IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Nine Eagles State Park  Date: 7/5/2018  Project No.  
  Silt Ponds Repairs  County:   DECATUR  Time: 3:00 p.m.  19-05-27-01

 

 
1
2
3
Estimated Cost: $42,026.00
Contractor: 
Jay & Garret IncSchaefer Excavating, Inc.Nail Excavating LLC
Funding Source: 100% REAP Land Management, 806 W 1st St
1864 215th St
32033 Harbor Ave
Leon IA  50144Mount Ayr IA  50854Jamesport MO  64648
Plan Sets Requested: 0
Quantities
641344764664134468736606052158
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$500.00$500.00 $350.00$350.00 $2,100.00$2,100.00 
2Pond 2 Clearing1L.S.$500.00$500.00 $1,540.00$1,540.00 $900.00$900.00 
3Pond 2 Seeding1L.S.$50.00$50.00 $350.00$350.00 $372.00$372.00 
4Pond 2 Beaver Dam Removal1L.S.$150.00$150.00 $140.00$140.00 $500.00$500.00 
5Pond 3 Dam Repair1389C.Y.$1.40$1,944.60 $1.80$2,500.20 $2.25$3,125.25 
6Pond 3 Sediment Removal from Outlet1L.S.$150.00$150.00 $140.00$140.00 $330.00$330.00 
7Pond 3 Clearing1L.S.$800.00$800.00 $840.00$840.00 $660.00$660.00 
8Pond 3 Seeding1L.S.$100.00$100.00 $750.00$750.00 $372.00$372.00 
9Pond 21 Spillway Repair4630C.Y.$1.40$6,482.00 $1.80$8,334.00 $2.25$10,417.50 
10Pond 21 Clearing1L.S.$1,500.00$1,500.00 $2,100.00$2,100.00 $600.00$600.00 
11Pond 21, 24" CMP Replacement110L.F.$34.43$3,787.30 $25.20$2,772.00 $36.00$3,960.00 
12Pond 21 Seeding1L.S.$100.00$100.00 $1,150.00$1,150.00 $372.00$372.00 
      $16,063.90  $20,966.20  $23,708.75 
 
 
4
5
6
Estimated Cost: $42,026.00
Contractor: 
Jarred Construction LLCDingman ConstJNC Construction, LLC
Funding Source: 100% REAP Land Management, 102 East Railroad St
1265 240th St
609 3rd St
Tingley IA  50863Creston IA  50801Clearfield IA  50840
Plan Sets Requested: 0
Quantities
641340149264124714316413444119
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$450.00$450.00 $2,500.00$2,500.00 $500.00$500.00 
2Pond 2 Clearing1L.S.$2,500.00$2,500.00 $2,000.00$2,000.00 $2,400.00$2,400.00 
3Pond 2 Seeding1L.S.$200.00$200.00 $250.00$250.00 $800.00$800.00 
4Pond 2 Beaver Dam Removal1L.S.$400.00$400.00 $500.00$500.00 $250.00$250.00 
5Pond 3 Dam Repair1389C.Y.$1.75$2,430.75 $2.00$2,778.00 $1.65$2,291.85 
6Pond 3 Sediment Removal from Outlet1L.S.$750.00$750.00 $500.00$500.00 $250.00$250.00 
7Pond 3 Clearing1L.S.$2,500.00$2,500.00 $1,000.00$1,000.00 $1,200.00$1,200.00 
8Pond 3 Seeding1L.S.$200.00$200.00 $250.00$250.00 $400.00$400.00 
9Pond 21 Spillway Repair4630C.Y.$1.75$8,102.50 $2.00$9,260.00 $1.65$7,639.50 
10Pond 21 Clearing1L.S.$3,000.00$3,000.00 $2,000.00$2,000.00 $6,000.00$6,000.00 
11Pond 21, 24" CMP Replacement110L.F.$30.00$3,300.00 $30.00$3,300.00 $31.19$3,430.90 
12Pond 21 Seeding1L.S.$250.00$250.00 $250.00$250.00 $2,000.00$2,000.00 
      $24,083.25  $24,588.00  $27,162.25 
 
7
8
9
Estimated Cost: $42,026.00
Contractor: 
Savage Dirt Works, LLCHill ContractingProgress Contracts Inc.
Funding Source: 100% REAP Land Management, 48499 Hy-Vee Rd
20904 215th Ave
910 S 15th St
Chariton IA  50049Leon IA  50144Clinton IA  52732
Plan Sets Requested: 0
Quantities
64120323576414466428563-212-7102
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$5,000.00$5,000.00 $2,750.00$2,750.00 $5,000.00$5,000.00 
2Pond 2 Clearing1L.S.$2,500.00$2,500.00 $2,000.00$2,000.00 $8,500.00$8,500.00 
3Pond 2 Seeding1L.S.$1,000.00$1,000.00 $1,000.00$1,000.00 $1,500.00$1,500.00 
4Pond 2 Beaver Dam Removal1L.S.$750.00$750.00 $1,500.00$1,500.00 $2,500.00$2,500.00 
5Pond 3 Dam Repair1389C.Y.$2.50$3,472.50 $5.00$6,945.00 $5.00$6,945.00 
6Pond 3 Sediment Removal from Outlet1L.S.$750.00$750.00 $200.00$200.00 $3,200.00$3,200.00 
7Pond 3 Clearing1L.S.$2,000.00$2,000.00 $500.00$500.00 $6,500.00$6,500.00 
8Pond 3 Seeding1L.S.$1,000.00$1,000.00 $500.00$500.00 $1,300.00$1,300.00 
9Pond 21 Spillway Repair4630C.Y.$2.50$11,575.00 $5.00$23,150.00 $5.00$23,150.00 
10Pond 21 Clearing1L.S.$2,250.00$2,250.00 $2,500.00$2,500.00 $7,500.00$7,500.00 
11Pond 21, 24" CMP Replacement110L.F.$35.00$3,850.00 $50.00$5,500.00 $40.90$4,499.00 
12Pond 21 Seeding1L.S.$1,000.00$1,000.00 $500.00$500.00 $1,250.00$1,250.00 
      $35,147.50  $47,045.00  $71,844.00 
 



 