IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Yellow River State Forest | Date: 5/25/2017 | Project No. |
Pavement Repairs(duplicate) | County: | ALLAMAKEE | Time: 3:00 p.m. | 17-03-03-03 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $22,000.00 | Contractor: | Skyline Construction, Inc. | Lansing Brothers Construction | Matt Construction, Inc. | |||||||||
Funding Source: 98% Park & Institutional Road Fund, 2% REAP Land Management, | 900 Montgomery St | 101 East 1st St | 203 Y Ave | ||||||||||
Decorah IA 52101 | Luxemburg IA 52056 | Sumner IA 50674 | |||||||||||
Plan Sets Requested: 0 | Quantities | 563-382-2933 | 563-543-7360 | 563-578-8418 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | 2102- Special Backfill | 39 | Tons | $30.00 | $1,170.00 | $30.00 | $1,170.00 | $20.00 | $780.00 | ||||
2 | 2102- Excavation, Class 10, Roadway | 24 | C.Y. | $6.66 | $159.84 | $20.00 | $480.00 | $20.00 | $480.00 | ||||
3 | 2113- Subgrade Stabilization Material, Polmer Grid | 143 | S.Y. | $3.33 | $476.19 | $4.00 | $572.00 | $3.00 | $429.00 | ||||
4 | 2528- Traffic Control | 1 | L.S. | $450.00 | $450.00 | $650.00 | $650.00 | $200.00 | $200.00 | ||||
5 | 2529- PCC Patches, Full Depth Finish, By Area, Class M | 143 | S.Y. | $66.66 | $9,532.38 | $70.00 | $10,010.00 | $60.00 | $8,580.00 | ||||
6 | 2533- Mobilization | 1 | L.S. | $2,201.00 | $2,201.00 | $2,800.00 | $2,800.00 | $6,000.00 | $6,000.00 | ||||
$13,989.41 | $15,682.00 | $16,469.00 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $22,000.00 | Contractor: | Cornwell Construction and Excavation | David Ryan Construction | Burr Oak Springs | |||||||||
Funding Source: 98% Park & Institutional Road Fund, 2% REAP Land Management, | 1678 Rabbit Run | 3566 236th Ave | 2113 Co. Rd. 114 | ||||||||||
Harpers Ferry IA 52146 | Decorah IA 52101 | Ridgeway IA 52065 | |||||||||||
Plan Sets Requested: 0 | Quantities | 563-535-7058 | 563-380-1365 | 563-737-2510 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | 2102- Special Backfill | 39 | Tons | $20.00 | $780.00 | $18.00 | $702.00 | $30.00 | $1,170.00 | ||||
2 | 2102- Excavation, Class 10, Roadway | 24 | C.Y. | $215.50 | $5,172.00 | $7.50 | $180.00 | $30.00 | $720.00 | ||||
3 | 2113- Subgrade Stabilization Material, Polmer Grid | 143 | S.Y. | $6.00 | $858.00 | $4.90 | $700.70 | $8.00 | $1,144.00 | ||||
4 | 2528- Traffic Control | 1 | L.S. | $500.00 | $500.00 | $300.00 | $300.00 | $1,000.00 | $1,000.00 | ||||
5 | 2529- PCC Patches, Full Depth Finish, By Area, Class M | 143 | S.Y. | $60.00 | $8,580.00 | $110.00 | $15,730.00 | $75.00 | $10,725.00 | ||||
6 | 2533- Mobilization | 1 | L.S. | $1,000.00 | $1,000.00 | $500.00 | $500.00 | $4,000.00 | $4,000.00 | ||||
$16,890.00 | $18,112.70 | $18,759.00 | |||||||||||
7 | 8 | 9 | |||||||||||
Estimated Cost: $22,000.00 | Contractor: | Croell, Inc. | American Pavement Solutions | ||||||||||
Funding Source: 98% Park & Institutional Road Fund, 2% REAP Land Management, | 2010 Kenwood Ave | 1455 Gruber Rd | |||||||||||
New Hampton IA 50659 | Green Bay WI 54313 | ||||||||||||
Plan Sets Requested: 0 | Quantities | 641-394-6789 | 920-662-9662 | ||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | 2102- Special Backfill | 39 | Tons | $20.00 | $780.00 | $50.00 | $1,950.00 | $0.00 | |||||
2 | 2102- Excavation, Class 10, Roadway | 24 | C.Y. | $20.00 | $480.00 | $75.00 | $1,800.00 | $0.00 | |||||
3 | 2113- Subgrade Stabilization Material, Polmer Grid | 143 | S.Y. | $5.00 | $715.00 | $10.00 | $1,430.00 | $0.00 | |||||
4 | 2528- Traffic Control | 1 | L.S. | $1,500.00 | $1,500.00 | $1,000.00 | $1,000.00 | $0.00 | |||||
5 | 2529- PCC Patches, Full Depth Finish, By Area, Class M | 143 | S.Y. | $98.00 | $14,014.00 | $168.00 | $24,024.00 | $0.00 | |||||
6 | 2533- Mobilization | 1 | L.S. | $3,000.00 | $3,000.00 | $9,000.00 | $9,000.00 | $0.00 | |||||
$20,489.00 | $39,204.00 | $0.00 | |||||||||||
5/1/2024