IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Lewis and Clark State Park | Date: 11/16/2017 | Project No. |
Shoreline Armoring | County: | MONONA | Time: 11:00 AM | 17-01-67-05 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $230,000.00 | Contractor: | L.A. Carlson Contracting, Inc. | Carley Construction, LLC | Niewohner Construction Inc. | |||||||||
Funding Source: 100% Lake Restoration, | 20984 C-43 | 421 E Broadway, Ste A | 309 East Iowa Ave | ||||||||||
Merrill IA 51038 | Council Bluffs IA 51503 | Onawa IA 51040 | |||||||||||
Plan Sets Requested: 5 | Quantities | 712-947-0002 | 712-256-5818 | 712-423-3805 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $8,000.00 | $8,000.00 | $12,500.00 | $12,500.00 | $35,000.00 | $35,000.00 | ||||
2 | Class E Fieldstone | 1795 | Tons | $41.70 | $74,851.50 | $45.00 | $80,775.00 | $52.70 | $94,596.50 | ||||
3 | Sand | 371 | Tons | $29.50 | $10,944.50 | $38.00 | $14,098.00 | $36.10 | $13,393.10 | ||||
4 | Block Retaining Wall | 256 | L.F. | $125.00 | $32,000.00 | $135.00 | $34,560.00 | $93.00 | $23,808.00 | ||||
5 | Crushed Stone, 2" Clean | 58 | Tons | $60.00 | $3,480.00 | $56.00 | $3,248.00 | $60.00 | $3,480.00 | ||||
6 | 6" Tile - Perf | 230 | L.F. | $6.50 | $1,495.00 | $14.00 | $3,220.00 | $8.00 | $1,840.00 | ||||
7 | 6" Tile Outlet | 2 | Each | $500.00 | $1,000.00 | $335.00 | $670.00 | $400.00 | $800.00 | ||||
8 | Excavation, Class 10 (Waste) | 410 | C.Y. | $12.00 | $4,920.00 | $17.50 | $7,175.00 | $12.00 | $4,920.00 | ||||
9 | Site Restoration | 1 | L.S. | $5,000.00 | $5,000.00 | $4,250.00 | $4,250.00 | $7,000.00 | $7,000.00 | ||||
10 | Demolition | 1 | L.S. | $3,500.00 | $3,500.00 | $2,910.00 | $2,910.00 | $2,000.00 | $2,000.00 | ||||
11 | Relocate Covered Picnic Table | 2 | Each | $500.00 | $1,000.00 | $1,325.00 | $2,650.00 | $1,500.00 | $3,000.00 | ||||
12 | Cap Utilities | 1 | L.S. | $1,000.00 | $1,000.00 | $1,500.00 | $1,500.00 | $300.00 | $300.00 | ||||
13 | 5" PCC, Reinforced | 91 | S.Y. | $115.00 | $10,465.00 | $58.00 | $5,278.00 | $47.50 | $4,322.50 | ||||
14 | 6" PCC | 70 | S.Y. | $115.00 | $8,050.00 | $60.00 | $4,200.00 | $49.50 | $3,465.00 | ||||
15 | Granular Subbase | 51 | Tons | $40.00 | $2,040.00 | $35.00 | $1,785.00 | $48.80 | $2,488.80 | ||||
16 | Handicap Parking Sign | 1 | Each | $375.00 | $375.00 | $1,020.00 | $1,020.00 | $1,200.00 | $1,200.00 | ||||
17 | Striping | 1 | L.S. | $600.00 | $600.00 | $1,605.00 | $1,605.00 | $500.00 | $500.00 | ||||
$168,721.00 | $181,444.00 | $202,113.90 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $230,000.00 | Contractor: | Bainbridge Construction, LLC | Detlefsen Construction LLC | Thompson Construction, Inc. | |||||||||
Funding Source: 100% Lake Restoration, | 106 Main St | 57363 Hwy 20 | 2404 N Lincoln Ave | ||||||||||
Kingsley IA 50218 | Laurel NE 68745 | Fremont NE 68025 | |||||||||||
Plan Sets Requested: 5 | Quantities | 712-378-3619 | 402-375-8566 | 402-704-2008 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $15,000.00 | $15,000.00 | $25,000.00 | $25,000.00 | $10,000.00 | $10,000.00 | ||||
