| Bids For: | Location: | Indian Bluffs WMA | Date: 4/16/2020 | Project No. |
| Road Maintenance | County: | JONES | Time: 11:00 a.m. | 18-06-53-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $130,000.00 | Contractor: | Connolly Construction Inc. | Ardo Schmidt Construction, Inc. | H & H Construction & Development LLC | |||||||||
| Funding Source: 100% Park & Institutional Road Fund, | 18409 N Cascade Rd | 35010 Hwy 64 | 60559 Hwy 64 | ||||||||||
| Peosta IA | Preston IA 52069 | Sabula IA 52070 | |||||||||||
| Plan Sets Requested: 9 | Quantities | 5638763225 | 5636894875 | 5633571849 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 2101 - CLEARING/GRUBBING | 1 | L.S. | $4,800.00 | $4,800.00 | $10,000.00 | $10,000.00 | $15,000.00 | $15,000.00 | ||||
| 2 | 2102 - EXCAVATION, CL 10, RDWY+BORROW | 35 | C.Y. | $8.35 | $292.25 | $12.00 | $420.00 | $20.00 | $700.00 | ||||
| 3 | 2102 - EXCAVATION, CL 12, BOULDER/ROCK FRAGMENT | 72 | C.Y. | $27.00 | $1,944.00 | $18.00 | $1,296.00 | $20.00 | $1,440.00 | ||||
| 4 | 2125 - RESHAPING/CLEANING DITCHES | 35.7 | STA. | $640.00 | $22,848.00 | $420.16 | $14,999.712 | $145.00 | $5,176.50 | ||||
| 5 | 2127 - RECONSTRUCTION OF ROADBED - BLADING/SHAPING | 29.5 | STA. | $155.00 | $4,572.50 | $200.00 | $5,900.00 | $271.20 | $8,000.40 | ||||
| 6 | 2127 - RECONSTRUCTION OF ROADBED - MOVING ROAD | 6.2 | STA. | $1,450.00 | $8,990.00 | $500.00 | $3,100.00 | $187.50 | $1,162.50 | ||||
| 7 | 2312 - GRANULAR SURFACING ON ROAD, CLASS A CRUSHED STONE | 1363 | Tons | $18.90 | $25,760.70 | $19.75 | $26,919.25 | $23.80 | $32,439.40 | ||||
| 8 | 2312 - GRANULAR SURFACING ON ROAD, MACADAM STONE | 210 | Tons | $24.25 | $5,092.50 | $22.55 | $4,735.50 | $26.05 | $5,470.50 | ||||
| 9 | 2507 - EROSION STONE - DITCH CHECKS | 119 | Tons | $25.70 | $3,058.30 | $46.60 | $5,545.40 | $42.85 | $5,099.15 | ||||
| 10 | 2507 - EROSION STONE - OUTLETS | 30 | Tons | $25.70 | $771.00 | $28.00 | $840.00 | $35.00 | $1,050.00 | ||||
| 11 | 2518 - SAFETY CLOSURE | 2 | Each | $600.00 | $1,200.00 | $500.00 | $1,000.00 | $750.00 | $1,500.00 | ||||
| 12 | 2533 - MOBILIZATION | 1 | L.S. | $5,600.00 | $5,600.00 | $14,900.00 | $14,900.00 | $16,974.50 | $16,974.50 | ||||
| 13 | 2601 - STABILIZE CROP - SEED+FERTILIZE | 2.4 | Acres | $2,345.00 | $5,628.00 | $2,200.00 | $5,280.00 | $2,750.00 | $6,600.00 | ||||
| $90,557.25 | $94,935.862 | $100,612.95 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $130,000.00 | Contractor: | Steger Const Inc. | David Ryan Construction | Eastern Iowa Excavating & Concrete, LLC | |||||||||
| Funding Source: 100% Park & Institutional Road Fund, | 3297 Vine Rd | 3566 236th Ave | 121 Nixon St SE | ||||||||||
| Dyersville IA 52040 | Decorah IA 52101 | Cascade IA 52033 | |||||||||||
| Plan Sets Requested: 9 | Quantities | 5638757876 | 5633801365 | 5638525120 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 2101 - CLEARING/GRUBBING | 1 | L.S. | $14,000.00 | $14,000.00 | $3,000.00 | $3,000.00 | $5,650.00 | $5,650.00 | ||||
| 2 | 2102 - EXCAVATION, CL 10, RDWY+BORROW | 35 | C.Y. | $16.40 | $574.00 | $10.00 | $350.00 | $109.00 | $3,815.00 | ||||
| 3 | 2102 - EXCAVATION, CL 12, BOULDER/ROCK FRAGMENT | 72 | C.Y. | $36.00 | $2,592.00 | $80.00 | $5,760.00 | $46.25 | $3,330.00 | ||||
| 4 | 2125 - RESHAPING/CLEANING DITCHES | 35.7 | STA. | $1,115.00 | $39,805.50 | $1,000.00 | $35,700.00 | $900.00 | $32,130.00 | ||||
