00 | $0.00 | |||||
6 | Fire Protection Cover | 1 | Each | $1,800.00 | $1,800.00 | $2,400.00 | $2,400.00 | $0.00 | |||||
7 | Erosion Stone | 318 | Tons | $48.00 | $15,264.00 | $35.00 | $11,130.00 | $0.00 | |||||
8 | 18" CMP | 10 | L.F. | $60.00 | $600.00 | $65.00 | $650.00 | $0.00 | |||||
9 | Rodent Guard | 1 | Each | $70.00 | $70.00 | $150.00 | $150.00 | $0.00 | |||||
10 | Excavation | 1 | L.S. | $3,500.00 | $3,500.00 | $3,000.00 | $3,000.00 | $0.00 | |||||
11 | Imported Clay Fill | 45 | C.Y. | $30.00 | $1,350.00 | $40.00 | $1,800.00 | $0.00 | |||||
12 | Structure Demolition | 1 | L.S. | $3,500.00 | $3,500.00 | $4,000.00 | $4,000.00 | $0.00 | |||||
13 | Site Restoration | 1 | L.S. | $1,200.00 | $1,200.00 | $1,000.00 | $1,000.00 | $0.00 | |||||
$33,484.05 | $39,880.00 | $0.00 | |||||||||||
5/4/2024