IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Ledges | Date: 3/22/2018 | Project No. |
| Road Repair | County: | BOONE | Time: 11:00 a.m. | 17-02-08-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $575,000.00 | Contractor: | Richards Construction Co., Inc. | TK Concrete, Inc. | Shekar Engineering | |||||||||
| Funding Source: 100% Park & Institutional Road Fund, | 2721 Sierra Ave | 1608 Fifield Rd | 2600 MLK Jr Pkwy #200 | ||||||||||
| Sac City IA 50583 | Pe IA 50219 | Des Moines IA 50310 | |||||||||||
| Plan Sets Requested: 4 | Quantities | 712-662-4421 | 641-628-4590 | 515-334-5062 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | MOBILIZATION & DEMOBILIZATION | 1 | L.S. | $15,000.00 | $15,000.00 | $29,000.00 | $29,000.00 | $19,000.00 | $19,000.00 | ||||
| 2 | TRAFFIC CONTROL | 1 | L.S. | $1,000.00 | $1,000.00 | $3,000.00 | $3,000.00 | $2,000.00 | $2,000.00 | ||||
| 3 | SITE PREP & CLEARING | 1 | L.S. | $25,000.00 | $25,000.00 | $25,000.00 | $25,000.00 | $20,000.00 | $20,000.00 | ||||
| 4 | CULVERT REMOVAL & DISPOSAL | 3 | Each | $200.00 | $600.00 | $500.00 | $1,500.00 | $1,250.00 | $3,750.00 | ||||
| 5 | CULVERT PLUGGING | 1 | Each | $250.00 | $250.00 | $850.00 | $850.00 | $1,800.00 | $1,800.00 | ||||
| 6 | DITCH GRADING | 420 | L.F. | $3.00 | $1,260.00 | $18.00 | $7,560.00 | $16.00 | $6,720.00 | ||||
| 7 | EXCAVATION | 2350 | C.Y. | $9.25 | $21,737.50 | $13.00 | $30,550.00 | $7.50 | $17,625.00 | ||||
| 8 | TOPSOIL IMPORT | 65 | C.Y. | $25.00 | $1,625.00 | $50.00 | $3,250.00 | $75.00 | $4,875.00 | ||||
| 9 | HMA REMOVAL & DISPOSAL | 462 | S.Y. | $8.00 | $3,696.00 | $10.00 | $4,620.00 | $9.00 | $4,158.00 | ||||
| 10 | PCC PAVEMENT (7") | 462 | S.Y. | $38.00 | $17,556.00 | $45.00 | $20,790.00 | $55.00 | $25,410.00 | ||||
| 11 | POROUS BACKFILL | 360 | Tons | $38.00 | $13,680.00 | $30.00 | $10,800.00 | $40.00 | $14,400.00 | ||||
| 12 | CLASS A ROADSTONE | 340 | Tons | $29.00 | $9,860.00 | $27.50 | $9,350.00 | $39.05 | $13,277.00 | ||||
| 13 | CLASS E REVETMENT (BANK STABILIZATION) | 370 | Tons | $53.00 | $19,610.00 | $55.00 | $20,350.00 | $56.75 | $20,997.50 | ||||
| 14 | CLASS E REVETMENT (CHECK DAM) | 120 | Tons | $58.00 | $6,960.00 | $55.00 | $6,600.00 | $56.75 | $6,810.00 | ||||
| 15 | SHOT ROCK (BENCH BACKFILL) | 3870 | Tons | $37.00 | $143,190.00 | $36.00 | $139,320.00 | $48.75 | $188,662.50 | ||||
| 16 | CLASS E REVETMENT (PIPE OUTLET) | 8 | Tons | $50.00 | $400.00 | $55.00 | $440.00 | $56.75 | $454.00 | ||||
| 17 | SUBDRAIN, PERFORATED, DUAL WALL HDPE, 6" | 450 | L.F. | $16.00 | $7,200.00 | $12.00 | $5,400.00 | $15.00 | $6,750.00 | ||||
| 18 | STORM SEWER, NON-PERFORATED, DUAL WALL HDPE, 18" | 305 | L.F. | $65.00 | $19,825.00 | $28.00 | $8,540.00 | $45.00 | $13,725.00 | ||||
| 19 | INTAKE, SW-512, 30" | 5 | Each | $1,300.00 | $6,500.00 | $3,000.00 | $15,000.00 | $1,250.00 | $6,250.00 | ||||
| 20 | ANTI-SEEPAGE COLLAR | 3 | Each | $400.00 | $1,200.00 | $400.00 | $1,200.00 | $100.00 | $300.00 | ||||
