IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Geode State Park | Date: 6/15/2017 | Project No. |
CCC SHELTER RESTORATION (REBID) | County: | HENRY | Time: 11:00 a.m. | 17-06-44-04 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $89,875.00 | Contractor: | MTS Contracting Inc | Hymbaugh Construction | ||||||||||
Funding Source: 100% Infrastructure 2017, | 6950 NE 14th St, Ste 30 | 821 Quiet Harbor | |||||||||||
Ankeny IA 50023 | Creston IA 50801 | ||||||||||||
Plan Sets Requested: 3 | Quantities | 515-289-7500 | 641-340-0232 | ||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | DEMOLITION | 1 | L.S. | $11,500.00 | $11,500.00 | $12,000.00 | $12,000.00 | $0.00 | |||||
2 | CCC SHELTER RESTORATION | 1 | L.S. | $77,000.00 | $77,000.00 | $110,000.00 | $110,000.00 | $0.00 | |||||
3 | FIREBOX REPLACEMENT | 2 | Each | $2,000.00 | $4,000.00 | $2,000.00 | $4,000.00 | $0.00 | |||||
4 | 6" PCC REINFORCED SLAB | 790 | S.F. | $13.924 | $10,999.96 | $11.00 | $8,690.00 | $0.00 | |||||
5 | MOBILIZATION | 1 | L.S. | $15,000.00 | $15,000.00 | $12,000.00 | $12,000.00 | $0.00 | |||||
$118,499.96 | $146,690.00 | $0.00 | |||||||||||
5/5/2024