2 | Class E Fieldstone | 1795 | Tons | $50.00 | $89,750.00 | $57.26 | $102,781.70 | $60.00 | $107,700.00 | ||||
3 | Sand | 371 | Tons | $36.00 | $13,356.00 | $32.19 | $11,942.49 | $45.00 | $16,695.00 | ||||
4 | Block Retaining Wall | 256 | L.F. | $135.00 | $34,560.00 | $102.54 | $26,250.24 | $131.00 | $33,536.00 | ||||
5 | Crushed Stone, 2" Clean | 58 | Tons | $130.00 | $7,540.00 | $84.52 | $4,902.16 | $80.00 | $4,640.00 | ||||
6 | 6" Tile - Perf | 230 | L.F. | $10.00 | $2,300.00 | $3.00 | $690.00 | $7.00 | $1,610.00 | ||||
7 | 6" Tile Outlet | 2 | Each | $320.00 | $640.00 | $150.00 | $300.00 | $275.00 | $550.00 | ||||
8 | Excavation, Class 10 (Waste) | 410 | C.Y. | $10.00 | $4,100.00 | $9.76 | $4,001.60 | $9.00 | $3,690.00 | ||||
9 | Site Restoration | 1 | L.S. | $10,000.00 | $10,000.00 | $3,000.00 | $3,000.00 | $9,000.00 | $9,000.00 | ||||
10 | Demolition | 1 | L.S. | $10,000.00 | $10,000.00 | $10,000.00 | $10,000.00 | $8,000.00 | $8,000.00 | ||||
11 | Relocate Covered Picnic Table | 2 | Each | $2,500.00 | $5,000.00 | $500.00 | $1,000.00 | $850.00 | $1,700.00 | ||||
12 | Cap Utilities | 1 | L.S. | $1,500.00 | $1,500.00 | $1,000.00 | $1,000.00 | $500.00 | $500.00 | ||||
13 | 5" PCC, Reinforced | 91 | S.Y. | $70.00 | $6,370.00 | $98.90 | $8,999.90 | $75.00 | $6,825.00 | ||||
14 | 6" PCC | 70 | S.Y. | $72.00 | $5,040.00 | $114.28 | $7,999.60 | $85.00 | $5,950.00 | ||||
15 | Granular Subbase | 51 | Tons | $45.75 | $2,333.25 | $67.16 | $3,425.16 | $55.00 | $2,805.00 | ||||
16 | Handicap Parking Sign | 1 | Each | $1,500.00 | $1,500.00 | $500.00 | $500.00 | $850.00 | $850.00 | ||||
17 | Striping | 1 | L.S. | $2,500.00 | $2,500.00 | $800.00 | $800.00 | $900.00 | $900.00 | ||||
$211,489.25 | $212,592.85 | $214,951.00 | |||||||||||
7 | 8 | 9 | |||||||||||
Estimated Cost: $230,000.00 | Contractor: | RP Constructors, LLC | Nelson & Rock Contracting Inc. | Crow River Construction | |||||||||
Funding Source: 100% Lake Restoration, | 310 N Derby Ln #195 | 23565 Hwy K45 | 21 1st Ave SW | ||||||||||
North Sioux City SD 57049 | Onawa IA 51040 | New London MN 56273 | |||||||||||
Plan Sets Requested: 5 | Quantities | 712-222-1452 | 712-423-1065 | 320-354-5554 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $19,000.00 | $19,000.00 | $40,000.00 | $40,000.00 | $70,000.00 | $70,000.00 | ||||
2 | Class E Fieldstone | 1795 | Tons | $48.95 | $87,865.25 | $54.00 | $96,930.00 | $48.00 | $86,160.00 | ||||
3 | Sand | 371 | Tons | $45.25 | $16,787.75 | $40.00 | $14,840.00 | $36.00 | $13,356.00 | ||||
4 | Block Retaining Wall | 256 | L.F. | $175.00 | $44,800.00 | $125.00 | $32,000.00 | $245.00 | $62,720.00 | ||||
5 | Crushed Stone, 2" Clean | 58 | Tons | $55.00 | $3,190.00 | $60.00 | $3,480.00 | $38.00 | $2,204.00 | ||||
6 | 6" Tile - Perf | 230 | L.F. | $25.00 | $5,750.00 | $5.00 | $1,150.00 | $40.00 | $9,200.00 | ||||