| 21 | SEEDING, DITCH MIX | 0.3 | Acres | $6,900.00 | $2,070.00 | $10,000.00 | $3,000.00 | $2,000.00 | $600.00 | ||||
| 22 | EROSION CONTROL, 8" WATTLES | 460 | L.F. | $2.50 | $1,150.00 | $3.00 | $1,380.00 | $5.00 | $2,300.00 | ||||
| $319,369.50 | $347,500.00 | $379,864.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $575,000.00 | Contractor: | MPS Engineers, PC dba Kingston Services, PC | Gehrke Inc. | Hendrickson Transportation, LLC | |||||||||
| Funding Source: 100% Park & Institutional Road Fund, | 1444 Illinois St | 1405 21st Ave | 2762 310th St | ||||||||||
| Des Moines IA 50314 | Eldora IA 50627 | Hamburg IA 51640 | |||||||||||
| Plan Sets Requested: 4 | Quantities | 515-221-9832 | 641-858-3821 | 712-382-1505 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | MOBILIZATION & DEMOBILIZATION | 1 | L.S. | $28,700.00 | $28,700.00 | $58,500.00 | $58,500.00 | $69,000.00 | $69,000.00 | ||||
| 2 | TRAFFIC CONTROL | 1 | L.S. | $2,850.00 | $2,850.00 | $4,000.00 | $4,000.00 | $3,500.00 | $3,500.00 | ||||
| 3 | SITE PREP & CLEARING | 1 | L.S. | $19,500.00 | $19,500.00 | $36,800.00 | $36,800.00 | $23,100.00 | $23,100.00 | ||||
| 4 | CULVERT REMOVAL & DISPOSAL | 3 | Each | $935.00 | $2,805.00 | $545.00 | $1,635.00 | $2,000.00 | $6,000.00 | ||||
| 5 | CULVERT PLUGGING | 1 | Each | $1,210.00 | $1,210.00 | $300.00 | $300.00 | $500.00 | $500.00 | ||||
| 6 | DITCH GRADING | 420 | L.F. | $18.00 | $7,560.00 | $8.00 | $3,360.00 | $2.50 | $1,050.00 | ||||
| 7 | EXCAVATION | 2350 | C.Y. | $12.00 | $28,200.00 | $20.00 | $47,000.00 | $10.00 | $23,500.00 | ||||
| 8 | TOPSOIL IMPORT | 65 | C.Y. | $56.00 | $3,640.00 | $95.40 | $6,201.00 | $10.00 | $650.00 | ||||
| 9 | HMA REMOVAL & DISPOSAL | 462 | S.Y. | $8.00 | $3,696.00 | $7.00 | $3,234.00 | $16.00 | $7,392.00 | ||||
| 10 | PCC PAVEMENT (7") | 462 | S.Y. | $46.00 | $21,252.00 | $80.00 | $36,960.00 | $130.00 | $60,060.00 | ||||
| 11 | POROUS BACKFILL | 360 | Tons | $34.00 | $12,240.00 | $37.45 | $13,482.00 | $40.00 | $14,400.00 | ||||
| 12 | CLASS A ROADSTONE | 340 | Tons | $33.00 | $11,220.00 | $32.25 | $10,965.00 | $40.00 | $13,600.00 | ||||
| 13 | CLASS E REVETMENT (BANK STABILIZATION) | 370 | Tons | $58.60 | $21,682.00 | $54.50 | $20,165.00 | $55.00 | $20,350.00 | ||||
| 14 | CLASS E REVETMENT (CHECK DAM) | 120 | Tons | $60.85 | $7,302.00 | $70.00 | $8,400.00 | $55.00 | $6,600.00 | ||||
| 15 | SHOT ROCK (BENCH BACKFILL) | 3870 | Tons | $48.85 | $189,049.50 | $38.00 | $147,060.00 | $45.00 | $174,150.00 | ||||
| 16 | CLASS E REVETMENT (PIPE OUTLET) | 8 | Tons | $60.85 | $486.80 | $69.50 | $556.00 | $55.00 | $440.00 | ||||
| 17 | SUBDRAIN, PERFORATED, DUAL WALL HDPE, 6" | 450 | L.F. | $38.00 | $17,100.00 | $19.00 | $8,550.00 | $12.00 | $5,400.00 | ||||
| 18 | STORM SEWER, NON-PERFORATED, DUAL WALL HDPE, 18" | 305 | L.F. | $64.00 | $19,520.00 | $48.00 | $14,640.00 | $20.00 | $6,100.00 | ||||
| 19 | INTAKE, SW-512, 30" | 5 | Each | $3,800.00 | $19,000.00 | $2,500.00 | $12,500.00 | $2,000.00 | $10,000.00 | ||||
