| Bids For: | Location: | Sweet Marsh WMA | Date: 1/25/2018 | Project No. |
| Albright Wetland Development | County: | BREMER | Time: 3:00 PM | 18-03-09-04 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $96,000.00 | Contractor: | Nate Moeller Const LLC | Chad Heim Excavating & Trucking LLC | Kinman Co Inc. | |||||||||
| Funding Source: 100% REAP OS Acquisition & Development, | 706 7th Ave SW | 1920 Joy Ave | 3101 Kent Ave | ||||||||||
| Tripoli IA 50676 | Waverly IA 50677 | Oskaloosa IA 52577 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 319-882-3600 | 319-230-0153 | 641-660-0896 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $1,500.00 | $1,500.00 | $1,000.00 | $1,000.00 | $5,150.00 | $5,150.00 | ||||
| 2 | Excavation, Class 10 | 54314 | C.Y. | $1.45 | $78,755.30 | $1.45 | $78,755.30 | $1.32 | $71,694.48 | ||||
| 3 | Water Controll Structure, 6' | 2 | Each | $1,200.00 | $2,400.00 | $250.00 | $500.00 | $700.00 | $1,400.00 | ||||
| 4 | Water Control Structure, 5' | 1 | Each | $800.00 | $800.00 | $250.00 | $250.00 | $645.00 | $645.00 | ||||
| 5 | CMP Outlet With Rodent Guard, 6" Dia. 20LF | 3 | Each | $250.00 | $750.00 | $60.00 | $180.00 | $160.00 | $480.00 | ||||
| 6 | Tile, Non-perforated Plastic, 6" Dia. | 280 | L.F. | $1.80 | $504.00 | $2.00 | $560.00 | $5.50 | $1,540.00 | ||||
| 7 | Tile, Non-perforated Plastic, 5" Dia. | 55 | L.F. | $1.40 | $77.00 | $2.00 | $110.00 | $5.50 | $302.50 | ||||
| 8 | Tile, Non-perforated Plastic, 4" | 230 | L.F. | $1.20 | $276.00 | $2.00 | $460.00 | $4.50 | $1,035.00 | ||||
| 9 | CMP Inlet Structure With Guard, 20 LF | 3 | Each | $250.00 | $750.00 | $500.00 | $1,500.00 | $190.00 | $570.00 | ||||
| 10 | Erosion Stone | 8 | Tons | $25.00 | $200.00 | $15.00 | $120.00 | $23.76 | $190.08 | ||||
| 11 | Straw Mat | 176 | S.Y. | $1.85 | $325.60 | $2.00 | $352.00 | $1.50 | $264.00 | ||||
| 12 | Stabilizing Crop Seeding | 0.5 | Acres | $1,200.00 | $600.00 | $200.00 | $100.00 | $1,400.00 | $700.00 | ||||
| 13 | Construction Staking | 1 | L.S. | $3,000.00 | $3,000.00 | $7,500.00 | $7,500.00 | $7,500.00 | $7,500.00 | ||||
| $89,937.90 | $91,387.30 | $91,471.06 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $96,000.00 | Contractor: | David Ryan Construction | Faas Construction & Excavating | Blazek Corporation | |||||||||
| Funding Source: 100% REAP OS Acquisition & Development, | 3566 236th Ave | 3407 V18 Rd | 2005 Union Ave | ||||||||||
| Decorah IA 52101 | Brooklyn IA 52211 | Lawler IA 52154 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-735-5895 | 641-751-1075 | 563-238-7150 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $2,500.00 | $2,500.00 | $5,000.00 | $5,000.00 | $3,800.00 | $3,800.00 | ||||
| 2 | Excavation, Class 10 | 54314 | C.Y. | $1.57 | $85,272.98 | $1.56 | $84,729.84 | $1.60 | $86,902.40 | ||||
| 3 | Water Controll Structure, 6' | 2 | Each | $750.00 | $1,500.00 | $1,043.21 | $2,086.42 | $965.00 | $1,930.00 | ||||
| 4 | Water Control Structure, 5' | 1 | Each | $750.00 | $750.00 | $940.83 | $940.83 | $925.00 | $925.00 | ||||
| 5 | CMP Outlet With Rodent Guard, 6" Dia. 20LF | 3 | Each | $200.00 | $600.00 | $250.00 | $750.00 | $200.00 | $600.00 | ||||
| 6 | Tile, Non-perforated Plastic, 6" Dia. | 280 | L.F. | $3.50 | $980.00 | $5.00 | $1,400.00 | $6.25 | $1,750.00 | ||||
| 7 | Tile, Non-perforated Plastic, 5" Dia. | 55 | L.F. | $3.00 | $165.00 | $5.00 | $275.00 | $6.00 | $330.00 | ||||
