IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Sweet Marsh WMA  Date: 3/7/2019  Project No.  
  Mohling Wetland Developmnet  County:   BREMER  Time: 3:00 p.m.  18-03-09-01

 

 
1
2
3
Estimated Cost: $35,100.00
Contractor: 
David Ryan ConstructionMatt Construction, Inc.Nate Moeller Const
Funding Source: 100% REAP Land Management, 3566 236th Ave
203 Y Ave
706 7th Ave SW
Decorah IA  52101Sumner IA  50674Tripoli IA  50676
Plan Sets Requested: 0
Quantities
563735589556357884183198823600
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$1,500.00$1,500.00 $2,500.00$2,500.00 $1,800.00$1,800.00 
2Excavation, Class 1018000C.Y.$1.35$24,300.00 $1.28$23,040.00 $1.45$26,100.00 
3Construction Staking1L.S.$3,500.00$3,500.00 $3,550.00$3,550.00 $3,500.00$3,500.00 
4Tile Exploration25L.F.$6.00$150.00 $10.00$250.00 $14.00$350.00 
5Tile, Non-Perferated, 6"1050L.F.$1.50$1,575.00 $2.00$2,100.00 $1.80$1,890.00 
6Stabilizing Crop Seeding1Acres$750.00$750.00 $1,500.00$1,500.00 $1,400.00$1,400.00 
      $31,775.00  $32,940.00  $35,040.00 
 
 
4
5
6
Estimated Cost: $35,100.00
Contractor: 
Crane ConstructionWalter Wenthold Excavating IncChad Heim Excavating and Trucking
Funding Source: 100% REAP Land Management, 1833 120th Ave
26574 V Ave
1920 Joy Ave
Manchester IA  52057Waucoma IA  52171Waverly IA  50677
Plan Sets Requested: 0
Quantities
563920125056338001443192300153
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$2,400.00$2,400.00 $2,500.00$2,500.00 $500.00$500.00 
2Excavation, Class 1018000C.Y.$1.60$28,800.00 $1.45$26,100.00 $1.90$34,200.00 
3Construction Staking1L.S.$1,700.00$1,700.00 $3,000.00$3,000.00 $1,500.00$1,500.00 
4Tile Exploration25L.F.$10.00$250.00 $10.00$250.00 $10.00$250.00 
5Tile, Non-Perferated, 6"1050L.F.$1.80$1,890.00 $3.50$3,675.00 $1.90$1,995.00 
6Stabilizing Crop Seeding1Acres$900.00$900.00 $1,000.00$1,000.00 $900.00$900.00 
      $35,940.00  $36,525.00  $39,345.00 
 
7
8
9
Estimated Cost: $35,100.00
Contractor: 
Donlon Brothers Construction LLCSteger Const. Inc.Dan Oberbreckling Concrete & Excavating
Funding Source: 100% REAP Land Management, 4061 Dove Rd
3297 Vine Rd
2780 Coggon Rd
Elgin IA  52141Dyersville IA  52040Coggon IA  52218
Plan Sets Requested: 0
Quantities
563581503656387578765639200970
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$4,500.00$4,500.00 $5,850.00$5,850.00 $3,000.00$3,000.00 
2Excavation, Class 1018000C.Y.$1.74$31,320.00 $1.90$34,200.00 $2.50$45,000.00 
3Construction Staking1L.S.$3,000.00$3,000.00 $3,000.00$3,000.00 $3,000.00$3,000.00 
4Tile Exploration25L.F.$50.00$1,250.00 $20.00$500.00 $2.80$70.00 
5Tile, Non-Perferated, 6"1050L.F.$3.00$3,150.00 $4.70$4,935.00 $3.80$3,990.00 
6Stabilizing Crop Seeding1Acres$3,000.00$3,000.00 $1,400.00$1,400.00 $275.00$275.00 
      $46,220.00  $49,885.00  $55,335.00 
 
 
10
11
12
Estimated Cost: $35,100.00
Contractor: 
Cole Excavating LLCRay's Excavating, LLCFaas Construction & Excavating, Inc.
Funding Source: 100% REAP Land Management, 122 N 2nd St
PO Box 617
404 E Union St
3407 V18 Rd
Greene IA  50636Edgewood IA  52042Brooklyn IA  52211
Plan Sets Requested: 0
Quantities
641823470056392872906417511075
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$1,600.00$1,600.00 $2,500.00$2,500.00 $5,000.00$5,000.00 
2Excavation, Class 1018000C.Y.$2.60$46,800.00 $3.50$63,000.00 $3.40$61,200.00 
3Construction Staking1L.S.$1,850.00$1,850.00 $3,500.00$3,500.00 $500.00$500.00 
4Tile Exploration25L.F.$6.00$150.00 $3.50$87.50 $8.00$200.00 
5Tile, Non-Perferated, 6"1050L.F.$7.00$7,350.00 $2.75$2,887.50 $6.10$6,405.00 
6Stabilizing Crop Seeding1Acres$1,200.00$1,200.00 $2,000.00$2,000.00 $2,500.00$2,500.00 
      $58,950.00  $73,975.00  $75,805.00 
 
13
14
15
Estimated Cost: $35,100.00
Contractor: 
Lodge Construction Inc.Midwest Liquidation, LLCBurr Oak Springs
Funding Source: 100% REAP Land Management,
PO Box 459
73137 State Highway 16, Ste 2
2113 County Rd W14
Clarksville IA  50619Grand Meadow MN  55936Ridgeway IA  52165
Plan Sets Requested: 0
Quantities
319290576750775475305632020310
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$7,000.00$7,000.00 $28,785.00$28,785.00 $1,000.00$1,000.00 
2Excavation, Class 1018000C.Y.$3.00$54,000.00 $3.95$71,100.00 $2.50$45,000.00 
3Construction Staking1L.S.$3,500.00$3,500.00 $3,360.00$3,360.00 $1,000.00$1,000.00 
4Tile Exploration25L.F.$5.00$125.00 $87.00$2,175.00 $1,000.00$25,000.00 
5Tile, Non-Perferated, 6"1050L.F.$8.00$8,400.00 $3.80$3,990.00 $1,000.00$1,050,000.00 
6Stabilizing Crop Seeding1Acres$3,700.00$3,700.00 $8,375.00$8,375.00 $1,000.00$1,000.00 
      $76,725.00  $117,785.00  $1,123,000.00 
 



 

4/6/2026