| 20 | ANTI-SEEPAGE COLLAR | 3 | Each | $1,250.00 | $3,750.00 | $500.00 | $1,500.00 | $250.00 | $750.00 | ||||
| 21 | SEEDING, DITCH MIX | 0.3 | Acres | $10,000.00 | $3,000.00 | $6,500.00 | $1,950.00 | $3,000.00 | $900.00 | ||||
| 22 | EROSION CONTROL, 8" WATTLES | 460 | L.F. | $2.25 | $1,035.00 | $5.00 | $2,300.00 | $5.00 | $2,300.00 | ||||
| $424,798.30 | $440,058.00 | $449,742.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $575,000.00 | Contractor: | H & H Construction & Development LLC | Con-Struct, Inc. | Absolute Concrete Construction, Inc. | |||||||||
| Funding Source: 100% Park & Institutional Road Fund, | 60559 Hwy 64 | 305 S Dayton Ave | 505 1st Ave N PO Box 148 | ||||||||||
| Sabula IA 52070 | Ames IA 50010 | Slater IA 50244 | |||||||||||
| Plan Sets Requested: 4 | Quantities | 563-357-1849 | 515-232-6443 | 515-228-3030 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | MOBILIZATION & DEMOBILIZATION | 1 | L.S. | $53,000.00 | $53,000.00 | $18,500.00 | $18,500.00 | $20,000.00 | $20,000.00 | ||||
| 2 | TRAFFIC CONTROL | 1 | L.S. | $10,000.00 | $10,000.00 | $2,585.00 | $2,585.00 | $2,500.00 | $2,500.00 | ||||
| 3 | SITE PREP & CLEARING | 1 | L.S. | $20,000.00 | $20,000.00 | $60,000.00 | $60,000.00 | $15,500.00 | $15,500.00 | ||||
| 4 | CULVERT REMOVAL & DISPOSAL | 3 | Each | $3,300.00 | $9,900.00 | $500.00 | $1,500.00 | $2,100.00 | $6,300.00 | ||||
| 5 | CULVERT PLUGGING | 1 | Each | $500.00 | $500.00 | $500.00 | $500.00 | $2,000.00 | $2,000.00 | ||||
| 6 | DITCH GRADING | 420 | L.F. | $11.50 | $4,830.00 | $10.00 | $4,200.00 | $24.00 | $10,080.00 | ||||
| 7 | EXCAVATION | 2350 | C.Y. | $14.80 | $34,780.00 | $25.00 | $58,750.00 | $25.00 | $58,750.00 | ||||
| 8 | TOPSOIL IMPORT | 65 | C.Y. | $100.00 | $6,500.00 | $50.00 | $3,250.00 | $85.00 | $5,525.00 | ||||
| 9 | HMA REMOVAL & DISPOSAL | 462 | S.Y. | $18.00 | $8,316.00 | $10.00 | $4,620.00 | $20.00 | $9,240.00 | ||||
| 10 | PCC PAVEMENT (7") | 462 | S.Y. | $190.00 | $87,780.00 | $80.00 | $36,960.00 | $85.00 | $39,270.00 | ||||
| 11 | POROUS BACKFILL | 360 | Tons | $30.00 | $10,800.00 | $33.00 | $11,880.00 | $55.00 | $19,800.00 | ||||
| 12 | CLASS A ROADSTONE | 340 | Tons | $27.50 | $9,350.00 | $33.00 | $11,220.00 | $55.00 | $18,700.00 | ||||
| 13 | CLASS E REVETMENT (BANK STABILIZATION) | 370 | Tons | $49.00 | $18,130.00 | $60.00 | $22,200.00 | $75.00 | $27,750.00 | ||||
| 14 | CLASS E REVETMENT (CHECK DAM) | 120 | Tons | $49.00 | $5,880.00 | $60.00 | $7,200.00 | $105.00 | $12,600.00 | ||||
| 15 | SHOT ROCK (BENCH BACKFILL) | 3870 | Tons | $38.00 | $147,060.00 | $50.00 | $193,500.00 | $50.00 | $193,500.00 | ||||
| 16 | CLASS E REVETMENT (PIPE OUTLET) | 8 | Tons | $60.00 | $480.00 | $60.00 | $480.00 | $310.00 | $2,480.00 | ||||
| 17 | SUBDRAIN, PERFORATED, DUAL WALL HDPE, 6" | 450 | L.F. | $15.00 | $6,750.00 | $20.00 | $9,000.00 | $36.00 | $16,200.00 | ||||