7 | 6" Tile Outlet | 2 | Each | $300.00 | $600.00 | $100.00 | $200.00 | $310.00 | $620.00 | ||||
8 | Excavation, Class 10 (Waste) | 410 | C.Y. | $15.00 | $6,150.00 | $10.00 | $4,100.00 | $10.00 | $4,100.00 | ||||
9 | Site Restoration | 1 | L.S. | $7,500.00 | $7,500.00 | $12,000.00 | $12,000.00 | $11,000.00 | $11,000.00 | ||||
10 | Demolition | 1 | L.S. | $6,000.00 | $6,000.00 | $12,000.00 | $12,000.00 | $11,250.00 | $11,250.00 | ||||
11 | Relocate Covered Picnic Table | 2 | Each | $6,000.00 | $12,000.00 | $4,000.00 | $8,000.00 | $3,000.00 | $6,000.00 | ||||
12 | Cap Utilities | 1 | L.S. | $2,500.00 | $2,500.00 | $1,000.00 | $1,000.00 | $2,500.00 | $2,500.00 | ||||
13 | 5" PCC, Reinforced | 91 | S.Y. | $75.00 | $6,825.00 | $100.00 | $9,100.00 | $80.00 | $7,280.00 | ||||
14 | 6" PCC | 70 | S.Y. | $70.00 | $4,900.00 | $100.00 | $7,000.00 | $110.00 | $7,700.00 | ||||
15 | Granular Subbase | 51 | Tons | $40.00 | $2,040.00 | $50.00 | $2,550.00 | $35.00 | $1,785.00 | ||||
16 | Handicap Parking Sign | 1 | Each | $800.00 | $800.00 | $1,000.00 | $1,000.00 | $800.00 | $800.00 | ||||
17 | Striping | 1 | L.S. | $1,100.00 | $1,100.00 | $1,000.00 | $1,000.00 | $1,200.00 | $1,200.00 | ||||
$227,808.00 | $246,350.00 | $297,875.00 | |||||||||||
10 | 11 | 12 | |||||||||||
Estimated Cost: $230,000.00 | Contractor: | Lessard Contracting Inc. | |||||||||||
Funding Source: 100% Lake Restoration, | 2300 Blvd of Champions | ||||||||||||
Sioux City IA 51111 | |||||||||||||
Plan Sets Requested: 5 | Quantities | 712-252-4131 | |||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | Mobilization | 1 | L.S. | $43,675.00 | $43,675.00 | $0.00 | $0.00 | ||||||
2 | Class E Fieldstone | 1795 | Tons | $50.00 | $89,750.00 | $0.00 | $0.00 | ||||||
3 | Sand | 371 | Tons | $44.00 | $16,324.00 | $0.00 | $0.00 | ||||||
4 | Block Retaining Wall | 256 | L.F. | $922.00 | $236,032.00 | $0.00 | $0.00 | ||||||
5 | Crushed Stone, 2" Clean | 58 | Tons | $85.00 | $4,930.00 | $0.00 | $0.00 | ||||||
6 | 6" Tile - Perf | 230 | L.F. | $13.00 | $2,990.00 | $0.00 | $0.00 | ||||||
7 | 6" Tile Outlet | 2 | Each | $260.00 | $520.00 | $0.00 | $0.00 | ||||||
8 | Excavation, Class 10 (Waste) | 410 | C.Y. | $13.50 | $5,535.00 | $0.00 | $0.00 | ||||||
9 | Site Restoration | 1 | L.S. | $8,500.00 | $8,500.00 | $0.00 | $0.00 | ||||||
10 | Demolition | 1 | L.S. | $16,000.00 | $16,000.00 | $0.00 | $0.00 | ||||||
11 | Relocate Covered Picnic Table | 2 | Each | $3,335.00 | $6,670.00 | $0.00 | $0.00 | ||||||
12 | Cap Utilities | 1 | L.S. | $2,500.00 | $2,500.00 | $0.00 | $0.00 | ||||||
13 | 5" PCC, Reinforced | 91 | S.Y. | $65.00 | $5,915.00 | $0.00 | $0.00 | ||||||
14 | 6" PCC | 70 | S.Y. | $60.00 | $4,200.00 | $0.00 | $0.00 | ||||||
15 | Granular Subbase | 51 | Tons | $40.00 | $2,040.00 | $0.00 | $0.00 | ||||||
16 | Handicap Parking Sign | 1 | Each | $450.00 | $450.00 | $0.00 | $0.00 | ||||||
17 | Striping | 1 | L.S. | $700.00 | $700.00 | $0.00 | $0.00 | ||||||
$446,731.00 | $0.00 | $0.00 | |||||||||||
3/29/2024