IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Lake Darling State Park | Date: 8/10/2017 | Project No. |
| Pedestrian Bridge Abutments and Approaches | County: | WASHINGTON | Time: 11:00 a.m. | 18-06-92-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $44,000.00 | Contractor: | Iowa Bridge & Culvert LC | Ricklefs Excavating Ltd | Taylor Construction, Inc. | |||||||||
| Funding Source: 100% Other, | 409 N Ave B PO Box 13 | 12536 Buffalo Road | 7314 Columbus Street Box 110 | ||||||||||
| Washington IA 52353 | Anamosa IA 52205 | New Vienna IA 52065 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 319-653-5436 | 319-462-4435 | 563-921-2315 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $15,000.00 | $15,000.00 | $26,000.00 | $26,000.00 | $44,000.00 | $44,000.00 | ||||
| 2 | Construction Survey | 1 | L.S. | $2,500.00 | $2,500.00 | $500.00 | $500.00 | $2,000.00 | $2,000.00 | ||||
| 3 | Abutments, Cast-In-Place PCC | 2 | Each | $15,000.00 | $30,000.00 | $15,000.00 | $30,000.00 | $12,000.00 | $24,000.00 | ||||
| 4 | Bridge Assembly and Placement | 1 | L.S. | $20,000.00 | $20,000.00 | $60,000.00 | $60,000.00 | $20,000.00 | $20,000.00 | ||||
| 5 | Borrow | 160 | C.Y. | $25.00 | $4,000.00 | $10.00 | $1,600.00 | $54.00 | $8,640.00 | ||||
| 6 | Granular Backfill | 45 | Tons | $45.00 | $2,025.00 | $16.00 | $720.00 | $45.00 | $2,025.00 | ||||
| 7 | 3/8 Minus Surfacing | 30 | Tons | $65.00 | $1,950.00 | $16.00 | $480.00 | $67.00 | $2,010.00 | ||||
| 8 | Site Restoration | 1 | L.S. | $7,500.00 | $7,500.00 | $3,500.00 | $3,500.00 | $21,000.00 | $21,000.00 | ||||
| $82,975.00 | $122,800.00 | $123,675.00 | |||||||||||
| Alternate | |||||||||||||
| 9 | Revetment, Class "E" – Alternate 1 | 100 | Tons | $50.00 | $5,000.00 | $40.00 | $4,000.00 | $40.00 | $4,000.00 | ||||
| Alternate | |||||||||||||
| 10 | Engineering Fabric – Alternate 1 | 56 | S.Y. | $2.00 | $112.00 | $1.00 | $56.00 | $2.00 | $112.00 | ||||
| Alternate | |||||||||||||
| 11 | Removable Bollards – Alternate 2 | 2 | Each | $1,000.00 | $2,000.00 | $800.00 | $1,600.00 | $1,100.00 | $2,200.00 | ||||
| $90,087.00 | $128,456.00 | $129,987.00 | |||||||||||
4/2/2026