IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Yellow River State Forest  Date: 5/25/2017  Project No.  
  Pavement Repairs(duplicate)  County:   ALLAMAKEE  Time: 3:00 p.m.  17-03-03-03

 

 
1
2
3
Estimated Cost: $22,000.00
Contractor: 
Skyline Construction, Inc.Lansing Brothers ConstructionMatt Construction, Inc.
Funding Source: 98% Park & Institutional Road Fund, 2% REAP Land Management, 900 Montgomery St
101 East 1st St
203 Y Ave
Decorah IA  52101Luxemburg IA  52056Sumner IA  50674
Plan Sets Requested: 0
Quantities
563-382-2933563-543-7360563-578-8418
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
12102- Special Backfill39Tons$30.00$1,170.00 $30.00$1,170.00 $20.00$780.00 
22102- Excavation, Class 10, Roadway24C.Y.$6.66$159.84 $20.00$480.00 $20.00$480.00 
32113- Subgrade Stabilization Material, Polmer Grid143S.Y.$3.33$476.19 $4.00$572.00 $3.00$429.00 
42528- Traffic Control1L.S.$450.00$450.00 $650.00$650.00 $200.00$200.00 
52529- PCC Patches, Full Depth Finish, By Area, Class M143S.Y.$66.66$9,532.38 $70.00$10,010.00 $60.00$8,580.00 
62533- Mobilization1L.S.$2,201.00$2,201.00 $2,800.00$2,800.00 $6,000.00$6,000.00 
      $13,989.41  $15,682.00  $16,469.00 
 
 
4
5
6
Estimated Cost: $22,000.00
Contractor: 
Cornwell Construction and ExcavationDavid Ryan ConstructionBurr Oak Springs
Funding Source: 98% Park & Institutional Road Fund, 2% REAP Land Management, 1678 Rabbit Run
3566 236th Ave
2113 Co. Rd. 114
Harpers Ferry IA  52146Decorah IA  52101Ridgeway IA  52065
Plan Sets Requested: 0
Quantities
563-535-7058563-380-1365563-737-2510
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
12102- Special Backfill39Tons$20.00$780.00 $18.00$702.00 $30.00$1,170.00 
22102- Excavation, Class 10, Roadway24C.Y.$215.50$5,172.00 $7.50$180.00 $30.00$720.00 
32113- Subgrade Stabilization Material, Polmer Grid143S.Y.$6.00$858.00 $4.90$700.70 $8.00$1,144.00 
42528- Traffic Control1L.S.$500.00$500.00 $300.00$300.00 $1,000.00$1,000.00 
52529- PCC Patches, Full Depth Finish, By Area, Class M143S.Y.$60.00$8,580.00 $110.00$15,730.00 $75.00$10,725.00 
62533- Mobilization1L.S.$1,000.00$1,000.00 $500.00$500.00 $4,000.00$4,000.00 
      $16,890.00  $18,112.70  $18,759.00 
 
7
8
9
Estimated Cost: $22,000.00
Contractor: 
Croell, Inc.American Pavement Solutions
Funding Source: 98% Park & Institutional Road Fund, 2% REAP Land Management, 2010 Kenwood Ave
1455 Gruber Rd

New Hampton IA  50659Green Bay WI  54313  
Plan Sets Requested: 0
Quantities
641-394-6789920-662-9662
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
12102- Special Backfill39Tons$20.00$780.00 $50.00$1,950.00 $0.00 
22102- Excavation, Class 10, Roadway24C.Y.$20.00$480.00 $75.00$1,800.00 $0.00 
32113- Subgrade Stabilization Material, Polmer Grid143S.Y.$5.00$715.00 $10.00$1,430.00 $0.00 
42528- Traffic Control1L.S.$1,500.00$1,500.00 $1,000.00$1,000.00 $0.00 
52529- PCC Patches, Full Depth Finish, By Area, Class M143S.Y.$98.00$14,014.00 $168.00$24,024.00 $0.00 
62533- Mobilization1L.S.$3,000.00$3,000.00 $9,000.00$9,000.00 $0.00 
      $20,489.00  $39,204.00  $0.00 
 



 