IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Lake Sugema Wildlife Management Area  Date: 7/28/2017  Project No.  
  Tug Forks Boat Ramp Replacement (TSB Contract)  County:   VAN BUREN  Time: 3:00 p.m.  15-06-89-05

 

 
1
2
3
Estimated Cost: $10,000.00
Contractor: 
DeLong Construction Inc
Funding Source: 100% Marine Fuel Tax, 1320 N 8th Ave
PO Box 488


Washington IA  52353    
Plan Sets Requested: 0
Quantities
319-653-3334
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$3,625.00$3,625.00 $0.00 $0.00 
2Granular Subbase, ¾” (6” Depth)10Tons$138.00$1,380.00 $0.00 $0.00 
3PCC Boat Ramp Removal and Replacement, 7” Depth, Reinforced34S.Y.$126.00$4,284.00 $0.00 $0.00 
4Site Restoration1L.S.$500.00$500.00 $0.00 $0.00 
      $9,789.00  $0.00  $0.00 
 



 