| 8 | Tile, Non-perforated Plastic, 4" | 230 | L.F. | $2.50 | $575.00 | $5.00 | $1,150.00 | $6.00 | $1,380.00 | ||||
| 9 | CMP Inlet Structure With Guard, 20 LF | 3 | Each | $200.00 | $600.00 | $350.00 | $1,050.00 | $220.00 | $660.00 | ||||
| 10 | Erosion Stone | 8 | Tons | $25.00 | $200.00 | $100.00 | $800.00 | $50.00 | $400.00 | ||||
| 11 | Straw Mat | 176 | S.Y. | $2.00 | $352.00 | $2.41 | $424.16 | $4.00 | $704.00 | ||||
| 12 | Stabilizing Crop Seeding | 0.5 | Acres | $1,500.00 | $750.00 | $1,600.00 | $800.00 | $1,500.00 | $750.00 | ||||
| 13 | Construction Staking | 1 | L.S. | $500.00 | $500.00 | $1,000.00 | $1,000.00 | $5,000.00 | $5,000.00 | ||||
| $94,744.98 | $100,406.25 | $105,131.40 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $96,000.00 | Contractor: | Steger Construction Inc. | Walter Wenthold Excavating Inc | Cole Excavating, LLC | |||||||||
| Funding Source: 100% REAP OS Acquisition & Development, | 3297 Vine Rd | 26574 V Ave | 10471 Packard Ave | ||||||||||
| Dyersville IA 52040 | Waucoma IA 52171 | Greene IA 50636 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-875-7876 | 563-380-0144 | 641-823-4700 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $4,900.00 | $4,900.00 | $3,000.00 | $3,000.00 | $3,750.00 | $3,750.00 | ||||
| 2 | Excavation, Class 10 | 54314 | C.Y. | $1.54 | $83,643.56 | $1.80 | $97,765.20 | $1.83 | $99,394.62 | ||||
| 3 | Water Controll Structure, 6' | 2 | Each | $1,200.00 | $2,400.00 | $900.00 | $1,800.00 | $1,625.00 | $3,250.00 | ||||
| 4 | Water Control Structure, 5' | 1 | Each | $1,140.00 | $1,140.00 | $900.00 | $900.00 | $1,580.00 | $1,580.00 | ||||
| 5 | CMP Outlet With Rodent Guard, 6" Dia. 20LF | 3 | Each | $403.00 | $1,209.00 | $155.00 | $465.00 | $265.00 | $795.00 | ||||
| 6 | Tile, Non-perforated Plastic, 6" Dia. | 280 | L.F. | $10.90 | $3,052.00 | $3.05 | $854.00 | $7.20 | $2,016.00 | ||||
| 7 | Tile, Non-perforated Plastic, 5" Dia. | 55 | L.F. | $10.90 | $599.50 | $3.05 | $167.75 | $8.60 | $473.00 | ||||
| 8 | Tile, Non-perforated Plastic, 4" | 230 | L.F. | $10.90 | $2,507.00 | $3.05 | $701.50 | $6.80 | $1,564.00 | ||||
| 9 | CMP Inlet Structure With Guard, 20 LF | 3 | Each | $459.00 | $1,377.00 | $25.20 | $75.60 | $250.00 | $750.00 | ||||
| 10 | Erosion Stone | 8 | Tons | $70.00 | $560.00 | $36.00 | $288.00 | $50.00 | $400.00 | ||||
| 11 | Straw Mat | 176 | S.Y. | $2.85 | $501.60 | $1.30 | $228.80 | $6.00 | $1,056.00 | ||||
| 12 | Stabilizing Crop Seeding | 0.5 | Acres | $1,550.00 | $775.00 | $3,000.00 | $1,500.00 | $1,200.00 | $600.00 | ||||
| 13 | Construction Staking | 1 | L.S. | $4,300.00 | $4,300.00 | $9,000.00 | $9,000.00 | $5,500.00 | $5,500.00 | ||||
| $106,964.66 | $116,745.85 | $121,128.62 | |||||||||||
10 | 11 | 12 | |||||||||||
| Estimated Cost: $96,000.00 | Contractor: | Crane Construction | Matt Construction, Inc. | Ethan Koehn Construction | |||||||||
| Funding Source: 100% REAP OS Acquisition & Development, | 1833 120th Ave | 203 Y Ave | 19397 Fawn Hollow Rd | ||||||||||
| Manchester IA 52057 | Sumner IA 50674 | Farmersburg IA 52047 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-920-1250 | 563-578-8418 | 563-880-8350 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $8,000.00 | $8,000.00 | $5,000.00 | $5,000.00 | $5,300.00 | $5,300.00 | ||||
| 2 | Excavation, Class 10 | 54314 | C.Y. | $1.80 | $97,765.20 | $1.80 | $97,765.20 | $2.43 | $131,983.02 | ||||
