IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Lacey-Keosauqua State Park | Date: 11/15/2018 | Project No. |
Campground Road Seal Coat | County: | VAN BUREN | Time: 11:00 a.m. | 18-06-89-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $160,000.00 | Contractor: | L L Pelling Company Inc | Fahrner Asphalt Sealers LLC | Meyers Driveway | |||||||||
Funding Source: 100% Park & Institutional Road Fund, | 1425 W Penn St Box 230 | 7680 Commerce Park Section C | 1000 Cedar Street | ||||||||||
North Liberty IA 523170230 | Dubuque IA 52002 | Keokuk IA 52132 | |||||||||||
Plan Sets Requested: 1 | Quantities | (319) 626-4600 | 563-556-6231 | 319-524-7329 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | 1/2" Crushed Stone | 269 | Tons | $59.00 | $15,871.00 | $70.00 | $18,830.00 | $150.00 | $40,350.00 | ||||
2 | Binder Bitumen | 6113 | GAL. | $3.35 | $20,478.55 | $9.00 | $55,017.00 | $12.00 | $73,356.00 | ||||
3 | Traffic Control | 1 | L.S. | $2,950.00 | $2,950.00 | $5,000.00 | $5,000.00 | $23,147.00 | $23,147.00 | ||||
4 | Mobilization | 1 | L.S. | $11,850.00 | $11,850.00 | $29,000.00 | $29,000.00 | $23,147.00 | $23,147.00 | ||||
$51,149.55 | $107,847.00 | $160,000.00 | |||||||||||
Alternate | |||||||||||||
5 | Full Depth HMA Patch, By Count | 1 | Each | $1,775.00 | $1,775.00 | $6,500.00 | $6,500.00 | $0.00 | $0.00 | ||||
Alternate | |||||||||||||
6 | Full Depth HMA Patch, By Area | 64 | S.Y. | $105.00 | $6,720.00 | $250.00 | $16,000.00 | $135.00 | $8,640.00 | ||||
Alternate | |||||||||||||
7 | 15" Dia. CMP | 50 | L.F. | $62.50 | $3,125.00 | $200.00 | $10,000.00 | $100.00 | $5,000.00 | ||||
Alternate | |||||||||||||
8 | CMP Apron | 2 | Each | $530.00 | $1,060.00 | $2,000.00 | $4,000.00 | $2,000.00 | $4,000.00 | ||||
$63,829.55 | $144,347.00 | $177,640.00 | |||||||||||