IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Stephens Forest Headquarters | Date: 5/3/2018 | Project No. |
| Driveway Replacement | County: | LUCAS | Time: 3:00 p.m. | 18-05-59-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $12,530.00 | Contractor: | Wright Build | Day Construction Services LLC | Mcgee Concrete, LLC | |||||||||
| Funding Source: 100% REAP OS Acquisition & Development, | 2701 Franklin Ave | 1721 Taylor Ave | 219 N Fryer St | ||||||||||
| Des Moines IA 50310 | Marshalltown IA 50158 | Russell IA 50238 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 5153213708 | 641-751-8419 | 641-203-0721 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $485.00 | $485.00 | $1,000.00 | $1,000.00 | $500.00 | $500.00 | ||||
| 2 | Concrete Demolition | 68 | S.Y. | $23.00 | $1,564.00 | $9.00 | $612.00 | $22.06 | $1,500.08 | ||||
| 3 | 6" Concrete, C4 Mix, with Reinforcement | 92 | S.Y. | $69.00 | $6,348.00 | $80.00 | $7,360.00 | $70.66 | $6,500.72 | ||||
| 4 | Class "A" Crushed Stone | 20 | Tons | $30.00 | $600.00 | $20.00 | $400.00 | $42.50 | $850.00 | ||||
| 5 | Core out and dispose base | 15 | C.Y. | $44.00 | $660.00 | $20.00 | $300.00 | $46.67 | $700.05 | ||||
| $9,657.00 | $9,672.00 | $10,050.85 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $12,530.00 | Contractor: | Hymbaugh Construction | TK Concrete, Inc. | ||||||||||
| Funding Source: 100% REAP OS Acquisition & Development, | 821 Quiet Harbor | 1608 Fifield Rd | |||||||||||
| Creston IA 50801 | Pella IA 50219 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 6413400232 | 641-628-4590 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $2,000.00 | $2,000.00 | $2,875.00 | $2,875.00 | $0.00 | |||||
| 2 | Concrete Demolition | 68 | S.Y. | $20.00 | $1,360.00 | $15.00 | $1,020.00 | $0.00 | |||||
| 3 | 6" Concrete, C4 Mix, with Reinforcement | 92 | S.Y. | $60.00 | $5,520.00 | $65.00 | $5,980.00 | $0.00 | |||||
| 4 | Class "A" Crushed Stone | 20 | Tons | $40.00 | $800.00 | $30.00 | $600.00 | $0.00 | |||||
| 5 | Core out and dispose base | 15 | C.Y. | $60.00 | $900.00 | $30.00 | $450.00 | $0.00 | |||||
| $10,580.00 | $10,925.00 | $0.00 | |||||||||||
12/20/2025