| 3 | Water Controll Structure, 6' | 2 | Each | $1,300.00 | $2,600.00 | $3,250.00 | $6,500.00 | $900.00 | $1,800.00 | ||||
| 4 | Water Control Structure, 5' | 1 | Each | $1,300.00 | $1,300.00 | $2,000.00 | $2,000.00 | $700.00 | $700.00 | ||||
| 5 | CMP Outlet With Rodent Guard, 6" Dia. 20LF | 3 | Each | $200.00 | $600.00 | $275.00 | $825.00 | $150.00 | $450.00 | ||||
| 6 | Tile, Non-perforated Plastic, 6" Dia. | 280 | L.F. | $4.00 | $1,120.00 | $7.00 | $1,960.00 | $1.00 | $280.00 | ||||
| 7 | Tile, Non-perforated Plastic, 5" Dia. | 55 | L.F. | $4.00 | $220.00 | $7.00 | $385.00 | $1.50 | $82.50 | ||||
| 8 | Tile, Non-perforated Plastic, 4" | 230 | L.F. | $4.00 | $920.00 | $7.00 | $1,610.00 | $1.30 | $299.00 | ||||
| 9 | CMP Inlet Structure With Guard, 20 LF | 3 | Each | $200.00 | $600.00 | $275.00 | $825.00 | $185.00 | $555.00 | ||||
| 10 | Erosion Stone | 8 | Tons | $50.00 | $400.00 | $20.00 | $160.00 | $15.49 | $123.92 | ||||
| 11 | Straw Mat | 176 | S.Y. | $3.00 | $528.00 | $2.00 | $352.00 | $2.00 | $352.00 | ||||
| 12 | Stabilizing Crop Seeding | 0.5 | Acres | $1,200.00 | $600.00 | $3,000.00 | $1,500.00 | $483.50 | $241.75 | ||||
| 13 | Construction Staking | 1 | L.S. | $8,000.00 | $8,000.00 | $9,000.00 | $9,000.00 | $7,000.00 | $7,000.00 | ||||
| $122,653.20 | $127,882.20 | $149,167.19 | |||||||||||
13 | 14 | 15 | |||||||||||
| Estimated Cost: $96,000.00 | Contractor: | Ray's Excavating, LLC | H&H Construction & Dev. LLC | Mehmert Tiling, Inc. | |||||||||
| Funding Source: 100% REAP OS Acquisition & Development, | 404 E Union St | 60559 Hwy 64 | 8635 Hwy 9 | ||||||||||
| Edgewood IA 52042 | Sabula IA 52070 | Lime Springs IA 52155 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-928-7290 | 563-357-1849 | 641-985-4076 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $7,500.00 | $7,500.00 | $15,875.00 | $15,875.00 | $5,000.00 | $5,000.00 | ||||
| 2 | Excavation, Class 10 | 54314 | C.Y. | $2.50 | $135,785.00 | $2.41 | $130,896.74 | $4.33 | $235,179.62 | ||||
| 3 | Water Controll Structure, 6' | 2 | Each | $1,000.00 | $2,000.00 | $1,000.00 | $2,000.00 | $2,210.00 | $4,420.00 | ||||
| 4 | Water Control Structure, 5' | 1 | Each | $950.00 | $950.00 | $1,000.00 | $1,000.00 | $1,985.00 | $1,985.00 | ||||
| 5 | CMP Outlet With Rodent Guard, 6" Dia. 20LF | 3 | Each | $275.00 | $825.00 | $300.00 | $900.00 | $425.00 | $1,275.00 | ||||
| 6 | Tile, Non-perforated Plastic, 6" Dia. | 280 | L.F. | $6.00 | $1,680.00 | $2.90 | $812.00 | $9.05 | $2,534.00 | ||||
| 7 | Tile, Non-perforated Plastic, 5" Dia. | 55 | L.F. | $5.00 | $275.00 | $2.90 | $159.50 | $9.05 | $497.75 | ||||
| 8 | Tile, Non-perforated Plastic, 4" | 230 | L.F. | $4.00 | $920.00 | $2.50 | $575.00 | $7.55 | $1,736.50 | ||||
| 9 | CMP Inlet Structure With Guard, 20 LF | 3 | Each | $225.00 | $675.00 | $300.00 | $900.00 | $515.00 | $1,545.00 | ||||
| 10 | Erosion Stone | 8 | Tons | $25.00 | $200.00 | $50.00 | $400.00 | $42.00 | $336.00 | ||||
| 11 | Straw Mat | 176 | S.Y. | $4.50 | $792.00 | $2.10 | $369.60 | $7.50 | $1,320.00 | ||||
| 12 | Stabilizing Crop Seeding | 0.5 | Acres | $1,500.00 | $750.00 | $1,000.00 | $500.00 | $1,500.00 | $750.00 | ||||
| 13 | Construction Staking | 1 | L.S. | $5,200.00 | $5,200.00 | $7,500.00 | $7,500.00 | $5,500.00 | $5,500.00 | ||||
| $157,552.00 | $161,887.84 | $262,078.87 | |||||||||||