IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   West Lake Complex  Date: 11/15/2018  Project No.  
  Watershed Improvements  County:   SCOTT  Time: 11:00 a.m.  17-06-82-01

 

 
1
2
3
Estimated Cost: $620,000.00
Contractor: 
H & H Construction & Development LLCArdo Schmidt Const. Inc.Customized Environmental Solutions
Funding Source: 100% Lake Restoration, 60559 Hwy 64
35010 Hwy 64
2045 Grand Ave, Ste A
Sabula IA  52070Preston IA  52069West Des Moines IA  50265
Plan Sets Requested: 19
Quantities
5633571849(563) 689-4875(515) 587-5809
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$65,000.00$65,000.00 $42,000.00$42,000.00 $46,000.00$46,000.00 
2Clearing and Grubbing1L.S.$50,000.00$50,000.00 $85,000.00$85,000.00 $15,500.00$15,500.00 
3Handling of Water1L.S.$7,500.00$7,500.00 $6,000.00$6,000.00 $12,000.00$12,000.00 
4Erosion Control (SWPPP)1L.S.$5,000.00$5,000.00 $23,600.00$23,600.00 $25,500.00$25,500.00 
5Seeding - Grass Seed Mix5.4Acres$2,000.00$10,800.00 $1,500.00$8,100.00 $1,200.00$6,480.00 
6Earthen Embankment32709C.Y.$2.25$73,595.25 $2.50$81,772.50 $2.50$81,772.50 
7Excavation13961C.Y.$3.50$48,863.50 $2.00$27,922.00 $2.50$34,902.50 
824" HDPE Pipe561L.F.$65.00$36,465.00 $81.33$45,626.13 $151.51$84,997.11 
924" Flared End Section4Each$275.00$1,100.00 $400.00$1,600.00 $625.00$2,500.00 
10Unformed Concrete38C.Y.$160.00$6,080.00 $200.00$7,600.00 $200.00$7,600.00 
11Class "C" Rock Riprap852Tons$32.50$27,690.00 $39.50$33,654.00 $45.00$38,340.00 
12Class "E" Rock Riprap41Tons$35.00$1,435.00 $39.00$1,599.00 $55.00$2,255.00 
13Formed Concrete36C.Y.$600.00$21,600.00 $500.00$18,000.00 $500.00$18,000.00 
14Steel Reinforcement3866LB.$1.25$4,832.50 $3.00$11,598.00 $5.00$19,330.00 
15Metal Fabrication50L.F.$212.00$10,600.00 $300.00$15,000.00 $150.00$7,500.00 
16Erosion Control Matting13991S.Y.$3.25$45,470.75 $1.75$24,484.25 $1.99$27,842.09 
17Existing Pipe Removal160L.F.$10.50$1,680.00 $10.00$1,600.00 $20.00$3,200.00 
18Excavation141C.Y.$10.00$1,410.00 $10.00$1,410.00 $3.50$493.50 
19Class "E" Rock Riprap50Tons$40.00$2,000.00 $39.00$1,950.00 $55.00$2,750.00 
20Formed Concrete0.83C.Y.$1,200.00$996.00 $500.00$415.00 $500.00$415.00 
21Steel Reinforcement57.3LB.$10.00$573.00 $3.00$171.90 $20.00$1,146.00 
22Turf Reinforcement Mat235S.F.$3.25$763.75 $3.00$705.00 $5.00$1,175.00 
23Cobbles2C.Y.$200.00$400.00 $150.00$300.00 $412.50$825.00 
24Erosion Control Matting263S.Y.$4.00$1,052.00 $3.00$789.00 $1.99$523.37 
25Amended Soils5C.Y.$100.00$500.00 $100.00$500.00 $50.00$250.00 
26Sand7C.Y.$100.00$700.00 $10.00$70.00 $268.30$1,878.10 
276" Slotted Wall PVC Pipe with Sock45L.F.$15.00$675.00 $25.00$1,125.00 $7.58$341.10 
286" Solid Wall PVC Pipe61L.F.$9.00$549.00 $25.00$1,525.00 $53.30$3,251.30 
29Asphalt Repairs7S.Y.$200.00$1,400.00 $140.00$980.00 $1,500.00$10,500.00 
30Plugs - Bioswale Bed Mix400Each$8.00$3,200.00 $10.00$4,000.00 $12.50$5,000.00 
31Seeding - Bioswale Slope Mix2366S.F.$1.26$2,981.16 $1.00$2,366.00 $2.00$4,732.00 
32Excavation5796C.Y.$3.25$18,837.00 $3.13$18,141.48 $2.50$14,490.00 
33Class "E" Rock Riprap265Tons$35.00$9,275.00 $39.00$10,335.00 $55.00$14,575.00 
34Erosion Control Matting33000S.Y.$1.80$59,400.00 $1.50$49,500.00 $1.99$65,670.00 
35Seeding - Grass Seed Mix7.3Acres$1,500.00$10,950.00 $1,500.00$10,950.00 $1,400.00$10,220.00 
36Seeding - Floodplain Mix1.2Acres$2,100.00$2,520.00 $2,000.00$2,400.00 $1,400.00$1,680.00 
      $535,893.91  $542,789.26  $573,634.57 
 
