|
IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Ingham-High Wildlife Unit Headquarters | Date: 3/29/2018 | Project No. |
| Ingham-High HQ Wetland Restoration | County: | EMMET | Time: 3:00 p.m. | 18-01-32-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $12,000.00 | Contractor: | Valley Contracting, Inc. | Cory Juergens Construction, LLC | Wedeking Construction, Inc. | |||||||||
| Funding Source: 100% Federal-NAWCA, | 1850 Hwy 4 | 219 W 2 St S | 13810 253rd Ave | ||||||||||
| Estherville IA 51334 | Estherville IA 51334 | Spirit Lake IA 51360 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 712-362-4969 | 712-380-0184 | 712-336-2981 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $800.00 | $800.00 | $1,000.00 | $1,000.00 | $500.00 | $500.00 | ||||
| 2 | Clear & Grub Vegetation and Stumps | 1 | L.S. | $500.00 | $500.00 | $1,000.00 | $1,000.00 | $2,800.00 | $2,800.00 | ||||
| 3 | Tile Search | 500 | L.F. | $2.00 | $1,000.00 | $2.00 | $1,000.00 | $2.00 | $1,000.00 | ||||
| 4 | Tile Break | 3 | Each | $150.00 | $450.00 | $50.00 | $150.00 | $150.00 | $450.00 | ||||
| 5 | Embankment (Dike Fill) | 1100 | C.Y. | $4.00 | $4,400.00 | $4.00 | $4,400.00 | $3.25 | $3,575.00 | ||||
| 6 | Channel Excavation | 35 | C.Y. | $3.00 | $105.00 | $10.00 | $350.00 | $4.50 | $157.50 | ||||
| 7 | 12" CMP Culvert | 40 | L.F. | $18.00 | $720.00 | $40.00 | $1,600.00 | $35.84 | $1,433.60 | ||||
| $7,975.00 | $9,500.00 | $9,916.10 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $12,000.00 | Contractor: | Reutzel Excavating, Inc | Erpelding Excavating Enterprise | Cohrs Construction Inc | |||||||||
| Funding Source: 100% Federal-NAWCA, | 3008 120th Ave PO Box 42 | 2200 River Rd | 1447 Hwy 86 | ||||||||||
| Burt IA 50522 | Algona IA 50511 | Spirit Lake IA 51360 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 515-924-3852 | 515-295-2499 | 712-832-3714 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $2,300.00 | $2,300.00 | $2,500.00 | $2,500.00 | $1,500.00 | $1,500.00 | ||||
| 2 | Clear & Grub Vegetation and Stumps | 1 | L.S. | $1,450.00 | $1,450.00 | $1,600.00 | $1,600.00 | $2,000.00 | $2,000.00 | ||||
| 3 | Tile Search | 500 | L.F. | $3.00 | $1,500.00 | $2.10 | $1,050.00 | $4.00 | $2,000.00 | ||||
| 4 | Tile Break | 3 | Each | $300.00 | $900.00 | $248.00 | $744.00 | $350.00 | $1,050.00 | ||||
| 5 | Embankment (Dike Fill) | 1100 | C.Y. | $3.50 | $3,850.00 | $5.20 | $5,720.00 | $8.00 | $8,800.00 | ||||
| 6 | Channel Excavation | 35 | C.Y. | $4.00 | $140.00 | $3.00 | $105.00 | $20.00 | $700.00 | ||||
| 7 | 12" CMP Culvert | 40 | L.F. | $26.00 | $1,040.00 | $26.00 | $1,040.00 | $30.00 | $1,200.00 | ||||
| $11,180.00 | $12,759.00 | $17,250.00 | |||||||||||
12/19/2025