| 18 | STORM SEWER, NON-PERFORATED, DUAL WALL HDPE, 18" | 305 | L.F. | $34.50 | $10,522.50 | $40.00 | $12,200.00 | $47.00 | $14,335.00 | ||||
| 19 | INTAKE, SW-512, 30" | 5 | Each | $2,700.00 | $13,500.00 | $3,500.00 | $17,500.00 | $2,100.00 | $10,500.00 | ||||
| 20 | ANTI-SEEPAGE COLLAR | 3 | Each | $300.00 | $900.00 | $500.00 | $1,500.00 | $200.00 | $600.00 | ||||
| 21 | SEEDING, DITCH MIX | 0.3 | Acres | $6,500.00 | $1,950.00 | $7,150.00 | $2,145.00 | $8,500.00 | $2,550.00 | ||||
| 22 | EROSION CONTROL, 8" WATTLES | 460 | L.F. | $3.75 | $1,725.00 | $2.20 | $1,012.00 | $7.00 | $3,220.00 | ||||
| $462,653.50 | $480,702.00 | $491,400.00 | |||||||||||
10 | 11 | 12 | |||||||||||
| Estimated Cost: $575,000.00 | Contractor: | Heck's Dozer Inc. | |||||||||||
| Funding Source: 100% Park & Institutional Road Fund, | 518 W Sycamore | ||||||||||||
| Ogden IA 50212 | |||||||||||||
| Plan Sets Requested: 4 | Quantities | 515-275-2953 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | MOBILIZATION & DEMOBILIZATION | 1 | L.S. | $12,100.00 | $12,100.00 | $0.00 | $0.00 | ||||||
| 2 | TRAFFIC CONTROL | 1 | L.S. | $27,500.00 | $27,500.00 | $0.00 | $0.00 | ||||||
| 3 | SITE PREP & CLEARING | 1 | L.S. | $65,120.00 | $65,120.00 | $0.00 | $0.00 | ||||||
| 4 | CULVERT REMOVAL & DISPOSAL | 3 | Each | $2,647.34 | $7,942.02 | $0.00 | $0.00 | ||||||
| 5 | CULVERT PLUGGING | 1 | Each | $1,364.00 | $1,364.00 | $0.00 | $0.00 | ||||||
| 6 | DITCH GRADING | 420 | L.F. | $17.60 | $7,392.00 | $0.00 | $0.00 | ||||||
| 7 | EXCAVATION | 2350 | C.Y. | $31.99 | $75,176.50 | $0.00 | $0.00 | ||||||
| 8 | TOPSOIL IMPORT | 65 | C.Y. | $35.20 | $2,288.00 | $0.00 | $0.00 | ||||||
| 9 | HMA REMOVAL & DISPOSAL | 462 | S.Y. | $80.76 | $37,311.12 | $0.00 | $0.00 | ||||||
| 10 | PCC PAVEMENT (7") | 462 | S.Y. | $123.81 | $57,200.22 | $0.00 | $0.00 | ||||||
| 11 | POROUS BACKFILL | 360 | Tons | $67.03 | $24,130.80 | $0.00 | $0.00 | ||||||
| 12 | CLASS A ROADSTONE | 340 | Tons | $47.62 | $16,190.80 | $0.00 | $0.00 | ||||||
| 13 | CLASS E REVETMENT (BANK STABILIZATION) | 370 | Tons | $170.89 | $63,229.30 | $0.00 | $0.00 | ||||||
| 14 | CLASS E REVETMENT (CHECK DAM) | 120 | Tons | $392.70 | $47,124.00 | $0.00 | $0.00 | ||||||
| 15 | SHOT ROCK (BENCH BACKFILL) | 3870 | Tons | $50.35 | $194,854.50 | $0.00 | $0.00 | ||||||
| 16 | CLASS E REVETMENT (PIPE OUTLET) | 8 | Tons | $161.15 | $1,289.20 | $0.00 | $0.00 | ||||||
| 17 | SUBDRAIN, PERFORATED, DUAL WALL HDPE, 6" | 450 | L.F. | $33.20 | $14,940.00 | $0.00 | $0.00 | ||||||
| 18 | STORM SEWER, NON-PERFORATED, DUAL WALL HDPE, 18" | 305 | L.F. | $57.42 | $17,513.10 | $0.00 | $0.00 | ||||||
| 19 | INTAKE, SW-512, 30" | 5 | Each | $3,841.20 | $19,206.00 | $0.00 | $0.00 | ||||||
| 20 | ANTI-SEEPAGE COLLAR | 3 | Each | $1,074.34 | $3,223.02 | $0.00 | $0.00 | ||||||
| 21 | SEEDING, DITCH MIX | 0.3 | Acres | $18,333.34 | $5,500.002 | $0.00 | $0.00 | ||||||
| 22 | EROSION CONTROL, 8" WATTLES | 460 | L.F. | $3.34 | $1,536.40 | $0.00 | $0.00 | ||||||
| $702,130.982 | $0.00 | $0.00 | |||||||||||