4
5
6
Estimated Cost: $620,000.00
Contractor: 
Langman Construction Inc.Engelbrecht Farms IncBWC Excavating, LC
Funding Source: 100% Lake Restoration, 220 34th Ave
22870 130th Ave
1303 Hickory Hollow Rd
Rock Island IL  61201Davenport IA  52806Solon IA  52333
Plan Sets Requested: 19
Quantities
(309) 786-8944(563) 285-8281(319) 848-7513
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$95,000.00$95,000.00 $49,679.19$49,679.19 $80,000.00$80,000.00 
2Clearing and Grubbing1L.S.$45,000.00$45,000.00 $31,095.42$31,095.42 $20,000.00$20,000.00 
3Handling of Water1L.S.$0.01$0.01 $16,275.47$16,275.47 $10,000.00$10,000.00 
4Erosion Control (SWPPP)1L.S.$3,000.00$3,000.00 $18,342.04$18,342.04 $15,000.00$15,000.00 
5Seeding - Grass Seed Mix5.4Acres$2,000.00$10,800.00 $1,865.12$10,071.648 $2,250.00$12,150.00 
6Earthen Embankment32709C.Y.$4.00$130,836.00 $5.51$180,226.59 $4.50$147,190.50 
7Excavation13961C.Y.$4.00$55,844.00 $5.51$76,925.11 $4.50$62,824.50 
824" HDPE Pipe561L.F.$90.00$50,490.00 $40.62$22,787.82 $105.00$58,905.00 
924" Flared End Section4Each$800.00$3,200.00 $508.16$2,032.64 $1,500.00$6,000.00 
10Unformed Concrete38C.Y.$140.00$5,320.00 $365.34$13,882.92 $250.00$9,500.00 
11Class "C" Rock Riprap852Tons$54.00$46,008.00 $69.82$59,486.64 $45.00$38,340.00 
12Class "E" Rock Riprap41Tons$54.00$2,214.00 $69.82$2,862.62 $80.00$3,280.00 
13Formed Concrete36C.Y.$835.00$30,060.00 $772.65$27,815.40 $600.00$21,600.00 
14Steel Reinforcement3866LB.$2.00$7,732.00 $1.09$4,213.94 $4.00$15,464.00 
15Metal Fabrication50L.F.$100.00$5,000.00 $175.39$8,769.50 $100.00$5,000.00 
16Erosion Control Matting13991S.Y.$0.75$10,493.25 $1.25$17,488.75 $2.00$27,982.00 
17Existing Pipe Removal160L.F.$10.00$1,600.00 $26.77$4,283.20 $10.00$1,600.00 
18Excavation141C.Y.$10.00$1,410.00 $5.51$776.91 $30.00$4,230.00 
19Class "E" Rock Riprap50Tons$54.00$2,700.00 $69.82$3,491.00 $50.00$2,500.00 
20Formed Concrete0.83C.Y.$1,500.00$1,245.00 $6,414.94$5,324.40 $20,000.00$16,600.00 
21Steel Reinforcement57.3LB.$5.00$286.50 $1.09$62.457 $10.00$573.00 
22Turf Reinforcement Mat235S.F.$1.00$235.00 $1.25$293.75 $4.00$940.00 
23Cobbles2C.Y.$100.00$200.00 $69.82$139.64 $2,000.00$4,000.00 
24Erosion Control Matting263S.Y.$1.00$263.00 $1.25$328.75 $3.25$854.75 
25Amended Soils5C.Y.$150.00$750.00 $48.65$243.25 $500.00$2,500.00 
26Sand7C.Y.$60.00$420.00 $15.29$107.03 $500.00$3,500.00 
276" Slotted Wall PVC Pipe with Sock45L.F.$15.00$675.00 $8.49$382.05 $30.00$1,350.00 
286" Solid Wall PVC Pipe61L.F.$15.00$915.00 $8.49$517.89 $30.00$1,830.00 
29Asphalt Repairs7S.Y.$80.00$560.00 $189.52$1,326.64 $250.00$1,750.00 
30Plugs - Bioswale Bed Mix400Each$6.00$2,400.00 $4.96$1,984.00 $20.00$8,000.00 
31Seeding - Bioswale Slope Mix2366S.F.$0.30$709.80 $0.40$946.40 $1.25$2,957.50 
32Excavation5796C.Y.$4.00$23,184.00 $5.50$31,878.00 $15.00$86,940.00 
33Class "E" Rock Riprap265Tons$54.00$14,310.00 $69.82$18,502.30 $50.00$13,250.00 
34Erosion Control Matting33000S.Y.$0.75$24,750.00 $1.25$41,250.00 $2.00$66,000.00 
35Seeding - Grass Seed Mix7.3Acres$2,000.00$14,600.00 $1,865.12$13,615.376 $1,500.00$10,950.00 
36Seeding - Floodplain Mix1.2Acres$3,000.00$3,600.00 $1,865.12$2,238.144 $2,000.00$2,400.00 
      $595,810.56  $669,646.885  $765,961.25 
 