| 5 | 2127 - RECONSTRUCTION OF ROADBED - BLADING/SHAPING | 29.5 | STA. | $140.00 | $4,130.00 | $500.00 | $14,750.00 | $102.50 | $3,023.75 | ||||
| 6 | 2127 - RECONSTRUCTION OF ROADBED - MOVING ROAD | 6.2 | STA. | $680.00 | $4,216.00 | $1,000.00 | $6,200.00 | $1,665.00 | $10,323.00 | ||||
| 7 | 2312 - GRANULAR SURFACING ON ROAD, CLASS A CRUSHED STONE | 1363 | Tons | $16.80 | $22,898.40 | $19.00 | $25,897.00 | $20.50 | $27,941.50 | ||||
| 8 | 2312 - GRANULAR SURFACING ON ROAD, MACADAM STONE | 210 | Tons | $19.00 | $3,990.00 | $25.00 | $5,250.00 | $22.25 | $4,672.50 | ||||
| 9 | 2507 - EROSION STONE - DITCH CHECKS | 119 | Tons | $43.45 | $5,170.55 | $35.00 | $4,165.00 | $52.25 | $6,217.75 | ||||
| 10 | 2507 - EROSION STONE - OUTLETS | 30 | Tons | $43.45 | $1,303.50 | $30.00 | $900.00 | $46.50 | $1,395.00 | ||||
| 11 | 2518 - SAFETY CLOSURE | 2 | Each | $150.00 | $300.00 | $750.00 | $1,500.00 | $500.00 | $1,000.00 | ||||
| 12 | 2533 - MOBILIZATION | 1 | L.S. | $5,500.00 | $5,500.00 | $2,000.00 | $2,000.00 | $5,500.00 | $5,500.00 | ||||
| 13 | 2601 - STABILIZE CROP - SEED+FERTILIZE | 2.4 | Acres | $1,700.00 | $4,080.00 | $1,500.00 | $3,600.00 | $4,250.00 | $10,200.00 | ||||
| $108,559.95 | $109,072.00 | $115,198.50 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $130,000.00 | Contractor: | Boomerang Corp | Miller Trucking & Excavating | Tschiggfrie Exc Co. | |||||||||
| Funding Source: 100% Park & Institutional Road Fund, | 12536 Buffalo Rd | 3303 John Deere Road | 425 Julien Dubuque Dr | ||||||||||
| Anamosa IA 52205 | Silvis IL 61282 | Dubuque IA 52003 | |||||||||||
| Plan Sets Requested: 9 | Quantities | 3194624435 | 3097557644 | 5635577450 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | 2101 - CLEARING/GRUBBING | 1 | L.S. | $20,000.00 | $20,000.00 | $10,000.00 | $10,000.00 | $9,500.00 | $9,500.00 | ||||
| 2 | 2102 - EXCAVATION, CL 10, RDWY+BORROW | 35 | C.Y. | $60.00 | $2,100.00 | $40.00 | $1,400.00 | $40.00 | $1,400.00 | ||||
| 3 | 2102 - EXCAVATION, CL 12, BOULDER/ROCK FRAGMENT | 72 | C.Y. | $60.00 | $4,320.00 | $60.00 | $4,320.00 | $110.00 | $7,920.00 | ||||
| 4 | 2125 - RESHAPING/CLEANING DITCHES | 35.7 | STA. | $300.00 | $10,710.00 | $1,500.00 | $53,550.00 | $980.00 | $34,986.00 | ||||
| 5 | 2127 - RECONSTRUCTION OF ROADBED - BLADING/SHAPING | 29.5 | STA. | $300.00 | $8,850.00 | $315.00 | $9,292.50 | $590.00 | $17,405.00 | ||||
| 6 | 2127 - RECONSTRUCTION OF ROADBED - MOVING ROAD | 6.2 | STA. | $1,300.00 | $8,060.00 | $1,200.00 | $7,440.00 | $1,400.00 | $8,680.00 | ||||
| 7 | 2312 - GRANULAR SURFACING ON ROAD, CLASS A CRUSHED STONE | 1363 | Tons | $25.00 | $34,075.00 | $25.00 | $34,075.00 | $29.00 | $39,527.00 | ||||
| 8 | 2312 - GRANULAR SURFACING ON ROAD, MACADAM STONE | 210 | Tons | $25.00 | $5,250.00 | $45.00 | $9,450.00 | $32.00 | $6,720.00 | ||||
| 9 | 2507 - EROSION STONE - DITCH CHECKS | 119 | Tons | $80.00 | $9,520.00 | $90.00 | $10,710.00 | $36.00 | $4,284.00 | ||||
| 10 | 2507 - EROSION STONE - OUTLETS | 30 | Tons | $80.00 | $2,400.00 | $70.00 | $2,100.00 | $55.00 | $1,650.00 | ||||
| 11 | 2518 - SAFETY CLOSURE | 2 | Each | $250.00 | $500.00 | $250.00 | $500.00 | $700.00 | $1,400.00 | ||||
| 12 | 2533 - MOBILIZATION | 1 | L.S. | $20,000.00 | $20,000.00 | $10,200.00 | $10,200.00 | $13,500.00 | $13,500.00 | ||||
| 13 | 2601 - STABILIZE CROP - SEED+FERTILIZE | 2.4 | Acres | $3,000.00 | $7,200.00 | $2,500.00 | $6,000.00 | $7,500.00 | $18,000.00 | ||||
| $132,985.00 | $159,037.50 | $164,972.00 | |||||||||||
David Ryan Construction, Decorah, IA