7
8
9
Estimated Cost: $620,000.00
Contractor: 
McCarthy Improvement CompanyTriple B Construction
Funding Source: 100% Lake Restoration, 5401 Victoria Ave
710 Ayres Progress Dr

Davenport IA  52807Wilton IA  52778  
Plan Sets Requested: 19
Quantities
(563) 359-0321(563) 732-3478
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$147,000.00$147,000.00 $80,000.00$80,000.00 $0.00 
2Clearing and Grubbing1L.S.$100,000.00$100,000.00 $49,500.00$49,500.00 $0.00 
3Handling of Water1L.S.$82,000.00$82,000.00 $30,500.00$30,500.00 $0.00 
4Erosion Control (SWPPP)1L.S.$6,000.00$6,000.00 $15,000.00$15,000.00 $0.00 
5Seeding - Grass Seed Mix5.4Acres$800.00$4,320.00 $1,500.00$8,100.00 $0.00 
6Earthen Embankment32709C.Y.$11.15$364,705.35 $4.00$130,836.00 $0.00 
7Excavation13961C.Y.$18.00$251,298.00 $3.50$48,863.50 $0.00 
824" HDPE Pipe561L.F.$100.00$56,100.00 $80.00$44,880.00 $0.00 
924" Flared End Section4Each$900.00$3,600.00 $700.00$2,800.00 $0.00 
10Unformed Concrete38C.Y.$400.00$15,200.00 $250.00$9,500.00 $0.00 
11Class "C" Rock Riprap852Tons$65.00$55,380.00 $50.00$42,600.00 $0.00 
12Class "E" Rock Riprap41Tons$94.00$3,854.00 $50.00$2,050.00 $0.00 
13Formed Concrete36C.Y.$1,500.00$54,000.00 $500.00$18,000.00 $0.00 
14Steel Reinforcement3866LB.$4.00$15,464.00 $1.00$3,866.00 $0.00 
15Metal Fabrication50L.F.$1.00$50.00 $17,500.00$875,000.00 $0.00 
16Erosion Control Matting13991S.Y.$1.00$13,991.00 $1.75$24,484.25 $0.00 
17Existing Pipe Removal160L.F.$20.00$3,200.00 $20.00$3,200.00 $0.00 
18Excavation141C.Y.$35.00$4,935.00 $15.00$2,115.00 $0.00 
19Class "E" Rock Riprap50Tons$85.00$4,250.00 $46.00$2,300.00 $0.00 
20Formed Concrete0.83C.Y.$4,000.00$3,320.00 $3,200.00$2,656.00 $0.00 
21Steel Reinforcement57.3LB.$4.00$229.20 $1.00$57.30 $0.00 
22Turf Reinforcement Mat235S.F.$0.50$117.50 $3.00$705.00 $0.00 
23Cobbles2C.Y.$5.00$10.00 $100.00$200.00 $0.00 
24Erosion Control Matting263S.Y.$5.00$1,315.00 $3.00$789.00 $0.00 
25Amended Soils5C.Y.$200.00$1,000.00 $100.00$500.00 $0.00 
26Sand7C.Y.$100.00$700.00 $40.00$280.00 $0.00 
276" Slotted Wall PVC Pipe with Sock45L.F.$15.00$675.00 $30.00$1,350.00 $0.00 
286" Solid Wall PVC Pipe61L.F.$15.00$915.00 $25.00$1,525.00 $0.00 
29Asphalt Repairs7S.Y.$1,000.00$7,000.00 $200.00$1,400.00 $0.00 
30Plugs - Bioswale Bed Mix400Each$4.00$1,600.00 $10.00$4,000.00 $0.00 
31Seeding - Bioswale Slope Mix2366S.F.$0.35$828.10 $1.00$2,366.00 $0.00 
32Excavation5796C.Y.$7.00$40,572.00 $4.50$26,082.00 $0.00 
33Class "E" Rock Riprap265Tons$63.00$16,695.00 $50.00$13,250.00 $0.00 
34Erosion Control Matting33000S.Y.$1.00$33,000.00 $1.50$49,500.00 $0.00 
35Seeding - Grass Seed Mix7.3Acres$800.00$5,840.00 $1,500.00$10,950.00 $0.00 
36Seeding - Floodplain Mix1.2Acres$1,000.00$1,200.00 $2,000.00$2,400.00 $0.00 
      $1,300,364.15  $1,511,605.05  $0.00 
 


The following apparent low bidders were found to be Non-Responsive and/or Not Responsible. No determinations have been made regarding the Responsiveness and Responsibility of the bidders that are not the apparent low.


Langman Construction Inc., Rock Island , IL
 

DNR reserves the right to modify this list as it reviews and inspects the bids received. DNR will update the bid tab accordingly.

7/18/2019